Chapter 5 - Development of a Proposed National Science Centre
The committee examined the long-running National Children’s Science Centre project, focusing on how the State became tied to a costly commitment without a proper sponsoring Department, business case or public spending appraisal. The Comptroller and Auditor General said the OPW entered agreements too early, leading to a contingent liability now estimated at about €70 million, while OPW officials accepted key governance failings and said no funding source or parent Department has yet been identified. ICML argued the project remains important for science education and said it has planning permission, a draft business plan and a commitment to raise €25 million privately for fit-out. Several deputies criticised the project as poorly governed and asked whether it should proceed, partner with other centres, or be reconsidered, but no clear delivery path emerged.
This morning we will engage with the National Children's Science Centre to examine the Comptroller and Auditor General's report on the accounts of public services 2024 - chapter 5, development of a proposed national science centre. On behalf of the committee, I welcome Ms Barbara Galavan, chief executive officer, Professor Luke O'Neill, board director, and Mr. Paschal Naylor, chairperson. We are also joined by officials attending in a representative capacity from the Office of Public Works, OPW, Mr. John Conlon, chairperson, Mr. Conor Sreenan, State principal architect, and Ms Kathryn Whyte, head of organisational capability and corporate services; and from the Department of Public Expenditure, Infrastructure, Public Service Reform and Digitalisation Mr. Fionn Jenkinson, principal officer, and Mr. Andrew Gray, assistant principal officer. We are also joined by the Comptroller and Auditor General, Mr. Seamus McCarthy, who is a permanent witness to the committee, and Ms Sinéad Foy, deputy director of audit in his office. They are all very welcome.
Before we begin, I will explain some limitations to parliamentary privilege and the practice of the Houses as regards references the witnesses may make to other persons in their evidence. The evidence of witnesses physically present, or who give evidence from within the parliamentary precincts, is protected pursuant to both the Constitution and statute by absolute privilege. This means they have an absolute defence against any defamation action for anything they say at the meeting. However, they are expected not to abuse this privilege and it is my duty as Cathaoirleach to ensure that this privilege is not abused. Therefore, if their statements are potentially defamatory in relation to an identifiable person or entity, they will be directed to discontinue their remarks and it is imperative that they comply with any such direction. Witnesses are also reminded of the long-standing parliamentary practice that they should not criticise or make charges against any person or entity, by name or in such a way as to make him, her or it identifiable, or otherwise engage in speech that might be regarded as damaging to the good name of the person or entity.
I now call on the Comptroller and Auditor General, Mr. Seamus McCarthy, to make his opening statement.
Comment on this
Gabhaim buíochas leis an gCathaoirleach. Chapter 5 of my report on the accounts of the public services for 2024 reviews the development of a proposed national science centre, which has resulted in a contingent liability disclosed in the appropriation account of Vote 13 - Office of Public Works.
The OPW's original concept of the project was a perceived no-direct-cost initiative to develop the science centre as the key cultural component of a proposed major mixed-use development at Heuston Gate in Dublin. The initial 2003 agreement for leasing between the OPW and the centre's promoters was for the provision for 20 years of a building of 4,645 sq. m, with the promoters taking responsibility for the fit-out and exhibits and the recurrent operating costs. The Heuston Gate property development did not proceed and was abandoned following the 2008 property-related crash. In 2013, the OPW and the promoters entered a replacement agreement for the lease, committing the OPW to provide a building of 9,580 sq m. at Earlsfort Terrace, more than double the original size and on a more valuable and sensitive site.
Poor cost estimates of the State's liability in respect of the agreement were provided at different stages in the development. In May 2024, the construction costs to be borne by the State stood at an estimated €70.4 million, with potential for further increases. The examination found that the proposed science centre project has never been evaluated or appraised in accordance with the requirements of the public spending code or other applicable capital expenditure guidelines. Furthermore, we found that, because no public body has emerged to act as the sponsoring agency for the project, key controls designed to safeguard public funds were not applied to the science centre project. With no approved business case for the project objectively setting out and evaluating the costs, operating model and key business risks, the agreements for lease entered into by the OPW represent a premature commitment of significant, unquantified taxpayer resources.
The lessons from the examination focused on the need for robust project governance and safeguards to prevent and manage project scope drift and cost overruns. These learnings were accepted by the Accounting Officer for the OPW. There are also lessons in this case for the broader public sector about the absolute need to avoid granting premature contractual commitments to spending proposals.
Comment on this
I thank Mr. McCarthy. I now ask the chief executive officer, Ms Galavan, and board member Professor Luke O'Neill to make their opening statement on behalf of the National Children's Science Centre. As set out in the letter of invitation, they have five minutes.
Comment on this
I thank the Cathaoirleach and members of the committee for the invitation to discuss the development of a proposed national children's science centre. I am the chief executive officer of Irish Children’s Museum Limited, ICML, which trades as the National Children’s Science Centre, NCSC. I am joined today by Mr. Paschal Naylor, chair of the board, and Professor Luke O’Neill, who is a member of the board.
ICML is a not-for-profit company and a registered charity. Our board is voluntary and ICML has two part-time staff, of whom I am one. We welcome the opportunity to come before the public accounts committee to discuss this critically important project for Ireland.
ICML was established in 1998 by a group of people inspired by children’s science museums they had seen outside Ireland. In 2000, at the request of the then Tánaiste and Minister for Enterprise, Trade and Employment, a task force reporting to Forfás, the agency tasked with advising the Government on economic policy, recommended the establishment of such a facility. The Government adopted this recommendation, which ultimately led to the 2003 agreement between ICML and the OPW. The scope for the project evolved over the years at the request of the Government in order to align with Government policy and ambition. The delays that have regrettably beset the project in the intervening period are set out in chapter 5 of the C and AG’s report published last November and the result is that Ireland remains the only OECD country without a national science centre for children.
Full planning permission was granted for the design of the science centre at Earlsfort Terrace in Dublin 2 in 2016 and again in 2024. The plans feature 9,580 sq. m of public exhibition, event and programmable spaces. These include three floors of interactive exhibits, a 122-seater planetarium, a theatre and fully equipped science laboratory spaces.
This is the same site on which the National Concert Hall is located. The National Concert Hall also received planning permission in 2024, and phase I of its redevelopment works has already begun.
Locating the National Children's Science Centre at Earlsfort Terrace returns part of the building to its original purpose as an exhibition space. It acknowledges its long history with education, and provides a dedicated visitor attraction for children in the capital. Most important, it provides strong opportunities to embrace the science, technology, engineering, arts and maths, STEAM, framework. By integrating arts into science, it recognises that creativity drives innovation.
ICML has committed to raising €25 million for the fit-out of the science centre, which will be gifted to the State for the benefit of children. This has been made possible due to the ongoing strong philanthropic support for the project from leaders and employers in technology and science. They see the need for the project and are willing to back it financially. A report on the future of STEM in Irish education, produced in 2023 by the joint Oireachtas committee on education and youth, validated that need, stating “The National Children’s Science Centre, in gestation for many years, should be opened as a matter of urgent national priority ” We agree with this conclusion and that of the Comptroller and Auditor General's report that identified the lack of a sponsoring Department as the reason for a lack of progress on the project.
At this point, I would like to hand over to Professor Luke O'Neill.
Comment on this
I am grateful for the invitation. We are very happy to be here. I am chair of biochemistry in Trinity College Dublin. I was asked in 2022 to join the board and I jumped at the chance. I am very keen on this project for many reasons I will explain. It is an essential project for Ireland, its young people and science into the future. I am very happy to describe my enthusiasm for it.
There are three aspects we should emphasise here. The first is education. This is about our young people and educating them to the highest possible level in science and technology. Many studies show that the earlier that kids become involved in STEM, the better for them, their career prospects and their whole lives in many ways, because science is so important. That is our ambition.
Our goal is to inspire young people as to the wonder of science and give them options down the line. Very importantly, and consistent with the Government's goal, it is about girls in science. We will focus on that. We will also focus on non-traditional backgrounds. We want as many people as possible, from all over the country, to have access to the facility. It will be a national centre. This will be a big focus for us as well.
My dream is that a young person will come into the centre and be inspired to become a scientist and find a cure for some illness we cannot yet treat, or maybe help to address climate change and such big issues. That is my second key focus here. As members will all agree, there are many challenges that we now face in Ireland and globally, including in respect of food security, climate change, medicine and, most importantly, artificial intelligence, AI. AI was not around when this project began decades ago. The challenges AI will present for our young people make the project even more important. AI will also be a massive focus for us.
The third reason, which Ms Galavan touched on, is that the tech science sector in Ireland is critical for Ireland's success, as members will all agree. We get so much from it and it gets so much from us. Very importantly, it is very happy to engage with us on this project. One of my jobs will be to help with philanthropy and talk to industry, given my connections with big pharma. The drug companies I have spoken to are very keen to become directly involved. Why would they be involved? It is very simple. First, they see science as a societal good. They see the project as of benefit to society. Second, it is about employment and economic activity. We must educate our young people fully in science and technology because we do not know where the next challenges and jobs will come from. The tech science companies have identified a massive need in Ireland to improve our offer educationally for our children to ensure employment will be secure for them in the future. The educational aspect is extremely important to the companies.
I appeal to all the members to help us. This is a partnership. Together, we must deliver this. We hope the members will join us on this adventure to deliver what we think is the most important project for science in Ireland for the future.
Comment on this
I thank the witnesses. Everyone should note that we will suspend at about 12.15 p.m. for a short break of ten to 15 minutes. I now open the floor to members. The lead speaker today is Deputy Catherine Ardagh, who has 15 minutes. All other members will have ten minutes after she concludes. Thereafter, if time allows, members will be allowed back in for a short round of supplementary questions.
Comment on this
I thank all the witnesses for coming in today and for their opening statement. Obviously, our focus today is primarily on governance, accountability, value for money for the taxpayer, and discovering, for the public, whether this project is realistically deliverable.
In 2003, the State entered into a long-term lease agreement. Concerns have been raised about whether there were a clearly designated sponsoring authority and formal sanction for the project. I have a few questions in this regard. What was the formal designated sponsoring Department in 2003? Was the Minister for Finance's sanction obtained at the time of signing the lease? Was the full cost–benefit and capital appraisal conducted before the commitment to sign the lease was given and before the lease was signed? Does the OPW accept governance arrangements were unclear at the inception of the project in 2003? It is an OPW question but also one for Ms Galavan.
Comment on this
There were a few questions and I will do my best to answer as many as I can. It was ICML's very clear understanding from the very beginning in 2003 that the sponsoring Department was the Department of trade and enterprise. The Minister for trade and enterprise was also the Tánaiste at the time. ICML had very significant dealings with that Department and the Minister of State at the Department of Finance was also very much involved. From ICML's perspective, it was very clear that there was a Department, perhaps. It entered into discussion with the Department in good faith, perhaps. I think it has been identified by the Comptroller and Auditor General that a formal appointment was not made, but that would not have been within the knowledge of ICML. ICML's dealings were very much with the Department, and there were discussions and various meetings during 2003 at which ICML aligned its ambitions with Government ambition. Also, there was a Government appointment to the board requested. This was adhered to.
Comment on this
On the negotiation of the contract, the Chief State Solicitor had a conditional clause in it that recommended that it be linked to the development at Heuston Gate. This clause was taken out of the contract. Was it taken out at ICML's request? Does Ms Galavan know why it was taken out?
Comment on this
I do not. I think that is probably a matter for the OPW. As far as ICML was concerned, it was negotiating in good faith. We would not have been privy to any advice that the OPW would have been getting in that regard.
Comment on this
Ms Galavan was not involved in the negotiation on the lease.
Comment on this
ICML was obviously involved but we would not have been privy to advice that the OPW would have got in relation to the agreement.
Comment on this
Does Ms Galavan know if her organisation instructed its solicitors to remove the clause?
Comment on this
Sorry, but I do not know the answer to that.
Comment on this
With the financial crash, the project did not go ahead. There may be repercussions for the State in relation to that. There were repercussions, obviously. In 2013, ICML issued arbitration proceedings, which were ultimately settled. There was a second set of legal proceedings issued in 2019. Could Ms Galavan tell us the cost of the legal proceedings?
Comment on this
They were not legal proceedings, as such. Arbitration was initiated in 2013.
Comment on this
The C and AG has laid it out in his report. I will stand to be corrected, but I understand the cost is in and around €500,000.
Comment on this
Is that for the first set of proceedings or for both sets?
Comment on this
It is for the first set. For the second set, the cost is similar. I understand the recent costing is about €575,000. There are some costs still to come because there was a further hearing in relation to that arbitration.
Comment on this
After the 2013 settlement, it was decided to move to the Earlsfort Terrace site. Who gave formal approval for that? Was the approval of the Department of public expenditure necessary?
Comment on this
I cannot answer that question. It might be better directed to-----
Comment on this
I remind the Deputy that we have representatives here from both the Department and the OPW.
Comment on this
Sorry, I thought they were coming in on these questions.
Comment on this
I would like a response from the OPW on the costs issue, whether Ministers at the time were aware of it and in relation to the legal advice on the conditional clause.
Comment on this
Regarding the 2013 agreement and whether the sanction of the Minister for Finance was sought, the report of the C and AG, at paragraph 5.21, sets out that the Chief State Solicitor's office, CSSO, recommended inclusion of a conditional clause that if the Heuston Gate development did not proceed, the agreement to lease would not have effect. Unfortunately, and I say this as Accounting Officer 20 or more years later, that clause was not included. That is something I have some concerns about as the current Accounting Officer. For whatever reason at the time, the clause was not included, notwithstanding the legal advice from the CSSO to the OPW that it should be included. That is all I can say on that from a factual position.
Comment on this
Will Mr. Conlon comment on the costs issue in terms of the 2013 set of proceedings and the 2019 set of proceedings?
Comment on this
The C and AG has set that out in the report in relation to the original proceedings. As Ms Galavan said, the more recent proceedings have recently been settled for-----
Comment on this
Will Mr. Conlon confirm what the amount is for 2025?
Comment on this
Is that for both sets of costs or are there two separate sets of costs?
Comment on this
In relation to sanction for the revised agreement, was the Department of public expenditure aware of what was happening at all times?
Comment on this
That is addressed in the C and AG's report. In essence, there is no evidence the Department was asked for approval.
Comment on this
It is quite worrying for anyone listening to this discussion that huge contracts can be signed without proper approval. The OPW should have gone back to the Department for approval of the project. Why was that not done?
Comment on this
From my own review of the files, there were communications at that stage between the then chairperson of the OPW and the Department that would have informed the latter of the ongoing discussions to settle arbitration at the time. There was no formal approval sought, as Mr. Jenkinson said, but the Department was informed of the negotiations that were ongoing at the time.
Comment on this
Was there a fresh appraisal of how much it would cost to complete the project when the OPW was entering into the 2013 settlement?
Comment on this
I think there were discussions at that stage in relation to a possible alternative site and then there were discussions that led to the identification of the site now proposed for the National Children's Science Centre. My review shows there was no in-depth work done on costings in 2013.
Comment on this
We also now have 2024 costings in the region of €70 million. That is the new estimate. How are those costings backed up?
Comment on this
The plans are fully costed having regard to the full scope of the project in 2024 terms. Mr. Sreenan, who is the State architect and is involved in this, might address the question quickly.
Comment on this
The cost estimate of €70 million is a gross estimate covering all the costs involved in the development, including VAT, contingencies and all the levies a contracting authority would be subject to pay. The estimates are developed on a mature set of drawings based on the planning permissions that have been in place. It should be noted that previous cost estimates were not necessarily gross cost estimates. A final point is that in the time before the current 2025 cost estimate, there was a very troubling period of inflation in and around 2021, with inflation reaching in the order of 15%, which is the highest rate on record.
Comment on this
This project has not been plain sailing. There have been two sets of proceedings, an economic crash, issues with the initial agreement and failure to include conditional clauses in contracts. Has the OPW looked at a walk-away situation? A lot of large projects have come before us that have ended in disaster, with nobody seeming to be able to blow the whistle and say, "Let us stop this". Has the OPW looked at this project and considered what the cost would be to walk away from it, what the worst-case scenario would be and what its liability would be? The public wants to know whether that has been considered.
