Telephone service for Kerry public works site

Summary

A wayleave delay had held up the installation, which involves about 4½ miles of linework. Work was expected to start within a fortnight, with service by the end of August.

John O'Leary Mr. J. O'Leary Fianna Fáil

asked the Minister for Posts and Telegraphs the cause of the long delay in providing a telephone service on the site of a large public works project for a person (name supplied) in County Kerry; and the steps he proposes to take to provide service to enable work to proceed on the project.

Comment on this

The delay was due to difficulty in obtaining the necessary wayleave for erection of the pole route to serve the applicant. The installation involves approximately 4½ miles of linework including about 1½ miles of new pole route. It is hoped to commence the work within the next fortnight and to have service provided by the end of August.