Bellevue Park and Heights connections

Summary

The Minister expects connections in Bellevue Heights in the second quarter of 1976 and Bellevue Park in the third, citing unfinished main-cable links. Murphy questioned the delay and cable status; the Minister said Greystones exchange equipment was adequate and applications could be met within about three months once cable was available.

asked the Minister for Posts and Telegraphs when residents in the Bellevue Park area of Greystones, County Wicklow, will have telephone connections; and if he will make a statement on the matter.

28.

Comment on this

asked the Minister for Posts and Telegraphs when residents in the Bellevue Heights area of Greystones, County Wicklow will have telephone connections; and if he will make a statement on the matter.

Comment on this

With the permission of the Ceann Comhairle, I propose to take Questions Nos. 27 and 28 together.

It is hoped to instal telephones in Bellevue Park about the 3rd quarter of 1976 and in Bellevue Heights about the 2nd quarter of 1976.

Comment on this

Could the Minister give me any indication of the reason for the delay, which seems quite appreciably long, in this case?

Comment on this

The fact is that main cable to serve Bellevue Park is necessary between Greystones exchange and that estate. Local cabling within the estate has been completed for the waiting applicants. The main cabling is expected to be completed about the middle of 1976, following which service will be offered to the waiting applicants.

Comment on this

My information is that the main cabling has been completed, that the internal cabling is also complete and that in fact it is a question of awaiting the connecting ducts.

Comment on this
Seán Treacy An Ceann Comhairle Labour Party

The Deputy is giving information rather than seeking it.

Comment on this

Main cable to Bellevue Park is still necessary. Main cable to serve Bellevue Heights has been provided from the exchange to a distribution point about 200 yards from the estate. Local cabling has been completed within the estate and it remains only to link the main cable to the local cable.

Comment on this

As two questions are being taken together perhaps the Chair would allow me some leeway on this matter? Could the Minister indicate whether there are sufficient lines available in the Greystones exchange, or might that also be a factor in the delay?

Comment on this

The equipment position in Greystones exchange is satisfactory and applications are being met within about three months provided cable is available from the exchange to the premises at which service is required.