Comment on this
We have not considered that at this stage. I am conscious that this has been the subject of ongoing legal arbitration over quite a number of years. In the views of the Accounting Officer that I set out in the C and AG's report, I acknowledged that legal obligation. At this stage, I cannot make any comment in relation to any future consideration that may be given to any further negotiations. I would require legal advice on that.
Comment on this
Has the OPW ever looked for legal advice on termination of the project?
Comment on this
Has there been any discussion at senior management level on terminating the project?
Comment on this
No, not to date. As I said in the C and AG report, I acknowledge the obligation to construct this project. I pointed out in the report the funding dilemma. It would be premature for me at this stage to give any indication of any further consideration we may give.
Comment on this
Do the representatives from the OPW and the Department believe this project will be built? If so, do they have a realistic timeframe for when it will be built?
Comment on this
This is the fundamental dilemma I have with this project as Accounting Officer for the OPW. Until a funder is identified, it is not possible for me to answer that question at this stage.
Comment on this
This project never got off the ground. Another science centre was opened in Sandyford that has been quite successful. Without reinventing the wheel, have there ever been discussions about a collaboration with that centre? Do we need two science centres in this country?
Comment on this
The Deputy is referring to Explorium in Sandyford. I am conscious that no representative of that organisation is here and I would like to be as respectful as possible. Since joining the National Children's Science Centre in September 2024, I have not been out to Explorium. The promoters contacted us and I have met them. Primarily, we want to work with the Government to see this project through but I have met Explorium. I understand that, going back quite a while, Explorium has been consistent in approaching ICML with a view to working with it in some way. However, I have also been very clear with Explorium that our commitment and the Government's commitment is to each other. We are not really in a position to be able to have a meaningful conversation with Explorium because our commitment is to the Government.
Comment on this
I think we could have two science centres. Does Ms Galavan agree?
Comment on this
I absolutely agree.
There are many European countries that support multiple science centres. Perhaps Professor O'Neill would like to add to that.
Comment on this
This is a national centre, remember. We are aiming for more than one location. It will be around the country. We hope to have exhibits to go on tour, for instance. In terms of Explorium, absolutely, we will talk to them; you never know, they might be able to provide it with us. That is open to negotiation, obviously. We have got big ambitions here. We think the Earlsfort Terrace site is ideal for this. It is in the city centre. We are going to build a planetarium there, which would be a superb facility. It is beside the National Concert Hall, which we think is extremely important because of STEAM and the arts connection to science. Ireland could have a niche with the arts-science interface. It is a great location, so there are various reasons that would be the hub but there could be spokes around the place. We would love to explore that, in fact, as a possibility.
Comment on this
Go raibh míle maith agaibh. I thank the witnesses for coming in today. We appreciate them giving their time as they are all very busy people. I will start with DPER and Mr. Jenkinson. How did we get to this point? Was the sanctioning done correctly at the start? I presume Mr. Jenkinson was not there at that time.
Comment on this
So, he should feel free to comment honestly and openly.
Comment on this
It is set out in the Comptroller and Auditor General's report about how it all came to pass that DPER sanctioned-----
Comment on this
No, it was not, obviously. DPER approval was not sought. The infrastructure guidelines and the public spending code were not complied with at that time. There was not a sponsoring authority. The appropriate governance and value for money considerations were not in place when the contract was signed.
Comment on this
When representatives from the OPW were in here previously, they said they would be ready and willing to work if there was money assigned. Do you have a vision of what Department would be the lead Department on this?
Comment on this
Is that not the nub of the question here?
Comment on this
Normally what happens is that a sponsoring authority will come to DPER with a proposal and a business case, and will demonstrate how it complies with the infrastructure guidelines. Sponsoring authorities identify themselves to DPER and bring the projects. DPER would never previously have had a role whereby it said "here is a project; we think you should do it". I suppose it is an unusual situation.
Comment on this
I am very conscious that DPER was not in existence at the time as a self-identified Department. It would have been the Department of Finance. The OPW is under the Department of Finance. Was it pushed initially by the junior Minister at the time or was it the senior Minister? Was it a pet project for someone or what happened?
Comment on this
Just from reading the chapter, it was through the Department of enterprise that the project was initially brought forward in conjunction with the Minister of State in the Department of Finance, who I assume was over the OPW.
Comment on this
According to the OPW records, what was the process of engagement with it?
Comment on this
From my recollection of the files, the Department of trade and enterprise was the effective promoter of the project at that stage. It would have engaged with the OPW in relation to the possible location of a site for the project. At that stage, a site was identified by the OPW at Heuston Gate. That is set out in the Comptroller and Auditor General's report. It is probably worth bearing in mind that at that stage, from an Exchequer perspective, this was seen to be a project that would be funded from the property dividend from that site rather than from Exchequer resources. That changed, obviously, as the financial crash came and as we moved on. At that stage, the Department of enterprise and trade was pushing the project. It asked the OPW to get involved in site identification. That was done but it was seen to be an Exchequer-neutral project at that stage because it was part of a cultural gain from that big development of Heuston Gate.
Comment on this
Okay. If we fast forward 22 years, how much money has been spent to date?
Comment on this
I think figure 5.4 in the Comptroller and Auditor General's report sets out a sum of €4.2 million. If we add the €576,000 I mentioned earlier in terms of legal costs, we are now heading towards €5 million.
Comment on this
Approximately €5 million has been spent on absolutely nothing. We do not even have a plan. All we have is the same objective that we started off with in 2003. Is that correct?
Comment on this
Those are the facts, Deputy. That is all I am going to say.
Comment on this
No, no; those are the facts. I thank Mr. Conlon for being honest and open on it. Obviously, the OPW cannot do anything until it gets the money. It has said that it is ready and willing, if it gets the money. The ICML is here as an independent group. It obviously has an intention to develop. What is the latest business case that has been put forward on it?
Comment on this
If I could just jump back to a comment that the Deputy has just made, we have a designated building and planning permission.
Comment on this
It is a location. A significant amount of work needs to be done on that building to fit it out. It will cost up to €40 million just to make it serviceable. Is that correct? That is my understanding from reading the documents.
Comment on this
We have the north wing of the site at the National Concert Hall, which is about 60% of the overall planned site, and reinvestment in that would be 60% or so of the €70 million.
Comment on this
Yes, so around €40 million of the €70 million would have to be done anyway.
Comment on this
The north wing will require investment at some stage, for whatever purpose. The initial amount would be for the building of a planetarium. The building is there. A site and a building have been located. Investment is required in the existing building and also if we were to proceed with the further development of a planetarium.
Comment on this
Just to clarify, who owns that specific site?
Comment on this
The National Concert Hall is owned by the Commissioners of Public Works.
Comment on this
That is fine. Can I get an answer to my question on the business case?
Comment on this
The lack of a business case was not entirely clear to us until much later in the process. I cannot be definitive about that date. Obviously the Comptroller and Auditor General has pointed that out as well. When ICML became aware of it, it conducted an investment appraisal and business case in 2018. That document was circulated to a wide number of Departments because there were more Departments involved in it post 2013 after an interdepartmental-----
Comment on this
Just let me bring it back to the business case. We are talking about a significant investment. What would be the ongoing cost of running this State-run science centre, if it were built?
Comment on this
We tried to help the Departments by producing an investment appraisal and business case in accordance with the public guidelines. It is very hard to answer that question definitively until we get engagement with the Government.
Comment on this
At the same time, we must have some idea even as regards the running costs. I come from a financial background; I am an accountant. I am trying to get an idea of what the costs would be if it was built. Would there be running costs of €10 million, €20 million, or €5 million per year? I just do not have an-----
Comment on this
I am not trying to avoid the question but it is very difficult to answer it when we do not have-----
Comment on this
Yes, we do not have the up-to-date business case. I genuinely have no problem with that but-----
Comment on this
We have a draft business plan, which is obviously different to the business case. We have not really been able to finalise that because we have not had the necessary engagement with the Government. Based on that draft plan and looking at the figures for State support for other cultural institutions, which can vary from €15 million to €20 million, we do not envisage it being at that level at all.
Comment on this
No, I am sorry. I did not mean to give the impression-----
Comment on this
It is really difficult to finalise that plan without having that engagement with the Government. Going back to the origins, it was always the understanding of ICML that the State would have a significant role in terms of the ongoing operation of a science centre.
Comment on this
Would ICML see itself managing it or would it be more like a board? Would it be in oversight as opposed-----
Comment on this
Again, that is the discussion that we would love to have with the relevant Department.
Comment on this
As per the level of discussion, it is not clear, as yet. Is that right?
Comment on this
That is fine. Just to jump back to DPER, did the OPW have the legal right to sign that at the time?
Comment on this
It should have come to us for approval.
It is not a legal requirement but the public spending code was there. That is not on a statutory basis but it is supposed to be complied with by Departments to ensure value for money. It did not comply with that and it should have at the time.
Comment on this
I will have to pass that over to my colleague.
Comment on this
It would have been signed by a senior official in the OPW at that stage. The Deputy asked whether it had a legal entitlement to sign that lease. My understanding is it would have had a legal entitlement to sign it but it should have sought an approval, because of the financial consequences of entering into that, from DPER at that stage. The signature of the lease by the OPW official would have been a two-stage process but in my view, and looking back at it now, there should have been consent or sanction sought from the Minister.
Comment on this
The fact it was not does not negate the fact that-----
Comment on this
It does not negate the legal obligation. That is the point. I did not think so but I just wanted it clarified.
Comment on this
I know Deputy Byrne is in a mad hurry. She was telling me to finish and hurry up. I thank the witnesses for that and I will follow up on some of it.
Comment on this
My first question is for Ms Galavan. Will she explain why she sent a revised opening statement last night and removed only one line of it stating that up until 2022 the Government had a representative on the board?
Comment on this
That was just a misunderstanding on my part. The Government did nominate a representative to the board in 2024.
Comment on this
The statement says, "up until 2022".
Comment on this
I beg your pardon, it was 2004. I do not have the detail in relation to how long that board member served as a representative of Government. Whatever that period was, that person continued to remain on the board in a personal capacity. I was just conscious-----
Comment on this
Could Ms Galavan provide the exact detail of that to the committee afterwards?
Comment on this
I have to be frank with the witnesses before I start. I am of the firm belief that this is a vanity project and very much an unwelcome remnant of the Celtic tiger era and the "connected few" era. The politicians who originally agreed to this project are the ones who set this State on the road to financial ruin in 2008. This is probably not going to go down well but I believe that, collectively, the science centre and the OPW have used their connections to strong-arm the State and are trying to put the Irish taxpayer on the hook for tens of millions of euro. We have already heard of costs of up to €5 million with no explanation and nothing to show for it. Due process has not been followed from the outset, which was clarified here this morning, and the science centre has benefited from that. As mentioned by the first speaker, we are here to protect the taxpayer and to ensure there is value for money. The questions are hard this morning but they are needed. I really believe that.
I have two questions for the OPW and the Department, for which I would like a "Yes" or "No" from whichever is better placed to answer them. At this moment in time, has a parent Department been identified for this project?
Comment on this
Has an economic assessment been carried out, which is a requirement for public funding?
Comment on this
It would need to be carried out by the sponsoring authority, so the answer is "No". There is no sponsoring authority.
Comment on this
For the board, with no parent Department and no economic assessment, which is required - I understand it has a business case, which I will come to in moment, but there is no economic assessment - can they accept that the State simply cannot fund this project at this moment in time?
Comment on this
What has happened is that the process up until now has been extremely unfortunate, but the purpose behind the science centre from the get-go has only grown. The need for a children's science centre has only grown.
Comment on this
I do not dispute the fact at all that a science centre is needed. I am really supportive of it. Professor O'Neill's contribution at the beginning was very enthusiastic and, I have no doubt, very genuine. I do not dispute the need, but where we are at is there is no economic assessment and there has been no parent Department willing to take this on for over two decades. That suggests there is no faith in this project from this Government or previous Governments, if nobody is willing to step up and take this project on. Costs have been identified, most recently in 2024, of €70 million with the potential for further increases. We are in a time when construction costs and inflation costs are increasing. We already heard examples of how inflation hit high levels in 2021. That could potentially happen again. There is a business case that was updated in 2024 from 2018, but there is no 2026 updated version of the business case at this stage. How can the witnesses realistically sit in front of this committee and in their own words in their opening statement appeal to us today to support the progress of this project? I do not understand that.
Comment on this
I would like to bring Professor O'Neill in because the benefits of a science centre have to be discussed before we can talk about that. We, in good faith, got-----
Comment on this
The benefits are not in question here. I have already stated, and everybody who spoke agrees, there is a need for a science centre. I 100% support it. The benefits are not in question but realistically there is nobody willing to step up and take ownership of this, probably because due process has not been carried out from the outset 20 years ago. That is why nobody wants to put their name to it now. Will this turn out to be another national children's hospital fiasco and a bottomless pit with public money being lost at the core of that? Can the witnesses guarantee that will not happen?
Comment on this
I can try to answer. From my point of view, I joined this knowing about this unfortunate series of events that happened. It is obvious that puts people off getting involved. We need the Government to support us now. That is our ambition here. We can make the case for that. I made a bit of the case earlier and there is an extremely strong case. Most of the science centres in the world are supported with public money, not just private money. There are various reasons for this. One is educational. We will tie into the national curriculum, very importantly. Part of the Government's ambition, of course, is to improve science education in the way I said. That is why we need Government support. Science centres are used as soft-marketing devices to attract FDI or high-tech companies into countries. It can be used as a showcase for Irish research. That is a second function as to why Government sponsors it. Where there are private ones, and they of course exist in the world, they are inclined to be based on entertainment and have a different mission from what we have.
Again, there is a strong case to be made for some public funding but, really importantly, we have philanthropy lined up to donate to this project. We are estimating various amounts of money from who we are talking to now, but they will not participate unless there is Government support as well. Some kind of public-private partnership will be needed to entice our philanthropists, who are mainly science and tech-based companies. I am very confident we can raise substantial funding from them if the Government supports us. The bottom line for me is this is stuck. It is stuck because of the history, which is not great. I looked at the history when I joined the board and asked, "What happened here? This seems ridiculous". One reason was the economic crash but various unfortunate things have happened. We have to move on from that.
Comment on this
We do, but we can never move on unless we know what the true cost of this project will be. That is what I am coming to. There is a business case that was last updated in 2024. It is now 2026. We are talking about figures of €70 million. Does that €70 million contain contingency for increased costs? Does it contain contingency for the heritage aspect of the project and the restorative aspect of the heritage in the project? None of this is abundantly clear to anybody. We are talking about public money. We do not know what funds the centre at the moment. It has two members of staff. What does its nine-to-five look like at the moment and who is paying for those staff? There are so many question marks hanging over this project that I do not think the witnesses are in a place to be able to sit in front of the public accounts committee today and appeal to us, in their words, for support.
Comment on this
On the nine-to-five, as I said, I am part time and there is another part-time member of staff. Since I joined in 2024, I have been very focused on trying to communicate with Government and-----
Comment on this
Who pays for the staff? I am sorry to cut across Ms Galavan, but who is funding that at this moment?
Comment on this
Please, and I ask Mr. Naylor to be brief.
Comment on this
If I talk about the funding to date to the charity, or to the CLG that the board represents, in the order of €3.5 million has been donated by private companies, private individuals and Government over the period since 2006. There was a period between 2009 and 2016, during the economic crash-----
Comment on this
I do not need all of that. I asked a simple question.
Comment on this
In the 2024 accounts, which are fully available on record, there was €100,000 in the bank and today there is about €300,000 in the bank.
Today, all that money comes from private donations.
Comment on this
Members of the board itself have donated.
Comment on this
I understand that. I am conscious I am running out of time. Ms Galavan mentioned the Explorium. It is a fantastic facility. I quite enjoyed the time I spent there. Has a partnership with the Explorium been ruled out or is the only viable way forward for this project a significant partnership between both entities?
Comment on this
We have not ruled anything in or anything out. As I said, we are not really in a position to do that.
Comment on this
I take exception to that. That is something that needs to be considered. I am not saying the centre needs to rule it in. This has to be done to deliver the best outcome for the taxpayer at this stage, if Ms Galavan cannot guarantee significant costs sitting where they are at and potentially not increasing any further. I do not think she can guarantee that this will not exceed the projected figure of €70 million. She really needs to give serious consideration - I am not saying she has to rule it in - to a partnership with the Explorium being the best outcome for the taxpayer.
