‹ Ceisteanna—Questions. Oral Answers. - Skerries Harbour.

Skerries Harbour extension survey

Summary

Burke pressed for progress after survey equipment made one bore hole and then stopped. Murphy said the equipment had broken down, the survey funding had been increased, and specialised outside assistance would be used to complete the work; he said there was no undue delay.

asked the Minister for Agriculture and Fisheries the progress made with regard to the extension of Skerries Harbour; and if he will make a statement on the matter.

Comment on this

A boring survey of Skerries Harbour will be necessary before any scheme for the improvement of the landing facilities there could be formulated. I have asked the Office of Public Works to have this survey undertaken as soon as possible.

Comment on this

I accept that the Parliamentary Secretary gave that answer with tongue in cheek. The boring equipment—it certainly is boring at this stage—arrived at Skerries where one trial hole was made but then the whole operation was packed up. Would the Parliamentary Secretary like to say when the next piece of equipment will arrive?

Comment on this

Whatever about the answer given with tongue in cheek, as was stated by the Deputy, I would tell him that an additional sum of £4,000 was put into this by the Exchequer. Instead of the £3,000 originally provided for the survey of this work, which is undoubtedly essential and important, it was decided to extend the survey and also to extend the cost to the Exchequer up to £7,500. I can assure the Deputy that we have had a number of representations so far as the development work at Skerries is concerned and there is no undue delay in this matter. The Minister is particularly interested in this job. I can assure Deputy Burke that Skerries is being well looked after but the survey report must come to hand before a final decision is made.

Comment on this

The Parliamentary Secretary said that the boring equipment must be brought to Skerries and that the Office of Public Works have been asked to do this. I would point out to him that the equipment was there before and a trial hole was made——

Comment on this
Seán Treacy An Ceann Comhairle Labour Party

The Deputy is making a statement. I would remind him that this is Question Time.

Comment on this

Will the Parliamentary Secretary state when the equipment will be sent to Skerries?

Comment on this
Seán Treacy An Ceann Comhairle Labour Party

The Deputy has already asked that question.

Comment on this

I did not get an answer.

Comment on this
Seán Treacy An Ceann Comhairle Labour Party

That is not the fault of the Chair. I am calling Question No. 20.

Comment on this

I should like the permission of the Chair to answer the Deputy's question. The survey plant was sent down to Skerries in August, 1975, but unfortunately it broke down. That plant needs to be overhauled and, in order to complete the survey without more delay we propose, through the Office of Public Works, to employ specialised outside assistance. We are going outside for assistance in order to do the job and that will give an indication of the priority we attach to it.

Comment on this

It took Fianna Fáil 20 years to take the first bore hole.

Comment on this

At least we got it done. It seems the Government are going outside with work again.

Comment on this
Seán Treacy An Ceann Comhairle Labour Party

I have called Question No. 20.

20.