Dublin Bay oil refinery appeal
The Minister could not comment on the proposed refinery’s merits or pollution effects because a planning appeal was before him. He said there was no timetable; 400 people objected, most requesting an oral hearing, which would be required if the application proceeded.
asked the Minister for Local Government if he will make a statement regarding the proposed oil refinery in Dublin Bay and the effect it may have on pollution in the Dublin City area.
Comment on this
An appeal has been made to me on behalf of the proposed developers against the decision of the planning authority refusing permission under the Local Government (Planning and Development) Act, 1963, for the erection of storage and processing units for petroleum products, together with ancillaries, on a site east of Pigeon House (B) power station. It would not be appropriate for me, therefore, to make any comment on the matter.
Comment on this
It has been there for some time. Permission was applied for in April, 1973 and a refusal was issued in June of that year. The appeal was lodged in about July, 1973.
Comment on this
Apart from the merits of the appeal can the Minister tell us anything about the time schedule?
Comment on this
There are 400 objectors and about 75 per cent of those have requested an oral hearing.
Comment on this
In other words, the Minister refuses to say whether the application will be proceeded with?
Comment on this
Deputy Haughey has been a parliamentarian for too long to expect me to comment on something which will eventually come before me in a judicial way.
Comment on this
I should not dream of asking the Minister to do that, but I thought there was a hint in what he said that the application might not be proceeded with.
Comment on this
All applications are not proceeded with, particularly ones that have been around for a long time and which, for one reason or another, have not been pushed.