Comment on this
As the OPW has said, 60% of the cost of that €70 million has to be spent on the north wing, regardless of its end use. Breaking that down, it is about €30 million for the provision-----
Comment on this
That may never come to fruition at all. I am out of time but if we are being realistic, that may never come into fruition. Until Ms Galavan is in a position that she can sit with a black-and-white document with an up-to-date business case, with realistic costs and contingency plans for where potential increases will most likely occur-----
Comment on this
But Ms Galavan is not giving those answers.
Comment on this
We need to have those conversations with Government. As the OPW has stated, 60% needs to be spent on that iconic building, regardless of its end use. That means the cost of providing a national children's science centre for Ireland is €30 million. To go back to the origins of the project, it is a true public-private partnership. We are prepared to raise philanthropic donations to the level of €25 million to fit it out.
Comment on this
I thank the witnesses for attending. It is a most unusual situation for us to be in. I do not recall another meeting where we had one party - effectively a private entity - pursuing a legal claim against a Department that is also present. Our job is to protect public money and to ensure good governance around public money and to ensure that when mistakes are made, they are identified. The committees on children, education or higher education are the fora to advocate for many of the things which Professor O'Neill spoke about. We are also precluded from discussing matters of Government policy and so on. This committee has a very specific remit and all of the members have focused on that remit. There is huge merit in the idea of a children's science museum. I know there was great disappointment when the science museum in Trinity College closed, for example. A project can have merit. As public representatives, we come across good ideas every day. The question is how are they pursued.
I want to divide my time between both parties. By virtue of a decision in 2003, ICML effectively got the State over a barrel. Somehow, in 2013 it managed to get the State over two barrels. It has a legal claim and it has pursued this. Why would it not? Its objective is to deliver a science centre and it is pursuing the right it believes it has garnered. As a public affairs strategy, in pursuing that the State has accrued €5 million and ICML will be coming back to the State looking for €30 million or perhaps much more. Is it a good strategy by the board to pursue the current course of pursuing this legal right, which is ratcheting up costs for the State? There is a phrase, "Can youse just get a room?". I do not know why both sides need an arbitrator to be in the room with them. Surely this is a matter where we put people in a room and they come to a decision. Pursuing the legal claim always prevents a solution because it forces all Departments to act cautiously.
Comment on this
It is important to remind the committee of the genesis of the project. It is an unfair representation to say that ICML had the Government over a barrel in 2003. The Government sought proposals for a-----
Comment on this
ICML secured a legal obligation-----
Comment on this
-----through advocacy. I not suggesting ICML did anything wrong but it secured a legal obligation.
Comment on this
Having the Government over a barrel implies wrongdoing.
Comment on this
I am not suggesting that in any way.
Comment on this
Yes, I am happy just to clarify that. ICML pursued an non-legal strategy for ten years, having secured an agreement at the request of the State, to provide a national children's science centre. It was acknowledged by the State at that stage that it would be a very significant partner, by virtue of the fact that it actually funded ICML from the beginning. For ten years ICML pursued a non-legal strategy. It was only when there was absolutely no other option that it initiated arbitration. This led to a very positive outcome, which is the location of Earlsfort Terrace, a building with a long-----
Comment on this
Does Ms Galavan accept the reality of the current situation where more than €5 million of public money has been spent? She can hear the concern on this side of the table. No parent Department is willing to come forward to put itself on the hook for the remainder of the money. That would seem to be a flawed strategy over 20 years.
Comment on this
As I said, the board was left with absolutely no other option than to go that route. The 2013 agreement was very positive. It led to the identification of a very appropriate building that started its life as an exhibition centre. It is co-located with the National Concert Hall and gives wonderful opportunities in terms of being able to lean into-----
Comment on this
Based on the most recent court proceedings, what is Ms Galavan's expectation now of the OPW?
Comment on this
We have a very good constructive relationship with the OPW. I have been able to communicate-----
Comment on this
I am conscious of my time. What is ICML's expectation following the court case as to what the OPW should do?
Comment on this
What we would like is a Department to talk to that would take this on.
Comment on this
Am I correct that the court proceedings went further than just talking? Is there an expectation that there would be a specific purpose, which is the delivery of the centre?
Comment on this
It was not court proceedings; it was arbitration-----
Comment on this
-----and the commitment was reinforced during the course of the arbitration.
Comment on this
The arbitration reinforced the commitment the OPW has to ICML. Is that the case?
Comment on this
That is based on the 2003 and 2013 agreements. Is that correct?
Comment on this
Is there no deviating from that from ICML's perspective?
Comment on this
I have written a lot of letters to Government looking for meetings. If we could get into a room, as the chair said at the beginning, and communicate with Government about the project, I think we could make progress.
Comment on this
I will turn to Mr. Conlon. Is this not an incredibly messy situation?
Comment on this
It is certainly very unfortunate. This is my third or fourth time before the committee talking about this. As I have outlined in all the evidence I have given to the committee and as outlined in the report of the C and AG, we are a contracting authority, not a sponsoring authority. The way this has developed over time where sponsors have walked away from this project, has left me, as Accounting Officer, in a very invidious position.
Comment on this
Mr. Conlon said that sponsors had walked away from the project. Is he implying that the Department of enterprise was sponsoring the project and it has walked away?
Comment on this
As far as I can read back. The Department effectively sponsored this for quite some time, from 2003 to 2011 or so.
Comment on this
Does Mr. Jenkinson want to respond to that?
Comment on this
I agree with the chairman. At the time that was the impression given.
Comment on this
In 2003, the commitment was entered into on the basis that there would be no direct State funding to ICML. Is that correct? I want to note the difference between direct State funding for its operation versus funding for the capital fit-out. How in 2013 did we seem to double, or certainly increase, the exposure of the State?
Comment on this
I think that was in reaction to the legal proceedings via the arbitration process that was taken at that time. At that stage, according to my review of the files, the OPW reacted to the legal proceedings. Based on the legal advice that it got at the stage, it settled those legal proceedings through the provision of this site. At that stage, there was also an offer of another site that was refused by ICML, and that is set out in the C and AG's report as well.
Comment on this
It appears that ICML - I take it as a contracting party here as opposed to a good or bad idea - had a right to have a space in a building that was never built and somehow that converted into it having a right to be in what is effectively one of the jewels in the OPW's crown in the centre of Dublin city. In terms of a ten-year process to protect the State's exposure, how did we get to a point where that particular site was identified, and the commitments strengthened in 2013, at a time when there was no sponsoring authority?
Comment on this
I think it was because of the reaction to the legal proceedings rather than taking a wider view that included the legal proceedings process plus the funding process. From my perspective looking back at this now, there was very little capital available to the State in 2013. From the OPW's perspective, our capital budget, looking back on it-----
Comment on this
At a time when there was very little capital available, how did the OPW agree to a new commitment that was effectively double the size of the previous one?
Comment on this
The short answer I can give is that it was because of the legal proceedings that were taken and the reaction to it.
Comment on this
Was it a mistake for the OPW to enter into that new agreement in 2013?
Comment on this
I think there should have been a wider focus taken. This is my personal view after looking back on it, and hindsight is a perfect teacher for all of us, but I think at that stage the funding element should been more deeply considered.
Comment on this
Is it possible for the committee to see the details of that arbitration agreement?
Comment on this
I think the final word has been given. I will have to take advice in relation to 2013, but the later arbitration proceedings can be made available. I will see what I can make available.
Comment on this
I am wary of straying into the area of Government policy, but has the Department any current plans to engage with ICML?
Comment on this
Is it Mr. Jenkinson's view that the Department will engage with ICML at any point in the future?
Comment on this
I cannot say. We have got no indication from a sponsor-----
Comment on this
Given the current priorities of the Department, the national development plan and the voteable budget of the Dáil, is there any scope within all of that for the Department to deal with ICML or is this just not a priority for the Department? If not, is it better if we know that now?
Comment on this
I can say that there was no funding sought for this project as part of the NDP review process that happened last year. There was no indication at that point and that was a big process. It took a lot of time to nail down Government's priorities and set out funding. This was not reflected in any of those discussions.
Comment on this
Is Mr. Jenkinson aware of any other Department examining it?
Comment on this
I want to start with a direct question to the OPW and the representatives from the Department of public expenditure. To make this as simple and clear as possible, I want the witnesses to say whether they agree with my next statement. The OPW - the State - is effectively legally obligated to provide a children's science centre at a cost of at least €70 million, but it has no plan to do so. Is that correct?
Comment on this
The strict interpretation that I would give is that the OPW is legally obliged to provide what can be termed "a shell and core" building for the provision of a science centre. We have no obligation to fit out that and we have no obligation for any recurrent funding for that.
Comment on this
What is the estimated cost of the OPW's obligation?
Comment on this
As we said earlier, it is now in the region of about €70 million.
Comment on this
Mr. Conlon wanted to clarify it, and I appreciate that. Do the officials from the Department of public expenditure agree with my opening statement?
Comment on this
I want to go back to the beginning. Was the Department of enterprise the initiator and promoter of this in 2003?
Comment on this
Fast forward to 2013 when the OPW entered into a new agreement. Was the Department of enterprise on the scene at that stage?
Comment on this
Not that I can ascertain from my review of the files.
Comment on this
So, it effectively abandoned the project prior to that agreement in 2013.
Comment on this
As the Comptroller and Auditor General pointed out in his report at paragraph 5.36, there are notes and correspondence in the file about how the Department remained committed to the project in 2011.
Comment on this
This is just an observation around the origin of the project. My understanding of it is that the Department of enterprise was in favour of the development of a children's science centre. At the same time, the OPW was trying to develop a major development at Heuston Gate. It was caught up in the property bubble and the OPW needed to find a cultural component to put into that major project or else planning would have been a difficulty. The OPW had a driver that was going to provide Civil Service or public service accommodation and there was also going to be a huge commercial element to it. The Department of enterprise and ICML, in good faith, were available and willing to be part of that overall development. The problem was that when the development collapsed, the commitment had been given and it was open-ended. We ended up with a project that had been given a life because of the attitude of the OPW. There may be an analogy, and the OPW may be able to give a view, in that the redevelopment of the National Concert Hall site has always been an ambition. It is a site that is owned by the OPW. The OPW needed a solution for there as well, something to fill an empty space and an empty site. There is an element of this being a child of the OPW. I think there is an overemphasis on the role of the Department of enterprise. I am sorry that answer took so long.
Comment on this
No, I thank the C and AG. If we are trying to peel away the layers of responsibility here, that contribution is helpful.
I am going to stay in 2013 because a series of reckless decisions were made by the OPW during that year. Doubling down on its commitment is effectively what happened. The OPW committed to doubling the size of the project and obviously the cost of the project has escalated. These comments are not personally directed at Mr. Conlon because I know he was not there at the time. He is here in his current capacity. We are just trying to understand how those decisions were made back in 2013. There was obviously the backdrop of legal action and so on. Will Mr. Conlon comment briefly on that period and how that decision process came to be?
Comment on this
I thank the Deputy and the Comptroller and Auditor General. It is difficult for me to comment because I was not there at the time, so I speak from reviewing papers. I am still of the view that it was a reaction to the legal proceedings at the time, which were obviously based on the original 2003 decision, which as I stated earlier in evidence-----
Comment on this
How did it effectively double up?
Comment on this
Is the Deputy referring to the size of the budget?
Comment on this
Yes. There was an obligation from 2003, but, in simple terms, the OPW effectively doubled its obligation.
Comment on this
May I ask Mr. Sreenan to bring the Deputy through the development of that? I will come back in then.
Comment on this
I will try to do this as quickly as I can. Back in 2001 and 2003, it was effectively a master planning exercise at Heuston Gate. There very crude allowances and in effect there were no building designs. In old language, the assumption was that 40,000 sq. ft translated to about 3,700 sq. m. As the project developed, the planning application lodged in 2004 amounted to about 5,900 sq. m based on significantly more detail than would have been available at the master planning stage.
Comment on this
If the OPW had a public expenditure commitment in 2003, it seemed to increase that commitment in 2013. That is my point. How did that come to be? If there were legal obligations from 2003, how did the OPW increase its obligations? No one can answer that today.
Comment on this
I understand and acknowledge the question. I am trying to step through the technical-----
Comment on this
I know, and, with respect, I do not have time to go through all of the steps. I appreciate that the people here were not involved in that decision-making process, but that is the nub of the issue. In 2013, the OPW recommitted to a greater extent the State's obligation.
Comment on this
It recommitted based on legal advice at that time, which was based on the original 2003 commitment that was there.
It is set out in the Comptroller and Auditor General report on the development of the scope and the development of the site and a new section 554. We can go into that or provide further detail on it. What happened in 2013 was in reaction to the initiation of the arbitration proceedings by ICML at that stage.
Comment on this
I understand. My point is that we seemed to go further than we had to. That is one important correction.
I will turn to the Department of Public Expenditure, Infrastructure, Public Service Reform and Digitalisation. Ultimately, as the Department of public expenditure it is the guardian of public expenditure. I do not mean this personally but the witnesses from the Department seem to be coming here today as if it is not their problem. No Department has come to them looking to take this on and they are sitting back saying that is fine. How is that fine? There is a mounting cost to the State here. As in the title, it is the Department of public expenditure. How does the Department of public expenditure take that laissez-faire approach to this?
Comment on this
I think the Department has a very important role in terms of protecting public expenditure. We are very clear on how we do that. How we do that is by setting out the guidelines and rules around how these projects should be managed, governed and assessed. That obviously includes the infrastructure guidelines. The Department is involved in setting allocations and then sanctioning spend. It is an unusual situation where it does not pick out or have a project and tell a Department-----
Comment on this
I understand that. We went through our vision of the national development plan recently. All the Departments would have come to the Department of public expenditure looking for capital and expenditure. The Department is aware that there is effectively a hook here for in excess of €70 million that the State is obligated to provide for. It went through that national development plan, the capital programme, without providing for this, even though it knew full well that the cost of this was only going to increase because of ongoing legal challenges and the inflation in construction costs. How does the Department excuse itself in that sense?
Comment on this
For us to be able to engage on it, we need to see a business case. There has never been a business case provided to us. We have very little to go on in terms of assessing-----
Comment on this
Other than the fact that there is a legal obligation to provide for this. That is mounting. Nobody is bitting the bullet, taking responsibility or showing the backbone to make a decision on this. The Department - the guardian of public expenditure - is there in the background allowing this to happen.
Comment on this
We have the guidelines, we have the rules that are in place and we have Accounting Officers who have to deal with that. We have an Accounting Officer here who is trying to do that. We obviously need a sponsoring Department to step up and comply with the guidelines, put in place the appropriate governance and bring that to us. We will engage with it then on that basis.
Comment on this
I will turn to ICML in my final few seconds if I may. Do its representatives believe this centre will ever be built?
Comment on this
We remain very optimistic that it will be built. We believe it is a shame that 20 years later after we got involved in good faith with a plan, which was adopted by the Government at that stage, we still remain the only member of the OECD without a national children's science centre. However, we remain very optimistic.
Comment on this
I acknowledge the good faith of ICML in all of this. Ms Galavan mentioned earlier that she has written numerous letters to the Government. When were the most recent letters sent and who were they sent to, if Ms Galavan would not mind?
Comment on this
The most recent letters were sent in October 2025 to the Minister for public expenditure, infrastructure and reform; the Minister for Further and Higher Education, Research, Innovation and Science; and the Minister of State responsible for the OPW.
Comment on this
Other than the standard acknowledgement, no.
Comment on this
Just acknowledgements were received. My final question is on ICML's next steps. Is legal action going to be an ongoing process in this?
Comment on this
We have not discussed legal action at all in ICML. We are here today. As the committee can see, we truly believe in the project and we want to engage with the Government. I am conscious that the Chair of this committee mentioned the last time it was discussed here that there would be a recommendation going to the Government. We are appealing to this committee to-----
Comment on this
Yes, so that we can engage. That is what we want to do.
Comment on this
I thank Deputy McGrath. We will now take a short break for approximately 15 minutes.
