Ceisteanna—Questions. Oral Answers. - Drainage Schemes.
- Cooleen River drainage maintenance 2 speeches
The Cooleen River is part of the completed Inny scheme, and maintenance work is planned for the coming season.
Joseph M. Sheridan, Michael Begley
- Arterial drainage programme progress 2 speeches
Daly asked about 1976 progress and 1977 plans; the Minister referred to a statement detailing schemes in progress and proposals.
Brendan Daly, Michael Begley
- River Fergus drainage priority 4 speeches
The Fergus ranks 20th among 28 major catchments; drainage work has begun in nine and is under way in two. No funds are provided for the Fergus, and the Minister could not forecast when it would be undertaken.
Brendan Daly, Michael Begley
- Cooraclare-Doonbeg catchment drainage 8 speeches
Daly sought a timetable and asked whether the catchment could be added to the priority list. The Minister said it was not on the settled lists, could not forecast when it might be reached, and had no intention of changing the lists.
Brendan Daly, Michael Begley
asked the Minister for Finance when it is proposed to carry out drainage work on the Cooleen River, Moate, County Westmeath where flooding has affected the holding of some 20 farmers.
Comment on this
The Cooleen River is a scheduled channel of the completed Inny catchment drainage scheme and will be included in the programme for maintenance works during the coming season.
17.
Comment on this
asked the Minister for Finance the progress that was made in 1976 in the arterial drainage programme; and the proposals he has for such drainage in 1977.
Comment on this
A tabular statement, which I propose, with the permission of the Ceann Comhairle, to circulate with the Official Report, indicates the progress that was made in 1976 in the arterial drainage programme and the arterial drainage proposals for 1977.
Following is the statement:
During 1976 the following schemes were
(a) In continued progress: | Boyne (major catchment) (Counties Louth, Meath, Westmeath, Cavan, Kildare and Offaly).
Maigue (major catchment) (Counties Limerick and Cork).
(b) being examined following exhibition and prior to confirmation by the Minister for Finance: | Corrib-Mask-Robe (major catchment) (Counties Mayo and Galway).
(c) under maintenance:
Catchment Drainage Schemes
Abbey | Deele and Swillyburn
Ballyglass/Knockcroghery | Duff
Ballyteigue and Kilmore | Feale
Brickey | Glyde and Dee
Broadmeadow and Ward | Groody
Brosna | Inny
Burnfoot-Skeoge | Kilcoo
Carrigahorig | Killimor/Cappagh
Clareen | Maine
Cloonburn | Matt
Corrib/Clare | Moy
Corrib/Headford | Nenagh
Creagh | Owenavorragh
Deel | Owvane
Embankment Schemes
Shannon Estuary | Swilly
During 1977 works on the Boyne and Maigue and the maintenance of completed schemes will be continued and it is hoped that the Corrib-Mask-Robe will be ready to start at the end of the year.
18.
Comment on this
asked the Minister for Finance the position of the river Fergus in the priority list of areas for drainage; the progress, if any, that has been made on the higher placed catchments; and when he expects the catchment will be drained.
Comment on this
Out of the priority list of 28 major catchments, of which the Fergus is No. 20, arterial drainage operations have been carried out in nine and are in progress in two. I cannot at this stage say when the Fergus can be undertaken.
Comment on this
asked the Minister for Finance when the Cooraclare/ Doonbeg catchment, County Clare will be drained.
Comment on this
It is not possible to forecast when the Cooraclare/Doonbeg catchment may be reached in the national arterial drainage programme of the Commissioners of Public Works, as the catchment is not included in the settled priority lists which have been upheld by successive Governments.
Comment on this
What is the possibility of having it included? What has to be done to have it included in the list?
Comment on this
As I pointed out, it is not included in the settled priority lists which have been upheld by successive Governments. I have no intention of changing that.
Comment on this
When a number of catchments have been completed is it not the policy to put on further catchments?