Ballycasheen school construction

Summary

Plans for two proposed schools at Ballycasheen are under urgent review, but a start date is not yet known. Kenny said sanction had only recently been forthcoming and traced a three-year delay to the lack of communication after the site was approved in 1971; he said the project was now progressing and had acted on O’Leary’s request to press for urgency.

John O'Leary Mr. J. O'Leary Fianna Fáil

asked the Minister for Finance when work will commence on the new primary school at Ballycasheen, Killarney, County Kerry.

Comment on this
Mr. Kenny

Sketch plans for two proposed new schools at Ballycasheen have been prepared and submitted by an architect engaged by the school manager. These are being examined by the Commissioners of Public Works as a matter of urgency but it is yet too early to say when building work is likely to commence.

Comment on this
John O'Leary Mr. J. O'Leary Fianna Fáil

Is the Parliamentary Secretary aware of the concern of parents and teachers in the Killarney area with regard to additional primary school facilities and would he treat this as a matter of extreme urgency?

Comment on this
Mr. Kenny

It is being treated as a matter of extreme urgency now but, up to some time ago, sanction had not been received. Sanction for the grant was not forthcoming. It is forthcoming now and this is being treated as a matter of urgency now.

Comment on this
John O'Leary Mr. J. O'Leary Fianna Fáil

Is the Parliamentary Secretary confirming that sanction has now been issued for the grant?

Comment on this
Mr. Kenny

I will tell the Deputy exactly what the position is. The delay regarding this school happened at the beginning. The Department of Education advised the commissioners on 6th November, 1970, that a new national school should be provided on the eastern side of Killarney town. The site offered at Ballycasheen was inspected by the commissioners and in March, 1971, the Department were informed that that site was suitable. That was 1970 and 1971. The commissioners did not receive any further communication regarding the school until October, 1974. That is when the delay occurred.

Comment on this
Seán Treacy An Ceann Comhairle Labour Party

Question No. 9.

Comment on this
Mr. Kenny

I am not blaming any Department. There has been a delay of three years. From 1974 until now everything has been going well.

Comment on this
John O'Leary Mr. J. O'Leary Fianna Fáil

Would the Parliamentary Secretary now impress on the Department of Education and the commissioners that this is an urgent project?

Comment on this
Mr. Kenny

I have already received the Deputy's communications about that and it has been done.