‹ Ceisteanna—Questions. Oral Answers. - County Sligo Factory.

Ballymote advance factory

Summary

The original site was rejected because development costs were too high. The IDA has identified an alternative site and expects construction to begin by next October, subject to planning permission.

asked the Minister for Industry and Commerce the present position regarding the building of an advance factory at Ballymote, County Sligo; and the reasons for the delay in having this project started.

Comment on this

I have been informed by the Industrial Development Authority that it was decided not to build the advance factory on the site in Ballymote for which it was originally planned because development costs proved to be too high.

The IDA have now identified an alternative site and are about to apply for planning permission for a factory on this site.

Subject to planning permission being obtained, the authority expect that construction work on the factory will begin by next October.

Comment on this