‹ Ceisteanna—Questions. Oral Answers. - Piers and Slipways. County Donegal Pier and Crane.

Sladanavoohogue Pier improvements

Summary

Work funded by a £36,000 grant has spent £17,000 to date; transporting the dragline cost £1,300. The Minister will investigate its cost, operation and relocation. Fishermen’s proposed changes are under consideration, and any extra funding may require a county council contribution.

asked the Minister for Finance the progress that has been made on the improvement of Sladanavoohogue Pier, Fanad, County Donegal to date; and if he will state (a) the amount of money spent (b) the amount yet available and (c) the cost of bringing a dragline to the site.

Comment on this
Mr. Kenny

The work, for which a grant of £36,000 was made available, has been in progress since November, 1974. Good progress has been made on the pier and £17,000 has been spent. However, the local users have asked for modifications and these proposals have been transmitted for consideration to Roinn na Gaeltachta who are sponsoring the scheme. The cost of transporting the dragline was £1,300.

Comment on this

Would the Parliamentary Secretary ask for some investigation into the exorbitantly high cost of bringing this dragline to the site for the relatively small amount of work to be done? Would he also investigate whether or not, for the major portion of the time since it arrived on site, it has been sitting there doing nothing? Would he find out if it is being charged against the job for the days and weeks it has not been operating?

Comment on this
Mr. Kenny

I will answer what I can at the moment. This was a normal but necessarily expensive operation. A dragline had to be brought in. It was taken from the Murrow coast protection scheme, County Wicklow, and brought to Sladanavoohogue Pier, Fanad, County Donegal, together with ancillary equipment, jobs, buckets and so on. It involved two heavy vehicles, a low-loader and a lorry, and had to be accompanied by a scout van. The operation involved a staff of five.

Comment on this

How long did it take?

Comment on this
Mr. Kenny

I do not know the number of days it took them.

Comment on this

It would have been weeks rather than days.

Comment on this
Mr. Kenny

I do not know. I will inquire into the other matters raised by the Deputy.

Comment on this

Will the Parliamentary Secretary also inquire whether it was necessary to move this machinery from the east coast to the north-west coast when in the north of Donegal a dragline of similar dimensions was not fully occupied? This dragline has been moved somewhere else since, maybe down south.

Comment on this
Mr. Kenny

I will inquire into that matter also.

Comment on this

I should like to ask the Parliamentary Secretary whether, due to the requests which the fishermen have made to have alterations made to the outline of the proposed improvements which has been referred to Roinn na Gaeltachta, if these alterations are considered favourably we can expect that any additional finance required will be forthcoming to cover the desirable alterations in the scheme?

Comment on this
Mr. Kenny

Does the Deputy know what the fishermen can do without?

Comment on this

It is not so much what they want but what they have omitted. should it happen that the alterations cost more than has been provided can we expect that the additional finance will be made available through Roinn na Gaeltachta?

Comment on this
Mr. Kenny

It may be made available but there will have to be a contribution from the county council.