Comment on this
The witnesses are welcome. I very much share Professor O'Neill's passion for science. I am a trustee of a charity which encourages girls from underserved areas to go into STEM careers. It operates on an absolute shoestring, however. It does not have wealthy benefactors or sponsors. It educates girls in science subjects where they do not have science subjects in their school, as far too many girls' schools still do not. They do not have any science classrooms. It also provides after-school grinds, internships and Easter and summer camps. It supports these girls to enter science projects in international competitions. I am also the TD for the youngest and fastest-growing area in the country. Balbriggan is the youngest large town in the country and the most culturally diverse town in the country. Putting a science centre somewhere like that would be an amazing facility. Is there any leeway or room for negotiation on the site or the costs? If ICML is absolutely going to compel the State to deliver a €70 million at least project on the Earlsfort Terrace site, how can I stand over that to my constituents in Balbriggan, Skerries, Rush and Lusk where schools are falling down, where we cannot get access to childcare and where we do not have enough special classes? Here we have potentially a white elephant project that the witnesses have no business case for. They cannot tell us what the costs are going to be, what the revenues are going to be or how much they are expecting the State to give. I find it really difficult, to be honest. For ICML to compel the State, no matter the merits of the legal argument, and I am a lawyer, I find it really difficult to come in here and find no detailed business case, no understanding of what the actual running costs are going to be, what the expected revenue is going to be, and the witnesses telling us to just do it.
Comment on this
First of all, I cannot answer many of those things. What we are asking to happen here today is that we get support for this from a Government Department so we can move forward. That is the mission, first of all, just to move this thing, because it is stuck. What does it look like once we get going? We have reasonably robust plans to build the hub of the centre in Earlsfort Terrace, as was described already. Those plans are at a certain stage, they are not fully advanced yet but they are pretty well developed as plans. That will be the hub. Then there will be spokes. Have a place in Balbriggan. I was the president of the Irish Science Teachers Association. The science teachers are behind this whenever I talk to them. We would love to link into schools, into all these kinds of programmes all over the country. In other words, it will not just be one location by any means. It is a national resource. Our target audience is the very people the Deputy is mentioning. We want to bring children in from places that would not normally access science. That will be a key part of the project as well. These are obvious things in a sense. Internationally, there is always a central hub of a science centre, backed by public funding, and then it will link into the community in all kinds of ways. That is our ultimate vision with this. We are very conscious of the concerns. The science teachers want it, the Department of education hopefully wants it, as a way to deliver on the education programme for the country overall in science. That is my best way to answer that.
Comment on this
The point I would make is €70 million has been mentioned a number of times. As the OPW has said, however, about €40 million of that has to spent on that iconic building regardless of its end use. Really what we are talking about is €30 million in terms of construction funds to build the science centre and a very significant public-private partnership where ICML has committed to fitting it out to the tune of €25 million. I just think that is an important context.
Comment on this
At the outset of this, it was supposed to be that the State was going to provide a building. There was supposed to be no direct cost to the State. Decades later, there has been huge direct cost to the State and the exposure for the taxpayer is phenomenal and yet I have school buildings that are literally falling down. The people in Rush, Lusk and Balbriggan want investment in those school buildings and you are in here and you cannot tell me what the projected running costs and projected revenue of this project are going to be and yet you are asking us to fund it.
Comment on this
Just going back to the very beginning, again I think there is a slight bit of confusion. It was always meant to have a cost to the State. The State was always going to be a partner in this. That is borne out by the fact that the State began to fund ICML in the early days. I do not think it is fair to say it was a project that was conceived at no cost to the State. And also-----
Comment on this
Could Mr. Conlon respond to that, please?
Comment on this
Most definitely from an OPW perspective, there is a capital element, which we have mentioned.
Comment on this
In terms of the recurring costs, I have no insight into that. I do know at the very initiation of the project, from what I have read, that that really was not explored fully as to who would do the recurring costing going forward. That has never really developed as an issue of examination, from my perspective.
Comment on this
Is ICML wedded to the Earlsfort Terrace site? Are you willing to negotiate on anything with the State? Are you going to try to compel the State?
Comment on this
We believe the Earlsfort Terrace site has huge benefits. Obviously the location-----
Comment on this
Apart from that, are you willing to negotiate on anything?
Comment on this
I am not really at liberty to say what we could negotiate on and I think that is a question for the board of ICML. What we want to have with Government is dialogue. There has been a lot of-----
Comment on this
The dialogue cannot be saying you are going to compel the State to do this, no matter the cost to the State.
Comment on this
That has never been the attitude of ICML.
Comment on this
Certainly that is how it feels sitting on this side of the room.
Comment on this
I can appreciate that because of the legal strategy, as it has been termed, but that is not the case. We want to talk to the Government. I have been pleading for the last 18 months to talk to the Government. I just reiterate our ask today which, going back to the Chair's-----
Comment on this
Okay, I thank Ms Galavan.
Mr. Conlon mentioned that the Department was notified of negotiations. As a lawyer, I know there is a big difference between telling someone there are negotiations going on and approving them. Can Mr. Conlon guarantee that the OPW will never enter into an arrangement like this again, where it does not go to the approving body to get the required approval and binds the State into a ridiculously expensive contractual arrangement?
Comment on this
As the current Accounting Officer, that would be very much my approach.
Comment on this
And there are no other issues similar to this that you are aware of.
Comment on this
I fully appreciate that Mr. Jenkinson had no involvement in this and he has my sympathies for having to answer the questions here today.
Mr. Jenkinson mentioned earlier that he had never seen the 2018 business assessment. Is that because it was not sent to the Department or that because there is no sponsoring entity, the Department is not looking at it even if it was received?
Comment on this
I am not sure if it was sent to the Department but essentially one needs a sponsoring Department to conduct the business case and the economic analysis. The Department submits it to the Department of Public Expenditure, Infrastructure, Public Service Reform and Digitalisation if appropriate. The fact that this sponsoring agency is not there at the moment is the reason we have not been engaging on a business case.
Comment on this
In terms of state aid and the risk of state aid, has either the Department or the OPW carried out a risk assessment relating to the state aid risk exposure?
Comment on this
My understanding is that when it comes to something like a museum, state aid does not apply.
Comment on this
We know there is a private science museum so if the State was to support a publicly funded science museum, the competition issues would need to be assessed under state aid rules.
Comment on this
Yes, we would need to get legal advice on it.
Comment on this
But no one has undertaken that assessment so, again, we could be exposing the State to penalties. ICML compelling the State to do what it contracted to do in the 2013 arrangement, even though it was outside the public spending code, could actually expose us to further risk.
Comment on this
To be frank, we have not carried out what the Deputy termed a risk assessment of state aid. We have spoken to our legal advisers on it. I think the state issue will not crystallise until there is a state aid challenge and at that stage, I think we would be seeking firm legal advice. To be frank in answering the Deputy's question, we have not done a risk assessment because it is difficult to be-----
Comment on this
What are the consequences for non-compliance with the state code? What are the penalties?
Comment on this
There are no penalties as such. It is not in legislation. Guidelines are set out. Departments are supposed to comply with it and will be held to account at the Committee of Public Accounts if they do not. The whole point of it is to make sure good governance is in place. When Departments sanction something, we require it to have complied with the public-----
Comment on this
From our perspective, we do not see any consequences or penalties and nobody is ever held accountable. Everyone has always moved on by the time they get here. That is the reality. There needs to be some mechanism for holding people to account and enforcing some kind of penalty. These kind of situations just cannot be allowed to continue. We are all paying for it and we are going to continue to pay for it because ICML is going to continue to insist on compellability no matter the cost and risks to the State, which I find very unfortunate.
Comment on this
I agree. The process over the past 20 years has been very unfortunate but it doe not take away from the fact that we remain the only OECD country without a national children's science centre and that is why we are here.
Comment on this
It is very unfortunate. I am on the board of this project and would hate to think that the committee would think we are holding anybody to ransom here. This has to be a partnership between us and Government. That is the only way this is going to move forward. I take the Deputy's point about other investment in education. We need to up our game with it comes to science funding anyway. Trinity College, which is my university, is massively underfunded but the Government makes decisions on where to allocate its resources. It is important to think that all of this could happen actually and it will be a combined thing. It will not be either-or.
Comment on this
Perhaps I will start on that point. Let us say the Government goes to ICML and says it wants it to be a partnership but thinks it does not make sense to spend €70 million of public money on this but that because there is an existing science centre privately owned in the form of Explorium, the Government wants to facilitate and fund a partnership, perhaps buying Explorium out of private ownership and involving ICML. Would ICML be happy with that as a partnership, moving forward?
Comment on this
ICML is open to dialogue with the Government but it is very hard for us to talk about potential partnerships with other entities when our agreement is with the State as such. Since I came in, I have met Explorium. We want to talk to everybody in the space but in terms of what that might look like, it is very hard to have that conversation without having it first with the Government.
Comment on this
That is what I am trying to find out because Professor O'Neill says that ICML is not looking to hold the State over a barrel. What that looks like is to say that we have an existing science centre. If the Government came to ICML and said this is what it would like to do going forward, is that something ICML would be open to? Obviously, the details would have to be worked out. Alternatively, is ICML insisting that this project goes ahead?
Comment on this
We would like the Government to tell us anything and to engage with us because there has been no engagement with Government here. If the Government comes to us with its ideas, that would be great. We would look at them. Our mission should be combined here to deliver a world-class science centre for Ireland. There could be all kinds of models. It is very hard to get a precise budget and we cannot see the scale of it at the moment and what the ambitions are. It is almost like "think of a number" in a sense. The planetarium is part of our work-up. There is a budget here, of course; we have an initial budget. As I see it, however, the next step must be to engage with the board and bring Government on board with this project and we will start discussing any number of options to deliver the best possible value for money for the taxpayer. Is that a key feature? Of course, it is. Bringing in private investment is really important. All those things on the table as far as I am concerned.
Comment on this
Is ICML is open that one possible solution may be that the project envisaged at Earlsfort Terrace would not go ahead?
Comment on this
At the moment our preference is for Earlsfort Terrace based on what we have done so far. As I explained earlier, there are a few reasons for this. The OPW has to fit it out anyway, it is beside the National Concert Hall and it is in a city centre location. Other science centres are usually in a city centre location. It is our preferred option at the moment.
Comment on this
I am just trying to tease out what it means when Professor O'Neill says ICML is not going to hold the Government over a barrel. If it sticks to Earlsfort Terrace, that is holding the Government over a barrel and it is not clear to me whether ICML is willing to move from that.
Comment on this
The Deputy's point is rightly made but with engagement, I can envisage that a lot of options will be on the table. That would be the process and the due diligence that one would have to go through; no question about that. The mission of this organisation is very clear. The national children's science centre is here to enable the children of Deputy Boland's constituents to have a better life and a better place in Ireland. I understand and appreciate the role of the Committee of Public Accounts here but we also have public wealth and stakeholders. We have science, medtech and technology companies here and there is now a stakeholder effect here but what we need to do is feed that industry and world with fantastic kids who will have great ideas. I was talking to Professor O'Neill earlier about our own kids, who are who are now in their roles outside of Ireland because of being introduced to science very young. I am convinced of that.
Comment on this
I will on move on to something that has not yet been touched on, which is the impact of this on the Iveagh Gardens, which are an oasis in the city centre. They were designed to be that. They are our walled garden. I presume the ICML is aware that a petition has been started by local residents with almost 50,000 signatures that is opposed to this because of the impact on this walled garden. It will end the character of the Iveagh Gardens as a walled garden because it would remove a section of the wall in which bats live. It would go through what is effectively a small semi-wild forested area of the park at the moment so there is significant public opposition to this. They are saying that there was never any real process of public consultation on this. How does the ICML respond to this? What impact would it have in terms of the use of the gardens as they are currently used?
Comment on this
The design has been through very vigorous planning stages, starting obviously with Dublin City Council and going on to be appealed to An Bord Pleanála not once but twice. The last inspector's report from An Bord Pleanála said that the proposed national children's science centre would constitute a positive and sustainable adaptation and reuse of historic buildings that will extend their long-established cultural and educational usage into the future. I would not like to second-guess the planners in that respect
Comment on this
This wooded area would effectively be gone as a result.
Is Ms Galavan aware of whether that is used for any activities?
Comment on this
I do not believe it is. That is outside of our scope.
Comment on this
I will tell Ms Galavan. It is currently used as a forest school by a local school. I think that could not continue if it becomes a hindrance to a second entrance. If this project goes ahead, why does it need a second entrance? Why is the one entrance not good enough?
Comment on this
That is a question that would be more appropriately answered by the OPW.
Comment on this
Further to the points just made around the planning consent, the planning consent process took on board the views, observations and submissions from many people, including those with concerns around the Iveagh Gardens. The consent that was granted re-establishes that historic link between the Earlsfort Terrace campus and the gardens. To add some colour to the point around the impact on the gardens, at the north-western extent of the planned development, some works are planned in order to provide universal accessibility between the gardens and the campus.
Comment on this
There was mention of a lot of commitments from private organisations in terms of philanthropy. Ms Galavan is very confident that ICML would raise the €25 million for fit-out and so on. Are any of those legally binding commitments? How much money has actually been received or how many legally binding commitments have been received where somebody actually needs to put up the money?
Comment on this
It is a good question because it illustrates the difficulty we have in terms of the chicken and egg situation. We have done a lot of work on the philanthropic side of this and are very well prepared to deliver on our commitment. I could not sit here today and represent the board without being able to say that confidently. There is a good track record on the part of ICML in terms of being able to secure pledges and ongoing funding from corporate entities. We have made good progress, but obviously funders are not going to fund this until they know that it is going to be built. That comes back to our appeal to the Government to engage. We are ready and the funders are ready.
Comment on this
Ms Galavan is saying there are no legally binding commitments.
Comment on this
I presume a contract could be drawn up that someone commits to do it on the condition that the State has provided the money.
Comment on this
If that would satisfy the Government, I am sure we could talk about that.
Comment on this
How much money has been raised to date? Ms Galavan spoke about the very good record of raising private funds.
Comment on this
ICML secured a pledge years ago when this project was first born for €8 million from one of the banks. Very significant levels of funding-----
Comment on this
Was that delivered?
Comment on this
No, because the project was not delivered.
Comment on this
Ms Galavan spoke of a very good record, not of pledges, but of raising money. How much money has been raised?
Comment on this
To date, ICML has itself raised for the ongoing running of the charity over €1.5 million.
Comment on this
Let us say the State spends €70 million to do this and the €25 million is not forthcoming. Maybe we have a big crash and companies that previously had a bit of extra money and were willing to do it are not willing to do it any more. What happens then? Is there a potential that we are left with a building empty that the State has paid €70 million on and then does not open?
Comment on this
Our commitment is to deliver on that, and I believe the ICML board will deliver on that. It is important to contextualise. The value of science-based industries and tech in this country is enormous. The Irish Fiscal Advisory Council has estimated that at in or around €25 billion. As Professor O'Neill said, he knows some of these companies himself. He is speaking to them on a regular basis, and we have other board members who are hard at work in that respect.
Comment on this
How much office space is ICML currently occupying at Earlsfort Terrace? Is any rent associated with that?
Comment on this
We currently have use of 65 sq. m and there is no rent for that. That was part of the 2013 agreement.
Comment on this
I welcome all of the witnesses in today. I want to start at the start. At the beginning, Heuston Gate was mentioned. Is that in Kilmainham?
Comment on this
There was a building there that ICML had looked at initially.
Comment on this
No. The OPW might be able to speak better to this, but my interpretation of it is that, at that stage, there was a site at Heuston Gate and there was a requirement for a cultural anchor. That is the point at which ICML got involved with the then Department of Enterprise, Trade and Employment and was going to be that cultural anchor, but the building was yet to be built. It did not exist.
Comment on this
Was there State funding for that project? Was the State involved?
Comment on this
I think that is more a question for the Office of Public Works.
Comment on this
The OPW had a site there. There was a lot of discussion in relation to development of the overall site, which would have involved a number of different initiatives within it in terms of some public buildings for Government use, some residential buildings that would have been sold off and some commercial buildings that would either have been rented or sold off, all of which would have created a dividend that would have funded a cultural building in it for use by cultural purposes.
