Summary

An outline extension plan has been submitted, but a feasibility study is needed because of the site’s terrain before plans can be finalised. The Minister said work was aimed for late 1975, though early 1976 might be more realistic.

asked the Minister for Education if he has sanctioned plans for the extension to Ballina vocational school, County Mayo.

Comment on this
Mr. R. Burke

An outline plan for this extension has been submitted by the vocational education committee. Because of the nature of the site it has been found necessary to undertake a special study in order to decide the most economic approach to the next phase of building. It is hoped that the results of this study will be available soon and plans can then be finalised.

Comment on this

Did the Minister say one plan had been received?

Comment on this
Mr. R. Burke

Yes. The VEC have already submitted an outline plan showing the approach favoured by them.

Comment on this

Will the Minister state if the VEC also submitted a report from a quantity surveyor saying the plan submitted by the VEC was the cheaper of the two plans prepared by the architect?

Comment on this
Mr. R. Burke

Because of the nature of the terrain it is necessary for the VEC to initiate a feasibility study. I understand this feasibility study will be completed shortly and submitted. I have not yet received it.

Comment on this

Will the Minister state if the guarantee that work would start in late 1975 still holds?

Comment on this
Mr. R. Burke

We are aiming for the end of 1975 but in view of the delay, which was not caused necessarily by my Department, it might be better to say early 1976.