Summary

The Minister said contract documents were under review and the tender invitation had been premature because funding was unavailable; Mr. Blaney urged priority for completing the ongoing scheme.

asked the Minister for Local Government why a recent tender for the completion of Falcarragh sewerage scheme, County Donegal, was rejected by his Department.

Comment on this

Contract documents for Stage 2 of the Falcarragh sewerage scheme are under consideration in my Department. I cannot as yet indicate when a decision thereon will issue to the local authority. When it does, a decision will also be given on proposals for the acceptance of tenders, the invitation for which was premature.

Comment on this

Is it not a fact that this tender is either held up or has been rejected?

Comment on this

Tenders were submitted to the Department for approval quite some time ago and contract documents were submitted subsequently. The amount of money which was applied for was not available at the time and what I have said to Deputy Blaney is that the contracts were set before the application was made to know whether there was money to proceed with the scheme. The whole matter is being reviewed and, with a by-election coming along, you would never know what might happen.

Comment on this

It is on the right side of the line all right. However, what I would like to impress on the Minister is that it is an on-going scheme and therefore I would ask the Minister to give particular consideration to its completion, apart altogether from the consideration that a by-election will ensure that it gets.

10.

Comment on this