Comment on this
The financial crash came and it fell apart.
Comment on this
What happened after that? I am trying to get a history. Moving on, ICML came on board. That plan was obsolete after that.
Comment on this
This was over the period of 2003 to 2008 or 2009 where discussions were ongoing in relation to development of that site. ICML, it is my understanding, along with the then Department of Enterprise, Trade and Employment-----
Comment on this
ICML was involved in that Heuston Gate project.
Comment on this
Initially, it would have been the Department of trade and enterprise. In terms of its interest in the site, I think the Department then brought ICML in as a partner on the science centre at that stage.
Comment on this
I want to move back to the charitable donations that were received. Am I correct in saying that Mr. Naylor mentioned a figure of €3.5 million in that regard?
Comment on this
We have received €3.5 million in total donations.
Comment on this
It has gone from €3.5 million to €300,000. What has the money been spent on?
Comment on this
There is no building. I am just trying to figure it out. Ms Galavan mentioned that ICML had a great track record, but it has received €3.5 million so far in charitable donations, it has €300,000 left and there is nothing to show for it. What did the charity spend the money on?
Comment on this
A significant portion - Ms Galavan will outline it - was in terms of the planning side for the children's museum in the first place.
Comment on this
We are talking about a long period with €3.5 million. There has been a staff, albeit small-----
Comment on this
Particularly in the early stages, an awful lot of work was done on the design plans for the fit-out.
Comment on this
No. The design plans around the exhibits themselves. Experts were brought in. Some international experts were brought in at various stages. It is the fit-out for the science exhibitions.
Comment on this
I am just trying to work it out in my head. If the OPW goes ahead with this, the project is going to cost it €70 million. Is that correct? That is just for the building.
Comment on this
Yes, but €40 million of that has to be spent on that building regardless of its end use. The cost in terms of providing it as a science centre is €30 million.
Comment on this
I want to go back again. We have spent €3.5 million of charitable donations.
I cannot see what would have cost €3.5 million to get some plans. I cannot understand about the designs, and the designs that have been done are probably out of date at this stage. If it was originally the Heuston Gate building that project was thinking of and then it was doubled in space, meaning it has to be a completely new layout again. I am just wondering about the €3.5 million from charitable donations, different tech companies and philanthropists. That has gone. The way I see it, money is running out for this organisation and it is wondering what it will do next. There is a building with the OPW where it has free rent. Am I correct in saying the organisation has an office for which it receives free rent?
Comment on this
And the organisation is not charged any rent?
Comment on this
It is a great world we live in that we live in that the organisation is not charged any rent. I do not know any other organisation that gets free rent.
Comment on this
If I could make the point that all of the information on the financials of this organisation are fully audited. It is a CLG. All the financial accounts are reported. This organisation is not hiding anything. The people who are involved are very genuine. They put their hands in their pocket and they put their money in and they want to see the mission achieved. That is why we are here today. Okay?
Comment on this
Professor O'Neill might talk to the whole area since we did-----
Comment on this
I want to move on. I have another question. On the plans put in place, did those come from the OPW or the charitable organisation? When they were submitted there was a petition signed by 50,000 people to say they did not want it in Earlsfort Terrace. Was that taken into consideration? Fifty thousand people had signed a petition to say they did not want it in the Iveagh Gardens.
Comment on this
My understanding is that the objections of that group were not the on the development of the science centre itself but the impact it would have on a particular border with the Iveagh Gardens.
Comment on this
Was there any consideration of that?
Comment on this
That was fully taken on board, as has been intimated earlier, in terms of the planning process, the inspector's report, the decision by Dublin City Council and subsequent-----
Comment on this
Was there any consideration by Dublin City Council that it would not move ahead with this project because 50,000 people had signed a petition?
Comment on this
I think that was dealt with in the planning process. I am not sure what consideration Dublin City Council gave to that, to be frank.
Comment on this
Okay. Returning to the staff, how many staff are there in the charity?
Comment on this
At the moment, we have two. Can I just make one point of clarification? Earlier, the Deputy talked about charitable donations of up to €3.5 million. A significant amount of that funding came from the Government in the early stages-----
Comment on this
And it is gone. It is down to €300,000, so it is all gone.
Comment on this
I am just going back to the original intention of the project. It was very much ICML working in tandem with the Government.
Comment on this
When was the first donation from the Government? It actually gave State funding to the project. When was that first amount of money given? How much was that?
Comment on this
People keep coming into this committee and not having breakdowns.
Comment on this
Sorry, but if I may interject here, there is a table - figure 5.4 of the Comptroller and Auditor General's report - that sets out the Government contributions
Comment on this
So, how much did the Government give?
Comment on this
At that stage, when the Comptroller and Auditor General published his report in August, it would have been in the region of €4.273 million, which would have included legal fees until then and various contributions by us in relation to the work we did on the development of the site.
Comment on this
That would have been in addition to the €3.5 million?
Comment on this
No, this is included in the Government spend of €4.273 million. I am not clear-----
Comment on this
That was by public bodies. Some of that may have been accounted for by ICML as part of its income. I do not think I would characterise grants from Government bodies as donations. I think it has to be treated separately. Donations are a separate matter.
Comment on this
It is just that Mr. Naylor said to me at the start - I took note when he spoke - that it was €3.5 million in charitable donations.
Comment on this
I have always said it was from private-----
Comment on this
I am just getting back to the fact that the group has said it has a great track record but when I look at ,this I can see that €3.5 million was put into this and there is nothing to show for it.
That is my questions finished.
Comment on this
What an absolute shambles. It is unbelievable. I direct the word “shambles” at the Department of public expenditure and the OPW. I do not direct it at the group. As a former teacher and because I am glass half full on this, I recognise that when this is built, it will be one of the most positive pieces of work that this country has ever done in relation to science, technology, engineering or mathematics. It is a shocking indictment of this State that a legal obligation was made to build this museum and it has not been done. The witnesses came in here today and none of them will take any slack for the fact that this is still not done despite entering into a legal obligation. This is not directed personally towards Mr. Jenkinson but to come in here today and basically say that the Department of public expenditure is throwing its hands in the air and saying it will not take this on and will not approach any Department to take it on is shocking. These people are here today in good faith, I believe. They want to make good progress, but successive Governments, including my own party, which was in government, have failed to deliver on this legal obligation. It is a shocking indictment of this State.
On the commitment that was made, if someone made a legal obligation to build me a home, I would expect it to be built. It is as simple as that. That is in plain, normal English for any member of the public.
I have one question to the ICML on its own oversight and governance on this. When it knew there was not a sponsoring authority, how did it continue to negotiate this?
Comment on this
Sorry, I am not totally clear on the question.
Comment on this
ICML knew there was not a sponsoring authority but it continued to negotiate on the building of the centre.
Comment on this
I have continued to reach out on a very consistent basis. In the last year and a half, I have written repeatedly to some Departments. I have reached out to about seven Departments.
Comment on this
Ms Galavan said that October was the last time she had communicated with the Minister for public expenditure, the Minister of State at the OPW, and the Minister for higher education. In ten or 15 seconds, if she had the three of them in front of her now, what would she say to them?
Comment on this
Talk to us. This is a project full of merit. As we know, the corporation tax take in Ireland coming from science-based and technology industries is enormous. It is estimated at maybe €25 billion. This is an opportunity to give back. There is an employment pipeline that we cannot meet. It is currently being met by about 40% through migration. That is only growing. We are talking to these companies and they are concerned on that level. What a wonderful place to communicate with children-----
Comment on this
In relation to other stakeholders like Science Foundation Ireland, Research Ireland and particular universities like my own in Cork, what engagement is ICML having on the building of a science museum like this? Obviously, it is naturally going to be positive. Professor O’Neill is here from Trinity College but what about all stakeholder engagement?
Comment on this
It is an active process. We are talking to people all the time. The universities will have to be involved in this for definite. So will big pharma and all the companies I mentioned. One of my jobs is to talk to companies at the moment and try to encourage them to get on board. They keep asking me what is going on here. It is dragging on forever. The problem we have at the moment, as we all agree, is it is a bad history here.
It is an unfortunate history. We have to move on from it to deliver this. The most important message I would give on that question is that the Government has the same ambitions as us. Research Ireland is doing a great job. It is funding really core research. I am on the European Research Council, which will be coming to Dublin next June. We are all on the same page on this. We can build on what we have already achieved with science funding. As the Deputy correctly said, this is essential for the future education of our young people. That is our view in any event. We can be proud of it.
Comment on this
Let us say, for example, that the board got a communication in the morning to the effect that the Government was walking away from this and was not going to do it. If the Government wrote or telephoned in the morning or if one of the Ministers who, disgracefully, have not responded to the ICML responded in the morning and said that the Government was walking away, would the ICML take legal action against the Government? I do not want to be bluffed on this. I want a straight yes-no answer.
Comment on this
That conversation has not even happened.
Comment on this
I am sorry. I just cannot answer that question because-----
Comment on this
Does Ms Galavan believe, without having a conversation with the board about it, that the ICML should take legal action against the State if it does not commit to building this?
Comment on this
I remain optimistic that the Government will talk to us. That is where we are. We are here today to appeal to this committee and to appeal-----
Comment on this
I will ask again, and I am looking for a clear answer. Would the ICML take legal action against the State if it turned around in the morning and said it was not building this?
Comment on this
I am sorry. I just cannot answer that. That is a matter for the board of the ICML.
Comment on this
We have three members of the board here.
Comment on this
We are not empowered to make board decisions.
Comment on this
That is a difficult question, Deputy. There are ongoing discussions and conversations.
Comment on this
I will go to each of the members of the board. Yes or no.
Comment on this
Our mission is to get a science museum. The objective is to get that in the most orderly way possible. The board will discuss it in that light. I would see positive interaction from this board, in spite of some of the background that we talked about here. That would have to go to the board. There are people on the board who really want a positive approach, and I think the other board member here might-----
Comment on this
I appreciate that. I will move on.
Comment on this
Let us imagine for a minute that this does not happen. I would be very disappointed, as a scientist in Ireland, working in a university and heavily involved in research, because of what has been done already. I came in in 2022. A lot has happened since that time to try to build up the case, raise money and plan. Whenever I am in a city, I go to a science centre and examine it, and ask whether we will use this or that. There have been huge efforts on the board, and many people are onside when it comes to this. The most disappointing part is that we will not be able to engage with these companies to donate substantial investment into this with us. If it does not happen, it will be a shameful thing for Ireland, as a country, especially with our overall position in science internationally, where we need more of this kind of thing. That is well known.
Comment on this
I fully agree. Mr. Jenkinson is a principal officer in the Department. Does he have direct oversight of this? Why was he sent here today?
Comment on this
I am the principal officer who is over the OPW Vote section in the Department of Public Expenditure, Infrastructure, Public Service Reform and Digitalisation.
Comment on this
That is why Mr. Jenkinson were sent here today.
Comment on this
Is the Department of public expenditure basically saying, “We are not going to do it. Another Department can, and we will negotiate with them, but we are definitely not going to do it”?
Comment on this
No, I think it is slightly different. In any case of public expenditure, there is a sponsoring authority that is responsible for that policy area and that knows the policy, what the programme for Government is and what the strategy is, and-----
Comment on this
In Mr. Jenkinson's opinion, who should be the sponsoring authority? Is it the Department of higher education, the Department of enterprise or the Department of education?
Comment on this
A number of Departments have been involved in this project, and that is set out in the Comptroller and Auditor General's report. The Department of Public Expenditure, Infrastructure, Public Service Reform and Digitalisation does not have a role in selecting a sponsoring authority. A sponsoring authority needs to own a project.
Comment on this
The Department of Public Expenditure, Infrastructure, Public Service Reform and Digitalisation has a significant role in this, considering that the OPW comes under its remit. If it is not going to take this on board, it should be proactively engaging with other Departments in order to get one to become the sponsoring authority. Does Mr. Jenkinson agree? Yes or no.
Comment on this
There were different processes under way to try to identify a sponsoring authority previously. That is referenced in the chapter and, maybe, in the ICML's statement. There have been processes under way there. Obviously, there has also been ongoing arbitration, and you would have to be careful of what is going on there in terms of your engagement. That only finished in December, so that would have hindered-----
Comment on this
If we were looking at this in the context of the glass being half empty, which I hope is not the case, I can see the three organisations here coming back in a year’s time and no progress having been made. That is the difficulty. It has been a failure since 2003. It is a continuing failure that we have not engaged further on this. Ms Galavan has written to the Department that Mr. Jenkinson works for. She has written to the Minister of State who is over Mr. Conlon. She has written to the Minister for higher education. No one has engaged with her.
Comment on this
I will address that. In relation to the letter sent to the Minister of State with responsibility for the Office of Public Works, I acknowledge the receipt of that letter. I have met Ms Galavan on a number of occasions in the past six months.
Comment on this
Has Mr. Conlon meet her since her letter in October?
Comment on this
I have met Ms Galavan regularly to update her on the OPW's position on the development of the project, making it quite clear, as I have outlined-----
Comment on this
Would Mr. Conlon say that the OPW is just saying, “We will take a step back. We will wait for the Department of public expenditure or another Department to tell us what to do.”?
Comment on this
As I have outlined, we are involved in this as a contracting authority, not a sponsoring Department.
Comment on this
Mr. Conlon is saying that the problem lies with the senior Minister.
Comment on this
What has beleaguered this project has been the absence of a sponsoring authority for quite a number of years. There are many ways that can be interpreted, but the fact is that we are the contracting authority. We do not have a funding envelope for this. In terms of the development of the National Concert Hall, for example, we are in the throes of delivering one project there on behalf of the Department of culture, and we are working hard on a second on behalf of the Department of culture. That is the involvement we have.
Comment on this
I will finish with a general statement. I hope to God, for the benefit of educators and children in this State, that we will not be back here in a year’s time having the same conversation that we are having now.
Comment on this
I thank the witnesses. In the first instance, I acknowledge that whatever misgivings we may have about the legal strategy deployed by the charity, many of them were not even involved when that strategy was put in place. I also acknowledge that they are here voluntarily. As the previous speaker indicated, the unholy mess here does not rest not at their feet, whatever legal strategy they may have adopted, and that has been teased out a little.
I have a particular line of inquiry I want to pursue, but, first, Mr. Jenkinson mentioned that the arbitration finished in December. Is that it? Does Mr. Conlon know if that is the end of the arbitration process between the OPW and the charity?
Comment on this
The arbitration finished on 15 December. That arbitration makes a final award, and I think details have been provided to the committee. It sets out various obligations that we have to comply with over the next year.
Comment on this
The arbitrator has made a final award in the arbitration between the Office of Public Works and the charity.
Comment on this
Can Mr. Conlon provide a copy of the final award from the arbitrator?
Comment on this
I do not think we have it. Can Mr. Conlon provide a copy?
Comment on this
In that final award, what does the arbitrator say the OPW has to do?
Comment on this
I believe the charity is also familiar with the award. Perhaps Ms Galavan would like to outline that while Mr. Conlon is looking for his paperwork.
Comment on this
Ms Galavan can deal with that, if she likes.
Comment on this
The arbitrator has determined that the building has to be completed by the end of December 2029.
Comment on this
The arbitrator has determined that the OPW has to complete the building by the end of 2029. Is that correct?
Comment on this
Is the OPW legally bound by this determination?
Comment on this
Mr. Conlon is the Accounting Officer.
Comment on this
I am the Accounting Officer as a contracting authority for this. As has been clearly outlined in the Comptroller and Auditor General's report and in various discussions, I do not have a funder for this project. I am in a very awkward position.
Comment on this
I am genuinely sick to the back teeth of this line - and I would say that anybody watching is also sick of it - about a parent authority. In real terms, and this is the first time we have heard it, the OPW is bound by an arbitration agreement to deliver the building by the end of 2029.
Mr. Conlon, as the Accounting Officer, is obligated to do that. How is he going to do that? He should not tell me he will go to the parent authority or ring whatever Minister. How is he going to do that? It is his legal responsibility, so could he just tell the committee how he is going to do that?
Comment on this
To be very frank, at this stage I cannot do it without funding.
Comment on this
No, but what is Mr. Conlon going to do? Is he going to breach the agreement which he is bound to deliver?
