Clifden community school completion delay
The Minister said the original contractor’s receivership caused legal and other delays, but the County Galway Vocational Education Committee expected them to be resolved soon so another contractor could complete the school.
asked the Minister for Education the reason for the long delay in advertising for tenders for the completion of the new community school at Clifden, County Galway; and if he will make a statement on the matter.
Comment on this
The legal and other problems arising where the contractor goes into receivership take a considerable time to resolve.
I understand however, from the County Galway Vocational Education Committee, who are responsible for the erection of the new school at Clifden, that these problems should now be resolved soon and the completion of the work undertaken by another contractor.