Ceisteanna—Questions. Oral Answers. - Mayo Schools.
- Ballyhaunis primary school 6 speeches
The Department plans a six-classroom school, with an option to extend; the final sketch plan is accepted and the cost estimate is being sanctioned. The Minister could not give a start date but promised to give the project priority.
Seán Calleary, Mr. R. Burke
- Swinford primary school 4 speeches
A five-classroom boys’ school is planned, with revised plans and a cost estimate awaited before a grant can be sanctioned. The Minister could not say when construction would begin.
Seán Calleary, Mr. R. Burke
asked the Minister for Education the proposals his Department have for a new primary school at Ballyhaunis, County Mayo.
Comment on this
It is proposed to build a six-classroom block at Ballyhaunis, with provision for extension later if required which, with the convent school, will provide a central primary school for both boys and girls.
Comment on this
The final sketch plan has recently been accepted as suitable and the estimate is now in the course of being sanctioned. We will give it every possible priority. I am not in a position to say on precisely what date.
Comment on this
Is the Minister aware that the INTO are seriously thinking of taking action about this school?
Would he press to have this matter dealt with as urgently as possible?
Comment on this
asked the Minister for Education when work will commence on the erection of a new primary school at Swinford, County Mayo.
Comment on this
It has recently been decided to provide a new primary school for boys at Swinford comprising five classrooms instead of four classrooms as previously planned. The Office of Public Works have been asked to furnish revised plans and an estimate of cost for the larger school. When the new estimate is available my Department will sanction a grant towards the cost of erecting the new school and the further arrangements will proceed. I am unable to say at present when work will commence.
Comment on this
I thank the Minister for his reply. Is he aware of the conditions obtaining at the existing national school in Swinford? Is he also aware that work on the primary school was held up while the post-primary facilities in Swinford were being examined? Would he now seek to have the work on this school commenced as quickly as possible?
Comment on this
The case will be ready for sanction of a grant when the revised estimate is furnished by the Office of Public Works.