Dáil
‹ Ceisteanna—Questions. Oral Answers. - Mayo Piers.

Kilcummin Pier improvements

Summary

An engineering report on proposed Kilcummin Pier improvements is nearly complete after revisions and consultations. Calleary urged urgent action over safety concerns, and Kenny undertook to have the report finished within weeks.

asked the Minister for Finance when work will commence on the pier at Kilcummin, Ballina, County Mayo.

Comment on this
Mr. Kenny

The Commissioners of Public Works at the request of the Department of Agriculture and Fisheries have been investigating proposals for improvement works at Kilcummin Pier. Their engineer's report on the latest of these proposals is in preparation and will be furnished to the Department of Agriculture and Fisheries in the very near future. It will then be a matter for that Department to decide upon the works to be carried out.

Comment on this

How long is this report taking?

Comment on this
Mr. Kenny

Is it the reason for the delay the Deputy wants to know?

Comment on this

Why has it taken two years to get this report?

Comment on this
Mr. Kenny

I will explain it to the Deputy. The improvements recommended for Kilcummin Pier by the County Mayo Harbour Survey team were the extension of the slip, improvement of the boatyard and provision of a bigger winch, all estimated, in July, 1972, to cost £11,000. Following local consultations the commissioners were asked by the Department of Agriculture and Fisheries to examine revised requirements and, in May, 1974, the commissioners submitted two alternative proposals to the Department. The first proposal, estimated to cost £11,500, provided for replacement of the outer half of the existing strong-wall by a similar wall in concrete, aligned in a south-easterly direction, and the installation of a two-ton winch. The second proposal, estimated to cost £40,000, provided for demolition of the outer half of the existing strong-wall, incorporation of the remainder in a new pier, 12 feet wide with a six foot wide strong-wall, and the installation of a one-ton hand-operated crane. In July, 1974, the Department requested an estimate of cost of amending the first of the schemes mentioned, by enlargement of the outer end of the strong-wall to provide a small landing platform on which a crane would be erected. Due to heavy commitments of the marine engineering staff, particularly on projects in the Galway-Mayo area, the commissioners have been unable to submit their report to the Department of Agriculture and Fisheries. However, every effort will be made to furnish the required report and estimate to that Department within the next few weeks.

Comment on this

Knowing that the Parliamentary Secretary has been on the site and that he is aware of the situation, I would ask him, as a matter of urgent priority—before somebody is drowned—to have this report completed.

Comment on this
Mr. Kenny

To the best of my ability I will have it done within the next few weeks.