Comment on this
That will be the subject of further discussion with various parties. I cannot say at this stage.
Comment on this
We will discuss it with our parent Department and we may discuss it with ICML.
Comment on this
Could Mr. Conlon just explain "parent Department"? Will he discuss it with the Secretary General of the Department of public expenditure and reform? What will he discuss with him – that his options here are to breach the arbitration agreement? Is that the option he will be discussing? I just want to be clear.
Comment on this
Everyone was very clear on that: the position I am in is that we either build or breach.
Comment on this
Could Mr. Conlon hold on? There are two options: build or breach. He will go to the Secretary General of the Department of public expenditure and reform and tell him that he has two options: to build or breach. Is that his decision or the decision of the Secretary General of the Department of public expenditure and reform?
Comment on this
They are options that may emerge over time. At this stage I am not in a position where I can make a commitment to build this in the absence of funding. That might require further negotiation with ICML. The parent Department may sponsor it but the position I am in today is that I cannot commit to building this without funding being in place.
Comment on this
How can Mr. Conlon knowingly and actively take a decision like that to breach a legal agreement that the State is bound to, and that he is responsible for?
Comment on this
I am not taking the decision now. I am saying that these are the options that may pan out. I am in a very difficult position.
Comment on this
It is kind of like a form of State vandalism or anarchy that the State is contracted to do something, bound by an arbitration agreement to do so, which presumably the High Court could enforce, and Mr. Conlon would knowingly go to the Secretary General and say one of the options here is to sort of not do what this agreement is binding him to do.
Comment on this
There is a range of possibilities in this. I am not in a position I want to be in; I have inherited it.
Comment on this
That is well ventilated at this point.
Comment on this
When is the meeting? When is Mr. Conlon picking up the phone to whoever to have this discussion?
Comment on this
That is something I have to consider with my colleagues.
Comment on this
Is Mr. Conlon only considering it now? When was the arbitration agreement made?
Comment on this
On 15 December, and we are in February now. When will Mr. Conlon pick up the phone to the Secretary General to say "Look, I either have to breach a contractual agreement here or to force a negotiation." When is that happening? When is that meeting taking place?
Comment on this
I have had discussions both with the Department of public expenditure on this and-----
Comment on this
Mr. Conlon had discussions with who?
Comment on this
Who in the Department has Mr. Conlon had discussions with?
Comment on this
The vote is the principal officer.
Comment on this
Yes, okay. Is that the level Mr. Conlon is discussing it with?
Comment on this
I have mentioned this to my own Minister and to the Minister-----
Comment on this
His own Minister. Okay. What did he say in relation to it?
Comment on this
He is in a very difficult position, as am I.
Comment on this
Does Mr. Conlon mean the Minister of State with responsibility for the OPW?
Comment on this
At what level of the Department of public expenditure and reform has Mr. Conlon engaged - the Secretary General, assistant secretary or principal officer? Which level?
Comment on this
I have discussed it at various times with the Secretary General of the Department of public expenditure.
Comment on this
What has the Secretary General of the Department of public expenditure and reform said to Mr. Conlon in the course of those discussions?
Comment on this
In terms of his contribution to this, he is awaiting some options that may become clear over the next while.
Comment on this
I think it will be subject to further discussions.
Comment on this
But what are the options? That is what I am asking Mr. Conlon.
Comment on this
As I said, it is a very difficult position for me to be in-----
Comment on this
We know all that but what are the options?
Comment on this
-----to ventilate this in this forum because some of this may be subject to me taking further legal advice.
Comment on this
Further legal advice. We are going back to the lawyers.
Comment on this
I cannot take steps without being clear on my legal position here. It is quite clear as I see it at the moment that I have this obligation. It is also quite clear that I have no funding.
Comment on this
Mr. Conlon is now the Accounting Officer. Whether he likes it or not, that is his responsibility to fix. He will not be able to come back crying to this committee saying it was all his predecessors. The obligation legally right now is on him to solve this mess. What is his action plan to solve this mess?
Comment on this
The obligation is on me to move this forward. That will involve discussions with my parent Department and that includes my colleagues here, my own Minister, the Minister for public expenditure and reform and the Secretary General. It may involve discussions with ICML. It may also involve discussions with other Departments as to whether they are going to step in at this stage. I cannot predict at this stage how that will evolve over the next number of months.
Comment on this
It does not feel to me though that Mr. Conlon is acting with any degree of urgency in relation to this issue in particular when he is bound to deliver it by the end of 2027.
Comment on this
Let me assure the Deputy that I am very conscious of my obligations.
Comment on this
I know Mr. Conlon is conscious of his obligations but I feel like he is going to be comfortable coming back here in a year saying "Well look, no parent authority contacted me." Where will the accountability be then, as we have an ongoing situations of an empty building doing nothing?
Comment on this
I am not comfortable in the position I am in now. It is not that I have never been uncomfortable in this; I have always been uncomfortable with this since I have taken over as Accounting Officer.
Comment on this
We know all that but now Mr. Conlon is the man. He is the boss. He is responsible now so it is his job to fix it.
Comment on this
I cannot at this stage - in particular in this forum, which is very public - set out how I will deal with this over the next while but I will be speaking to the people I have mentioned on an ongoing basis. I cannot predict at this stage what way those obligations will go. People said earlier that this needs to be discussed and negotiated. That may well happen but I cannot say right now – to be fair to everybody here – what steps we will take.
Comment on this
I just want to be clear it is Mr. Conlon's responsibility as Accounting Officer to fulfil a contractual agreement that he is bound to, whatever decisions the other party takes. That is his obligation. If the State stops fulfilling legal obligations we are in a very serious scenario. He should not come back to this committee in a couple of months saying, "No parent authority has shown up", because that is not a sufficient excuse. He has to take the bull by the horns here, as the Accounting Officer, to find a resolution to either deliver, which is what he is bound to do by 2027, or find some magic – pull a rabbit out of a hat – but it has to be on him. He has to drive this process because there is nobody else who is legally obliged to do so as matters stand. Does he accept that?
Comment on this
I accept the legal obligation I have. I accept the legal position I am in. I accept what the Deputy is saying but I have to have those discussions and negotiations with other stakeholders, as I have outlined.
Comment on this
I will just make one further point if I can. It is very difficult to have these discussions, particularly with other funding Departments, where a legal strategy has been pursued and the Departments do not want to get involved. That makes it very difficult for me.
Comment on this
Is Mr. Conlon knocking on the door? They are writing letters and getting no replies. He is an Accounting Officer for the OPW. He is the head of the OPW. Is he knocking on the doors of relevant Departments to ask how he is going to discharge his contractual obligation without their support?
Comment on this
I have spoken to the Secretaries General of the Departments that have had an involvement. This has been set out in the report. They are all very reluctant to engage. I am being very frank. They have been very reluctant to engage because this has been mired in a legal process.
Comment on this
The State overall has a responsibility here. The moneys are mounting up. That incredible building – the monument that is Earlsfort Terrace - has been vacant for ten or 15 years at this point.
Comment on this
The monument that is Earlsfort Terrace-----
Comment on this
I refer to the second part; the part that is not the National Concert Hall-----
Comment on this
I have been in the building myself. It is extraordinary. It is just sitting there doing absolutely nothing. The OPW is the title owner of it and has a leasehold opportunity potentially.
Comment on this
The development of the overall complex, as Deputy Geoghegan knows, is contingent on NDP funding. Two elements are going through that process. One contract has started. One will hopefully start in the next couple of years, which will be a very significant project. Then we are left with the north wing, which we are discussing here.
Comment on this
Mr. Conlon has to fight to resolve this issue.
Comment on this
I thank everybody for being here. After watching what has played out here over the last 11 minutes, how could Ms Galavan possibly say from the point of view of the organisation she is representing here that the State is not over a barrel?
Comment on this
That is a bit of an unfair categorisation of it.
Comment on this
The transcripts will show the very difficult position everybody involved finds themselves in now, whereby the OPW has been tasked to deliver this building by 2029 and it does not have a red cent to do that.
Comment on this
ICML entered into a partnership arrangement with the Government over 20 years ago.
Comment on this
I was ten when that arrangement was made. That is a long time ago.
Comment on this
Yes, but it is important to go back to the origins of the project. It was a decision that was taken by the Government at that stage. ICML came forward and worked really hard.
Everyone on the board of ICML at that stage, and indeed since then, has given it their time and energy voluntarily and-----
Comment on this
Now what we have is a mandate that the OPW must deliver by 2029. If we play that out in practical terms, it means that the OPW must somehow find €70 million in budget 2027. It is going to be budget 2027 at this point. By the time it goes through proper procurement to deliver a tender package and all of that, we already know it is going to be breached. Who instigated that process? The organisation that Ms Galavan is here to represent today-----
Comment on this
It is because of the value of the project. As I said earlier, science and science-based industries and technology contribute enormously to the-----
Comment on this
We are not questioning the merits.
Comment on this
-----corporation tax receipts in this country. There is a very significant employment deficit. It is really important that we encourage Irish children into science subjects because that leads, ultimately, to what can be a very valuable career in science. The way we look at it is that we look at what the young scientist competition did for the Collisons - loads. It is really important to remind-----
Comment on this
That is fair enough, but what we are talking about here-----
Comment on this
With respect, no one is questioning that. No one has questioned that this morning at all.
Comment on this
I understand that. Was it in the programme for Government to deliver a national science centre?
Comment on this
It is not in the programme for Government.
Comment on this
Has it ever been in a programme for Government?
Comment on this
Yes, I believe it was originally back in-----
Comment on this
It has not been in the past three; I have checked.
Comment on this
Has it been in a national development plan?
Comment on this
-----in relation to trying to get it into the programme for Government.
Comment on this
I am not around here very long, but what I have learned with frustration is that if something does not make the programme for Government negotiations or make an NDP allocation, then signs are on it that it is not going to happen.
Comment on this
As I said earlier, we remain very optimistic that it will happen. It is an important project. It needs to happen. Ireland remains the only country in the OECD that does not have a national children's science centre. We really believe in it.
Comment on this
Government Ministers should in theory be lining up and beating down ICML's door, wanting responsibility for this project. There could be five or six different Departments that would want this in theory, but there is something wrong.
Comment on this
I will address that. That is exactly the point. We need-----
Comment on this
We accept the merits of it.
Comment on this
It is a mystery to me why they are not.
Comment on this
We can talk about that there is a bad smell about this whole thing.
Comment on this
We got to get beyond that now and move forward. There is an urgency behind this now. This is partly because, as the Deputy said, the legal position, which is another unfortunate. Having to go to arbitration-----
Comment on this
It is not unfortunate when that is the intention. It cannot be unfortunate and intentional and that is what the witnesses are representing today. That was the intention. The intention was to bring about this.
Comment on this
The intention is to deliver on the project that the Government agreed to. That is the strange thing here. It was meant to be delivered on 20 years ago. As the Deputy correctly said, it still has not. What we are trying to do now is hopefully get the committee's help to get this back on track and hopefully get this sponsored by the Government in some way.
Comment on this
How many Departments have the witnesses written to in the past 12 months seeking a meeting?
Comment on this
Six or seven different Departments.
Comment on this
Apart from Ms Galavan's engagements with the OPW, how many other Ministers or Department officials has she met with about this project?
Comment on this
I have not been successful in getting a Department official meeting. It is about six or seven Departments that I have written to.
Comment on this
Does Ms Galavan think any of this in part due to the questionable presence of a business case? Let us say that State investment in this project was parked and the Collison brothers came to Ms Galavan tomorrow and said, "Do you know what? We are going to invest in this. We are going to give you everything you need to get this delivered, but how much is it going to cost us annually to keep this going?" The witnesses cannot answer that question. For example, they should be able to say how much phase 1 of the project is going to cost and, if we add the planetarium on top of that, how much it is going to cost. Those details should be fairly easy to rhyme off as part of this proposal. Ms Galavan is seeking meetings, but she will not be able to bring the details to the meetings.
Comment on this
Those details depend on, for example, whether there will be an entrance or admission fee to the science centre, or whether the Government would like this to be a free facility like the National Gallery of Ireland, the National Museum of Ireland, etc. There are very key-----
Comment on this
Ms Galavan could do projections based on those different proposals.
Comment on this
Will Ms Galavan publish those with us?
Comment on this
We could certainly share them. This comes back to wanting to engage with a Department. Until those questions are answered, it is impossible to be definitive. We need answers and engagement to be able to publish the business plan.
Comment on this
Ms Galavan said a bank was pledging €8 million. Which bank was that?
Comment on this
That was a good few years ago. That was AIB.
Comment on this
Has that pledge expired now?
Comment on this
What is the total value of the live pledges that are accurate right now?
Comment on this
I cannot give the Deputy a figure on that right now.
Comment on this
I am talking to big pharma in the US and describing the project to them. They are engaging. However, as it is stuck, we cannot progress with those donations that might ultimately come in from those sources. For the very reasons the Deputy is addressing, in a way, there are unknowns in this project. The only way to answer those unknowns is to move this to the next stage and get a Minister or Department to help us. Then we can begin to go back to those companies again. I would not say it is getting a bit embarrassing, but there is an urgency now behind it. We have several companies interested. Now is the time to engage with them and try to deliver on it. That is the stage we are at.
Comment on this
Does Professor O'Neill have that schedule of pledges or donors or is this just a informal conversation?
Comment on this
It is my connections in those companies. It is ad hoc at the moment. Of course, we will have a massive fundraising campaign behind this to deliver, as Ms Galavan said, €25 million. That is the ultimate amount of money we are looking for here in total. It is a work in progress. We are using board members and our connections to try to do this. It is a key goal to receive philanthropic finance to back this whole project.
Comment on this
I wish to ask Mr. Sreenan about it from an architectural perspective because I would not know anything about it. If we were starting from scratch back in 1998 and we were proposing to develop a national children's science centre in the way in which it is being proposed currently as per the planning permission, would it be done on the current site, or would a greenfield site be more optimal?
Comment on this
That is a tricky question to answer because that is complete speculation. All I can-----
Comment on this
From an architectural design perspective, what is the easiest way to get children in the door?
Comment on this
I will answer it this way. It is clear from today that what the project has suffered from is scrutiny in its totality. That scrutiny is carried out through the infrastructure guidelines. That addresses issues like that. Demand analysis is, in a sense, where we go from a long list of options that take the investment rationale and demand analysis at a preliminary level and then they test it. That is where those questions are teased out. What has played out here today has demonstrated the difficulty it presents because it has not happened. It would be speculation at best if I was to speak to the Deputy about greenfield versus brownfield because there are so many variables.
Comment on this
I accept that this is speculation, but if the OPW was forthcoming with a greenfield site - an alternative site - that could deliver a realistic timeframe of how this project could progress, maybe outside of Dublin or somewhere else around the country, would the witnesses entertain a proposal that would see this national centre being delivered somewhere else?
Comment on this
I could only entertain that if there was a sponsoring Department.
Comment on this
As I said earlier, we want engagement. We are not discounting any conversation with the Government. Let us have that conversation. I appeal again to this committee to recommend that a Department or somebody is assigned to talk to us so we can start this very important conversation.
Comment on this
I can try to answer that. It is a complicated question. On the best possible location for this, international best practice is that these centres are inclined to be in city centre sites that are very accessible and attract the crowds, including people walking by. Accessibility becomes a key issue. That would be a preference, but not necessarily definitive. These things need to be examined.
Comment on this
I thank Deputy Farrelly. I have a number of observations and questions. During my time on the Committee of Public Accounts, I have never been as frustrated as I have been during this meeting and our previous engagement with the OPW on this subject. It is nearly like Groundhog Day in that we are hearing the same answers. The same stand-off has been in place now for many years.
Unfortunately, it has put the taxpayer on the hook for considerable ongoing costs into the future with no end in sight despite there being a legal agreement, which I think is questionable to be able to achieve. I never thought I would be quoting some of my schoolday science in here, but this certainly defies the law of gravity because everything does not come back down when it goes up. The costs are only on the way up and they are certainly not going to come down at this point or at any point over the next number of years.
This is a question to the Department of Public Expenditure, Infrastructure, Public Service Reform and Digitalisation. We have gone through a process in terms of the national development plan and the reviews. The witnesses said there were no formal proposals or no asks. Was there any engagement with any Department on the prospect of including funding for this in their portfolios?
