‹ Ceisteanna—Questions. Oral Answers. - Rural Electrification. Electricity supply to Inisbiggle
Summary
The ESB has surveyed Inisbiggle and expects to begin erecting the electricity network in about six weeks.
asked the Minister for Transport and Power when it is proposed to have ESB power provided for Inisbiggle Island, County Mayo.
Comment on this
I am informed by the ESB that the preliminary work on the extension of supply to applicants on Inisbiggle Island has commenced. The area has been surveyed and the route has been selected. It is expected that the actual work of erecting the network will commence in about six weeks' time.