We use Google Analytics to see which pages are read and how the site is used, so we know what to improve. This only runs if you accept. See our privacy notice for details.

Dáil
‹ Ceisteanna—Questions. Oral Answers. - Youth Community Projects.

Youth community projects employment

Summary

The Minister reported 37 projects employing about 332 people, with four to 30 per project; he estimated no more than 40 in Dublin, while Fitzgerald suggested 13. Projects require community sponsorship, materials and consultation with unemployed workers and unions, which has slowed expansion, especially in Dublin. Fitzgerald challenged progress against a forecast; the Minister said his target was 1,000, and clarified that a separate premium employment programme achieved about 5,500 against a 10,000 target.

Garrett Fitzgerald Mr. G. Fitzgerald Fine Gael

asked the Minister for Labour the number of schemes at present in progress under the youth community projects; and the number of persons employed in each.

Comment on this

There are 37 projects in progress at present. The numbers engaged on individual projects can vary from four to 30.

Comment on this
Garrett Fitzgerald Mr. G. Fitzgerald Fine Gael

The Minister has not answered the question. I asked for the number of persons employed on each project. The Minister has said that this can vary from four to 30 but that is not an answer to the question.

Comment on this

I have given the number of schemes and have told the Deputy that the number employed in each varies from four to 30.

Comment on this

What is the total number?

Comment on this

About 332.

Comment on this

That is an average of about nine per project.

Comment on this

It varies from a low of four to 30.

Comment on this
Garrett Fitzgerald Mr. G. Fitzgerald Fine Gael

How many of those people are employed in the Dublin area?

Comment on this

I think there are two projects in the Dublin area.

Comment on this
Garrett Fitzgerald Mr. G. Fitzgerald Fine Gael

How many people are employed on those projects in this area?

Comment on this

So far as I know the number is not more than 40.

Comment on this
Garrett Fitzgerald Mr. G. Fitzgerald Fine Gael

Thirteen might be nearer the mark.

Comment on this

As the Deputy is aware there has been some difficulty in the Dublin area in the expansion of the projects. This arises from the situation whereby each one of these projects has to be agreed with the trade union authorities. Schemes are prepared on the basis that craftsmen will not be ruled out, that there will be no loss of work opportunities for any such trade union people who may be unemployed. This has involved consultation with the building groups in the ICTU and with the training authority and before each project gets off the ground it must be agreed in consultation with these interests.

Comment on this
Mr. Kitt

Can the Minister say what is involved in the majority of these projects?

Comment on this

The requirements are that materials for work involved be provided by local authorities, community organisations or church bodies and the projects may be sponsored by any of these organisations with a community objective. Organisations putting forward projects for consideration must provide AnCO with details which show that the materials involved can be provided, that the project is part of a community effort and that the work cannot be undertaken by using normal employer-employee practice. There must be consultation with unemployed workers in the area.

Comment on this
Garrett Fitzgerald Mr. G. Fitzgerald Fine Gael

Can the Minister say how the figure of 332 compares with his forecast earlier this year of the figure of approximately 2,000?

Comment on this

My figure was not 2,000 but 1,000.

Comment on this
Garrett Fitzgerald Mr. G. Fitzgerald Fine Gael

What has been achieved is less than half that figure. As usual we have a disgraceful performance.

Comment on this

If the Deputy would look at the details of programmes he would realise that sometimes it is very difficult to reach targets. In relation to the premium employment programme I set a target which was roughly double that which was achieved. In the area we are talking of we are faced with one serious difficulty, that is, the necessity of consulting with union organisations in the area in which we wish to see projects expanding. Certain difficulties have arisen in the Dublin area. We are endeavouring to overcome these but they may result in targets not being met. The difficulties arise from the legitimate objections of unemployed craftsmen who claim that work would be lost to them as a result of the projects.

Comment on this
Garrett Fitzgerald Mr. G. Fitzgerald Fine Gael

In the interest of accuracy——

Comment on this
Seán Treacy An Ceann Comhairle Labour Party

We have dwelt for long enough on this question. We must move on to Question No. 35.

Comment on this
Garrett Fitzgerald Mr. G. Fitzgerald Fine Gael

——would the Minister repeat his reference to the premium employment programme?

Comment on this

While the target set was 10,000, we succeeded in achieving a figure of about 5,500. As the Deputy knows this programme depended for success on employer and business confidence and on the state of the market. As a result of these factors we did not reach our target. However, this does not mean that at any time we should fail to set targets or try to have them achieved but when targets are not achieved we should be accurate in giving the reasons for the failure.

Comment on this