Dunkellin River drainage works
The Dunkellin is tenth on the priority list for arterial drainage, and no cost-benefit study has been conducted. The Parliamentary Secretary could not give a start date and expected the work to be more than two years away.
asked the Minister for Finance when it is proposed to start work on the Dunkellin River, County Galway; if any cost/benefit survey has been done on this river; and the position of the river on the priority list.
Comment on this
The Dunkellin is No. 10 on the priority list of minor catchments to be considered for treatment under the Arterial Drainage Act, 1945. It is not possible to say at this stage when a scheme for this catchment might commence. No cost/benefit study of the drainage of the catchment has been carried out to date.
Comment on this
It does not appear to have moved on the priority list in the last ten years. I understood from the late Deputy Kenny that this project had moved up on the priority list and that a cost/benefit survey was to be started. However, the Parliamentary Secretary is now saying that there is no proposal to have a cost/benefit survey carried out.
Comment on this
This is what the late Deputy Kenny said: "If I were my predecessor I could give a date, but it would be a provisional date and I might be promising things——
Comment on this
Is it the opinion of the Parliamentary Secretary that this work will be carried out in the next two years?