Summary

The questions concern approval of stage-one contract documents and phase-two tenders. The Minister said stage one was completed, stage two section one was under construction, and tenders for site investigations for a proposed dam were under consideration.

asked the Minister for Local Government if his Department has approved of the contract documents submitted by Kerry County Council for the north-east Kerry stage one water scheme.

25.

Comment on this

asked the Minister for Local Government if his Department has approved of the tenders submitted for phase two of the north-east Kerry water scheme.

Comment on this

I propose, with the permission of the Ceann Comhairle, to take Questions Nos. 24 and 25 together.

Stage one of the north-east Kerry water supply scheme has been completed since 1974. Stage two, section one, is in construction and is, I understand, expected to be completed in the autumn of this year.

Tenders for site investigations in connection with a proposed dam which will constitute a further section of this scheme are at present under consideration in my Department.