Comment on this
No, there was no ask, basically, from any Department. Obviously, the OPW has made us aware of the ongoing arbitration.
Comment on this
There was no ask despite the fact there was a legal process and arbitration going on in the midst of that. We had the previous round of arbitration, and the findings and recommendations from that. There were no asks. Again, no Department wants to touch this. We know about the planning permission, and we know the deadline. I do not think we have received a copy of the arbitration. It would be useful to get that. However, we know about the planning permission. When is the planning permission due to expire on this?
Comment on this
In 2029. Okay. We know that the national development plan runs to 2030. That obviously pushes that deadline out. There is a timeframe here that is going to be very difficult to achieve. We are in a stand-off situation whereby no Department and no Minister want to touch this. We have current Ministers who in the past have made comments about the viability of this. I will come back to that in a moment. However, this goes back to a series of fundamental things. I take issue with the suggestion that this is "unfortunate". The chain of events that has led to this is more than unfortunate. It has put the taxpayer on the hook for considerable costs.
I want to go back to the very start when this was put in place. I take exception with the briefing notes that were supplied by the witnesses. They state that the contract - this is going back to the original contract - was drafted by the Chief State Solicitor's office and signed on 29 October 2003. Of course, there is a glaring omission from that because we now know that the clause that the Chief State Solicitor's office asked to be included in that was not included. The lease was not, therefore, drafted by the Chief State Solicitor's office. Am I right in saying that?
Comment on this
What I was trying to convey there is that ICML was negotiating in good faith with the OPW. As far as we were concerned-----
Comment on this
I am not questioning that. I am asking because that information is misleading because the conditional clause that was recommended by the Chief State Solicitor's office was not included in it. That is the nub of the issue here. That is why we are where we are. I take exception with the briefing document. It is misleading for anybody.
Comment on this
I will move on from that and go back to 2003. Ms Galavan might talk very briefly about the original proposal that led to ICML being selected. What kinds of costs were going to be incurred by the State in the initial proposal that was put in?
Comment on this
That is a long time ago. I cannot really speak to that, but if there is-----
Comment on this
Ms Galavan made a statement earlier that it was always envisaged that there would be ongoing costs to the State. To go back to that original proposal, it was to be incorporated in the cultural element with the Heuston Gate development. ICML was selected on the basis that it would not require any direct State funding. That is the basis on which ICML was selected. Am I right in saying that?
Comment on this
As paragraph 5.16 sets out, we did find a financial plan which was given to us by OPW. It states: "The plan set out the projected cash flows of the project and included a State subsidy of €100,000 per annum towards operating costs." That was in 2003. I do not know whether ICML would have proposed a figure like that or whether it was a figure that the OPW speculated might be required.
Comment on this
I do not know whether Mr. Conlon has any information but, certainly, the information that has been given to this point is saying the original proposal was that this operation was to wash its face going forward.
Comment on this
I would need to further review the files. I think the very original proposal would have indicated that there would have been no State funding required. I think that was later amended to some State funding.
Comment on this
What started off with no State funding being required has now led to a situation where we are on the hook for €70 million going forward.
Comment on this
I am sorry; there was no State funding required in 2003 in terms of the capital development because it was to be financed within the overall gain. In terms of the recurring costs, which I think is the issue here, there would have been no State obligation at that stage.
Comment on this
Moving forward now, the figure of €70 million is based on analysis back in 2024. Has that been recosted at this point given the cost of inflation?
Comment on this
I did talk through this earlier. That cost is a total development cost, so it is the cost to the Exchequer for the capital delivery. It is separate to the operation. It has been contemporised, as I said earlier, to-----
Comment on this
I would say there is an allowance in there. There is an assumption in there around construction inflation and contingency. The contingency would reflect the level of design that was costed at the time, if that makes sense.
Comment on this
Mr. Conlon gave the figures for the two rounds of arbitration, which were €500,000 and €576,000. What way was the cost on that? How much did it cost the OPW? Was the OPW's cost included in that or what is the split?
Comment on this
I would probably need to double-check that. I think they are the total costs but let me double-check that.
Comment on this
I think in relation to the OPW costs, our own legal team might have been funded through the CSSO. I will need to double-check that and get back to the Cathaoirleach.
Comment on this
As set out in paragraph 5.70 of the chapter, the legal costs incurred to date - this was for the first arbitration process - included a payment of €307,500 towards ICML's legal costs and OPW legal costs of €255,252. I am not sure whether that includes any provision in relation to the Chief State Solicitor's office. That may be counsel.
Comment on this
Mr. Conlon might come back to us. In terms of ICML's legal approach to this, who led the negotiations in the arbitration?
Comment on this
Does the Cathaoirleach mean who was our counsel and-----
Comment on this
Our counsel at that time was Michael McDowell and Caren Geoghegan.
Comment on this
I believe the board was kept up to date at all stages, yes, and-----
Comment on this
I know there are certain board members from a legal background. Were they directly involved?
Comment on this
No, absolutely not. All board members have given voluntarily of their time and have never received any payment ever.
Comment on this
Okay. At one point, there was an alternative location proposed, Stack A, that had originally put in an expression of interest going way back to 2003.
That was not looked at. I do not think a proper evaluation was carried out as to why it was not selected. That was put forward as an option. That was stack A down by the quays. Why was it turned down by ICML?
Comment on this
I have not heard stack A referred to. Is that the CHQ building?
Comment on this
Okay. That was obviously before my time but I believe a number of locations were considered at the time. Advice was taken, including from international people involved in museums, and it was rejected as unsuitable for a science centre.
Comment on this
It was a long time ago but I will see if we can locate it.
Comment on this
That would be extremely useful. Over the years, as has been alluded to, State funding has been received. I have some figures here for donations and grants. In 2001, there was € 17,000 and that ramps up to €106,000 in 2004, then to €100,000 and €300,000. In 2007, €796,000 was received in donations and grants.
Comment on this
They are Ms Galavan's organisation's financial statements, I think.
Comment on this
Could we get a breakdown of that money? Ms Galavan said her organisation was getting State funding. Obviously, the Department of enterprise was involved. Was the organisation receiving grants from other Departments along the way?
Comment on this
Yes, there were grants from a number of Departments. I believe that funding is included in the C and AG's report. There were also grants from other agencies of the State.
Comment on this
Could we get a breakdown of those - the year, how much it was for and what Department or sponsoring agency furnished those?
Comment on this
I will open it up to members for a second round. I know there are a lot of questions. Is it agreeable to witnesses that we open it up again? We will try to keep it to five minutes each. Is that okay with our witnesses? Yes, thank you. We will go back to Deputy Neville first.
Comment on this
I thank the Cathaoirleach. I note he quoted school science books but the one thing that jumps out at me is a quote from Cool Hand Luke, also used at the start of the song "Civil War" by Guns N' Roses: "What we've got here is failure to communicate."
Comment on this
Exactly. Great movie. What jumps out at me is that failure to communicate. When was the last time all the witnesses were in a room together - the OPW, the Department of Public Expenditure, Infrastructure, Public Service Reform and Digitalisation and all the rest?
Comment on this
Does the Deputy mean all three parties?
Comment on this
I am not aware of all three of us being in a room together before.
Comment on this
Okay, so it is a start. That is something to work with. There is the legal question that is almost like a cloud over the whole thing. If we could move away from that legal difficulty, that would be the most positive thing.
This is a question for ICML. Did Ms Galavan reference who was negotiating the lease agreement on ICML's behalf at the time? Was that what she referenced a few minutes ago, just to clarify?
Comment on this
No. The Cathaoirleach asked who our representatives were in the last arbitration.
Comment on this
Okay, sorry. Who was at the lease agreement at the time?
Comment on this
It is before my time. I can try to find out who negotiated that.
Comment on this
Thanks. If Ms Galavan could just send back in the information after she gets it, there is no problem there.
Ms Galavan might have mentioned it our someone else might have asked the question regarding staff. Is there two staff working with ICML now? Is that correct?
Comment on this
Was that the case in the previous year?
Comment on this
I started in 2024. There would have been possibly one staff member-----
Comment on this
The ICML's financial statements, I think, listed no staff. They stated there were no staff members, but was there a professional consultancy basis?
Comment on this
It might have been a contractor in a role but it became a part-time role. I just wanted to clarify that. There is no question. I was just curious. In trying to bring this to fruition, staff were brought on to replace a contractor so it was not an additional resource, as such.
Comment on this
Okay, that is fine. Has ICML ever talked to Explorium?
Comment on this
Obviously, that group would not be here in this setting but it is another organisation in this sphere, I suppose. Just to that point, has ICML had discussions with them?
Comment on this
We have. I had not been to Explorium before I started in this role. I went out there and met the promoters of Explorium and we continued to talk to them as we do all operators in the State in that sphere.
Comment on this
Does ICLM see itself running a similar business model?
Comment on this
Similar but different. Professor O'Neill can probably speak to that better than I can.
Comment on this
That is a key question. If you look at publicly funded science centres versus private, there are differences between them. The private ones are inclined to lean more towards entertainment. There is a science part of it but there is a different goal because it is commercial. Second, the art is plugged into the education programme. We connect to the curriculum. There is no obligation on Explorium, for obvious reasons, to do that because of the criticism of them, so there are differences. That is the reason why, around the world, science centres are publicly funded. It is always a public-private partnership.
Comment on this
Have any of the witnesses been to W5? I have been to W5 myself.
Comment on this
So it would be something in keeping with W5 in Belfast-----
Comment on this
Very much so. We model ourselves on those kinds of thing. There is a great one in Edinburgh and a great one in Manchester. They are all public-private partnerships.
Comment on this
One of the Deputies just asked the OPW if it would be stuck on Earlsfort Terrace. I know the original plan was to have one in Dublin and two others, in Galway and Cork. I totally get the city centre: people passing, walking up and down, tourists going in. It makes sense. I would be in town in half an hour. It would be grand, but I am thinking of people from Laois, Offaly and Cork, and of students - all those students, would it be easier for them to come up to a location outside the city centre? Would the witnesses be open to that? Is it about Earlsfort Terrace or is it about-----
Comment on this
From my point of view and that of the board, we like Earlsfort Terrace because it is in the city centre and there are good examples of city centre science centres. The second reason is the National Concert Hall. We love the arts connection - STEAM. That is a real positive for Ireland. We are very famous in the arts. Bringing that into this science centre would be a clever thing to do. The co-location is potentially very useful but, again, these things could be discussed.
Comment on this
The timing in relation to the NCH is also relevant. That project has just started and I know there is funding for it. It is logical for us that a building like that would be refurbished or redeveloped together. It is hard to understand how that could happen in any other way.
Comment on this
Can we get clarity from the Department of Public Expenditure, Infrastructure, Public Service Reform and Digitalisation? I know it is not in the national development plan but the Department has done a lot of work in that sphere. Essentially, that is its work. What are we planning here? The OPW has its own infrastructure budgets over the next few years. We need to figure out if it is in it or not, or what that could look like. What would ICML like to be the next steps?
Comment on this
As I have said already, we want to engage. We would like to see a Department appointed to engage with us in a meaningful way and we would like to have this conversation with a Department.
Comment on this
Since I came in, all of our engagement with the OPW has been very constructive. The chairman has been extremely helpful and has communicated. The OPW is a big of this and we will continue to work with it.
Comment on this
I hope out of today there is movement for everybody in the room. What is clear for anyone looking in is how frustrating this is for us in the room who are examining public finances, for the representatives from ICML who are championing a project, for the OPW for the legal position it is in and for the Department of public expenditure.
Our economic model is built on our commitment to science and research and so on. The first time I heard Professor O'Neill was in the biomedical centre talking about the crazy research prioritisation programme that was planned around 2012 or 2013. We are a long way from that. Deputy Lawless announced €750 million for the INSPIRE programme and the Department of Further and Higher Education, Research, Innovation and Science and so on. A children's science centre is important and it fits into the broader picture.
As a champion of this project, ICML would be mad to walk away from two commitments and then a binding arbitration determination to deliver on those commitments. If ICML were a sports club or youth centre in my community, I would tell it to not to walk away because it will then get nothing. It has essentially been told that it has nothing, but at least it has the binding arbitration determination.
The difficulty for Mr. Conlon is that he has been told that the OPW either performs the contract, which is the fit-out, or it will have failed to comply with the arbitration determination and therefore will face costs for the legal proceedings and possible compensation or some sort of settled compensation. That is where I see how things sit.
All of those outcomes are incredibly expensive for the State. That is very clear. They are incredibly expensive for the State, and we do need more details around the 2013 decision, in particular, because that doubled down on our obligation. I do not know why the OPW was so specific about the Earlsfort Terrace site. Why did it not try to seek a commitment to house the centre, but not in a specific location. Was it because the OPW was doing other work on that site and it thought it could just fold this in as part of a bigger project? There are big questions around that 2013 decision. When we look at the documents, we will reserve the right to look at that.
I am going to go back to Mr. Jenkinson because he is the representative of the Department. It has a dual role here. It is the parent Department of the OPW and it has departmental responsibility for public spending. If nothing happens here, we are going to spend more and more public money. It is very clear that no one in the room is saying there is legal advice that this will go way. No one is saying that sitting this out somehow reduces the cost. I know the Secretary General of the Department is not here but I do not see this as three parties. There is a Government commitment with a number of Government agencies and Departments dealing with it and then there is ICML. It is a legal dispute. We have to seek a resolution and the OPW has to have the support of the Department of public expenditure on this because the problem is not going to go away and it has dual responsibility. It is the parent Department and it is responsible for ensuring that we do not spend another half a million euro on arbitration in four more years' time.
There are huge questions around the oversight of this, but, in the absence of any other Department, it ultimately falls on the Department of public expenditure because it has those responsibilities. Perhaps that is something that Mr. Jenkinson needs to take back to the Secretary General. We deserve the right to have the Secretary General of the Department of public expenditure here before us on this as well, but we have to resolve this one way or another. It is not going to go away. Deputy Geoghegan is right when he says that Mr. Conlon is the man as he is the only one who has been left holding this because the OPW signed that contract and on the second occasion doubled down on it, so there are big questions there, but the solution will not come from the OPW alone.
Comment on this
I want to make a comment in relation to that last point. The Vote for the Office of Public Works discloses a contingent liability. My view is that it will fall to the Vote for the OPW if there is not somebody else who is willing to fund it. It has become an OPW project and partly it is of its own doing because of the commitments it signed.
Comment on this
The C and AG always makes helpful contributions.
Comment on this
No, but the implications of it falling on the OPW without a sponsoring Department, in the absence of additional funding being provided, will mean that I will have to consider reducing expenditure on things like flood schemes, which is something I would find almost impossible to do, particularly given what we now know are our climate obligations and the climate change, and even what happened in recent weeks. I told Deputy Geoghegan about the difficult position I am in. I recognise the deep obligation, but this brings up more and more difficult options that have to explored.
I am also very concerned that if no funder is found, I could be found to have a recurrent funding obligation beyond the construction, which needs a lot of consideration.
Comment on this
I thank everyone for bearing with us. It has been over three hours at this stage. I very much appreciate it. I want to start with ICML. Ms Galavan was cautious earlier when we discussed possible further legal action. I understand that. There is a legal obligation from the State here. Is it ICML's absolute determination that it will be fulfilled?
Comment on this
It is our absolute determination that we want to see a national children's science centre in Dublin and in Ireland. I am not sure how far the Deputy is talking about there, but, as I covered earlier, I cannot really go-----
Comment on this
Is ICML resolutely determined to deliver the project?
Comment on this
It is something that the board of ICML is extremely passionate about and has remained passionate about for over 20 years.
Comment on this
To be fair, she mentioned a number of times that ICML is open to discussions and negotiations. It is clear today that it is certainly extending that hand. What is the response ICML is getting? It has sent letters. It has got acknowledgments. How would Ms Galavan characterise the State's response?
Comment on this
That is an understatement. Is Ms Galavan frustrated, disappointed or angry?
Comment on this
I am definitely frustrated. Since I joined, it has been my focus to try to reach out and to get that dialogue with government that is so badly needed. It is difficult.
Comment on this
Does Ms Galavan feel stonewalled at the moment?
Comment on this
It is difficult when there is no meaningful response.
Comment on this
It is not an exaggeration to say that she is being stonewalled at present. Those are my words.
Comment on this
Does Ms Galavan disagree with them?
Comment on this
Deputy Geoghegan, to be fair, went into some detail in terms of what the OPW is trying to do proactively to resolve the situation. Mr. Conlon mentioned that the OPW is engaging with the Department of public expenditure. Are there records of that engagement?
Comment on this
No, it would have been phone calls and-----
Comment on this
If the public accounts committee sought information in relation to that engagement, are there any records?
Comment on this
That is not satisfactory, but that is where we are. In relation to the arbitration determination in December, the overall commitment was to provide the facility by 2029. Was a month stipulated or is it 2029 as a whole?
Comment on this
The month of December, at the end of 2029. Are there stage commitments in that or is there an overall commitment?
Comment on this
There are a number of terms to the agreement. I will step through them as quickly as I can. I think term two is probably the key term and that is, before the end of this calendar year, to have, in plain English, the project ready to go tender.
Comment on this
Are there built in penalties in the arbitration determination? What happens if the OPW does not meet that commitment in 12 months?
Comment on this
I am not a lawyer, but I assume it would constitute-----
Comment on this
Are there penalties for breaches laid out in the agreement?
Comment on this
So, we can go to 2029 without any penalties in the intervening period and, if the OPW has not delivered by the end of 2029, we will be back to square one again.
Comment on this
I think maybe the question is for ICML. The terms have been set out here and so-----
Comment on this
The obligation from the arbitration is on the OPW and the State. My point is, I presume it is a detailed enough determination. It sets out stage commitments and an overall commitment, but what we are hearing is that there are no penalties until the end of 2029 when the whole thing will have to be reviewed. In other words, it will not be delivered in 2029 unless there is movement very quickly.
Comment on this
It is sequential but there are no built-in penalties. If in two years there is no movement, nothing happens.
Comment on this
I suspect something will have happened if the second term of the award has not been met, but I do not want to say either way. I am trying mind my words here because-----
Comment on this
-----I am stepping through what the terms of the final award are without reading from top to tail the arbitrator's document.
Comment on this
It seems strange. It clearly lays out commitments again, but it does not clearly lay out how they are to be fulfilled.
Comment on this
It places obligations on us to do certain things at certain times. I do not think these types of arbitration awards normally have penalty clauses, but it is an arbitration between two parties. If we were to not meet our requirements as set out in arbitration, there may well be a reaction from the other party at that stage.
Comment on this
I understand. The OPW and the science centre have had engagement, as Mr. Conlon said earlier. How would he characterise that engagement? Are there meetings and minutes for those engagements?
Comment on this
I have met Ms Galavan and various directors of the board over the last year or so and we have had ongoing discussions about what the present position is. For my part, I have continuously relayed to them the difficulties I am having in finding a sponsor for this.
Comment on this
There would not be any records of that engagement. Is it informal as well?
Comment on this
We should have had the arbitration final decision before we came into this hearing, because we are getting a drip feed of essential information.
Comment on this
I acknowledge that, but we should have been given it beforehand. It has dripped out that, by the end of 2029, the building and the museum will have to be delivered.
Comment on this
No, sorry, deliver the shell and core building.
Comment on this
Pardon me, deliver the shell and core building.
Comment on this
Deputy, can I make a point? This week we received a copy of the arbitration finding. I think the witness is under the impression that that is giving it to the PAC-----
Comment on this
-----but we do not necessarily share every document that we get from an audit point of view. That is causing a bit of confusion.
Comment on this
Fair enough, but I have no criticism of Mr. Conlon.
Comment on this
The other point is that I was not asked for an opening statement or a briefing. If I had been, I would have given it.
Comment on this
That is fair enough too. There is not criticism in relation to that. However, it has come out that, before the end of 2029, the OPW has to deliver up this shell of a building ready to go for a museum to be put into, is it?
Comment on this
Ready to be fitted out, okay, so that has to be delivered. Before the end of this year, as Mr. Sreenan has just explained, the project to make the building ready to be fitted out has to be ready to go to tender. Is that right?
Comment on this
Correct, that is the project as is consented for.
Comment on this
What other conditions are in the final decision? For example, what, if anything, does it say in relation to recurrent revenue, which we have had a lot of discussion about?
Comment on this
That was not part of the arbitration agreement.
Comment on this
It is not part of the arbitration agreement. Is the OPW legally bound in respect of the revenue element of this project?
Comment on this
As Accounting Officer I have no legal obligation on that. However, I do have concerns that if it is funded by the OPW, that no other sponsor is in place and there is a funding gap, I would be asked to find it. I find that a very real issue.
Comment on this
Is it Ms Galavan's understanding as well, that the State has no legal obligation when it comes to the revenue component of this project?
Comment on this
Does the Deputy mean the operational costs on an ongoing basis?
Comment on this
Yes, that is less clear than the commitment in terms of the building and the fit out. Going back to the origins, it was always ICML's understanding that the State would be involved in the running of a national children's science centre.
Comment on this
I might just walk the Deputy through them because-----
Comment on this
Okay, as long as I get a minute extra. Go ahead.
Comment on this
Three has to do with the pre-qualification of works contractors. Four has to do with the subsequent selection of works contractors. Five has to do with compliance with planning conditions. Six has to do with carrying out the work to the highest standards in terms of the specification and it will go to market. Seven is a requirement for me to publish a quarterly report. Eight has to do with the quality of the works and nine is an issue to do with costs.
Comment on this
So Mr. Sreenan is bound to publish a quarterly report as he is the OPW architect, is it? So when is the first-----
Comment on this
Not to publish but to provide it to the ICML.
Comment on this
When is the first quarterly report due?
Comment on this
So in a month's time. What will be in this quarterly report?
Comment on this
Again, I do not want to frustrate the Deputy with the answer but it would be speculation at this point. We are here today. We have had the-----
Comment on this
It is for sure, yes. We have had the final award just before the Christmas break-up. That is all under review.
Comment on this
So the first reporting obligation on the OPW arising from this arbitration agreement is 31 March.
Comment on this
Just to be careful on the wording in the commitment, it is on a quarterly basis.
Comment on this
Yes, so 31 March, whatever the quarter of this year is. The first reporting obligation is in five weeks' time.
Comment on this
As matters stand, the report will say that a parent authority has not been found.
Comment on this
I do not want to predict what will be in the report at this stage. It may refer to that. It may also refer to the works we will be doing in relation to getting a team in place to tender for work and stuff like that.
Comment on this
Is the OPW already in the process of getting the tender to works together?
Comment on this
But Mr. Conlon said he had no funding to do anything.
Comment on this
I am very conscious of two things here. There is the funding element, which is a key issue, but there is also the obligation to bring it to tender by the end of the year, and it is up to me to do that.
Comment on this
We are having discussions in-house on that.
Comment on this
Okay. I will conclude on this. I think Deputy Kenny said glass half full. Despite my tough line of questioning, I am glass half full and I buy into the general premise of the project, notwithstanding all of this. However, I am also really concerned about the fiscal element and the obligations on the State. In an ideal world, we would work out where the science goal and the fiscal costs meet one another somewhere in the middle. I find it hard to go beyond believing that there is any other Department apart from the only Government Department that has "science" in its title that could be the appropriate Department to take this on. I fully acknowledge that it is a brave Minister who would put their hand up and say, "Let's work this out." Given the amount of obligation imposed on Mr. Conlon, I hope that he can assist in leading this process. To whoever is watching this hearing today, maybe there is a way that we can find ourselves out of this. As matters stand, it is almost a farce that the OPW is going to keep getting this project ready without a parent authority. I think the Department that has science in its title, at least on a without-prejudice basis, and perhaps the Minister could engage with the charity. That has merit on the fiscal side and on the science goal.
Comment on this
I want to follow up on one of the questions that Deputy Geoghegan put about whether anyone else is on the hook for meeting the operating costs. We did not find any evidence of any other Department being on the hook for operating costs. An added complexity in this is that in order to have something in the building, if it were available at the end of 2029, there is probably a long lead time as well. There is also the question about how it is funded or financed as it is going ahead, so that if ICML is going to take possession of a building, it needs a lead time to prepare the exhibits, commission them and have them delivered.
Comment on this
I ask Mr. Conlon to restate his answer on the tender. I am not sure what was said about the preparation of the tender.
Comment on this
The final award imposes an obligation on us to prepare a tender for issuing in December of this year. Deputy Geoghegan criticised us for doing nothing, but we are having internal meetings in relation to how we put our team together to get that work ready, so we can issue the tender.
Comment on this
The OPW is doing work to prepare a tender for December.
Comment on this
We have already done a lot of design work, so it is building on the work already done.
Comment on this
I do not know how we are three hours into the meeting, and that is the first time we have heard that. That is another important piece of information. Are we going to tender on this in December?
Comment on this
That is our legal obligation. That is the problem.
Comment on this
To pick up on that point, it is frustrating that we get this information at the back end of the meeting. I acknowledge what Mr. Conlon said in terms of the documentation going to the Comptroller and Auditor General's office.
Comment on this
To be fair, I was not asked for an opening statement or to provide a briefing. If I were, I would have.
Comment on this
I appreciate that. Nonetheless, it is an important piece of information that there is work being carried out now within the OPW. Obviously, it is legally bound to do so. It is Mr. Conlon's full intention to move to tender.
Comment on this
It is my legal obligation, and I take that seriously. I have said in the Comptroller and Auditor General's report, and in previous evidence, that I respect the legal obligation I am put under, but it puts me in a very difficult position from a funding perspective. If I put something to tender and I cannot fund it, I am in a very difficult legal position.
Comment on this
That is if Mr. Conlon puts it out to tender, and there is a successful tenderer, but no funding.
Comment on this
I could also be sued for that. Then, I have the other issue that if we do construct this, and there is a gap in the recurrent funding, that could land on me as well.
Comment on this
There are serious issues here in a multitude of areas. I would put the question to ICML. The ICML witnesses are aware of the process and the work that has commenced within the OPW. However, the OPW is in an impossible situation in many regards. If the OPW does not comply with that by issuing the tender and awarding a contract, which it is legally obliged to, will ICML go back down the legal route at that stage? What is the intention?
Comment on this
As I have said, ICML absolutely does not want, and has never wanted, to go down the legal route. There has been absolutely no discussion at ICML board level in relation to more legal routes. That is really all I can say for the moment. It would be a matter for the board. We are here, and we are again appealing to the Government to grant us a meaningful conversation.
Comment on this
We had some discussion on the business case. There was some criticism going to back to 2018, when we had the former chair of the OPW before the Committee of Public Accounts, although that was before my time. He was critical of ICML due to the failure to bring forward a cost-benefit analysis. At that stage, I think he stated that he had repeatedly asked for a cost-benefit analysis to be produced and furnished by ICML.
Comment on this
That is a bit confusing. A cost-benefit analysis, I thought, was something a Department would do. In terms of business plans, we have certainly circulated business plans to people we were dealing with over the period. I presume that would have been the Department of trade and enterprise, and there was an interdepartmental committee as well. Various business plans were certainly conducted and circulated. When, in 2018, it became clear that a business appraisal had not been carried out by the State, we carried that out in an attempt to be helpful, and that was circulated to a wide number of Departments.
Comment on this
I completely agree with Ms Galavan's representation of where the obligation lies. The obligation is on the public sponsoring agency for a project to prepare an objective review and analysis of any spending proposal. That is clearly what is required under the Department of public expenditure's rules, but because there is no sponsoring agency, I would expect any promoter of a project who was looking for public funding to put forward a business analysis and business case. It would be looking at the demand for the service, the cost, where the funding is going to come from and all of that. However, it still behoves the sponsoring agency that is going to look to Parliament to provide funding for a project to explain it, look at it objectively and make a recommendation as to what represents good value for money, or otherwise.
Comment on this
That is where we are with the current stand-off position. There is no sponsoring agency. There is a question for the Department of public expenditure with regard to not having that sponsoring agency. Concerns have been expressed here about a private operation, Explorium, that has been established since the original concept, and whether two science centres in the one city would be viable. Is that an area where the Department of public expenditure could embark on a piece of analysis?
Comment on this
I think that would have to be captured in the business case. A business case would look at demand because that would be a key element of a business case carried out by the sponsoring Department. You would expect that to be reflected in it.
Comment on this
I will try to bring things to a head. It is deeply frustrating for everyone in the room. That this is the first time the three parties have sat in the one room is extraordinary for something like this, which has dragged on for over 25 years and cost nearly €5 million at this point, with the State on the hook for €70 million. There are Ministers who sat in here at the time but who now say we do not need this, and ask how on earth we are progressing a children's museum that we do not need because we have a perfectly good one in Sandyford. That was said by a former member of this committee who is now a Minister. There is a view that we do not need it and that it is not going to progress, but the State is still on the hook here.
A break is needed. We will publish a report on foot of our engagement, but ultimately, and I do not think it is on anyone here, a political decision needs to be taken by a Minister and by the Government to bring this impasse to an end, and end this stand-off. It is unbelievable. It is shocking, to say the least, that this has the potential to drag on until 2029 and into 2030, with no end in sight. The “stick the head in the sand” approach has failed and has left the State more financially exposed. The appeal coming out of this meeting by everyone here is to end this crazy situation. I would encourage everyone to pull together to bring this impasse to a conclusion.
Comment on this
I am two thirds “glass half-full” on this one. I am very optimistic about this because there is such a strong case for it, and we are all agreed that we need this. A Minister needs to take it on. I would say to that Minister that this will be the jewel in the crown of Irish science if we get this right together. We are building on what the Deputy said. We have Research Ireland, we have great investment in science in this country, we have a great cohort of teachers and we have our education system. This is very much part of that continuum. We will build on that success. It will be good for our school kids and good for industry, and the economic arguments are very strong. To me, the case is so compelling. It has been stuck for so long, and the negativity around it has put everybody off. We have to move on, or otherwise, we will miss a huge opportunity here.
Comment on this
I would add one thing. The Oireachtas joint committee on education in 2023 made the point that it wanted to see the national children's science centre. It recommended that the national children's science centre, in gestation for many years, should be built as a matter of urgent national priority.
Comment on this
I am sorry to bring the tone down again. The witnesses have been great, and we will welcome them all back together again.
Comment on this
The Comptroller and Auditor General mentioned something interesting about the obligation of cost-benefit analysis, and how it is for the State entity. It is now in the hands of the OPW. Should the OPW be carrying out a cost-benefit analysis now, notwithstanding the unusual situation that it is not the parent party?
Do they have an obligation under public spending codes, etc., to carry out this analysis now as they are moving through the tendering process that they are bound to by this arbitration?
Comment on this
I did raise that as an idea when we were drafting the chapter but I think the situation we are in is that the OPW deals with buildings and the provision of buildings. It does not deal with running museums or the State contribution. It is at a higher level. The only thing that I can think of in the circumstances is that the Irish Government Economic and Evaluation Service, which is part of the Department of public expenditure, might take a higher-level view looking at the overall project and the ask from ICML, which, as I understand it now, is that there will be a substantial State funding element. I can see that as the only way for this to break. Then, afterwards, it can be decided which Vote the money goes through. At the end of the day, it is up to Dáil Éireann to decide what money is provided in what Vote for what service.
Comment on this
I thank Mr. McCarthy for that. We will publish a report on this. I think members will agree that all options need to remain on the table. Key to bringing this impasse to an end is dialogue. That needs to involve all parties, and all options need to be looked at, whether it is a public private partnership, PPP, including another operator in the city. Every option needs to be looked at here to move things forward because it is an extraordinary situation.
That concludes our engagement for today. I thank the chief executive officer and her officials from the National Children's Science Centre for attending today. I also thank the officials from the Office of Public Works, the Department of Public Expenditure, Infrastructure, Public Service Reform and Digitalisation and the Comptroller and Auditor General for their attendance. Is it agreed that the clerk will seek any follow-up information and carry out any agreed actions from the meeting? Agreed.
The committee's next meeting is on Thursday, 19 February 2026 when we will engage with officials from the Department of Justice, Home Affairs and Migration and representatives from the Department of Public Expenditure, Infrastructure, Public Service Reform and Digitalisation.