Deputies raised low water pressure and the risk of shortages, blaming delays in laying pipelines and securing wayleaves. The Minister said local authorities were undertaking projects to increase supply, would examine ways to reduce delays, and would take action within his responsibility to avert a shortage.

asked the Minister for the Environment if he is aware of the forecast by Dublin Corporation of a major water shortage in the Dublin area arising from the delays in laying pipelines from Ballymore Eustace to Dublin; and the action he is taking to deal with this problem.

8.

Comment on this

asked the Minister for the Environment the proposals he has to ensure an adequate water supply in the Dublin area for future years; and whether he is aware of the difficulty being experienced in recent months in the operation of the Dublin water system.

Comment on this

With the permission of the Ceann Comhairle, I propose to take Questions Nos. 7 and 8 together.

The responsibility for the provision and operation of an adequate water supply system in an area is primarily a matter for the relevant local authority. I am aware that difficulties are currently being experienced in certain areas in Dublin due to low pressures arising out of the necessity to ensure as far as is practicable even distribution of the available supply.

The Dublin local authorities have undertaken several projects which when completed will result in an increase in the water supply for the area from the present 63/65 million gallons per day to well over 100 million gallons per day. Already the capacity of the treatment works at Ballymore Eustace has been increased by 20 million gallons per day. The crux is that the extra water cannot be taken to the city area until a new pipeline has been laid from there to Saggart. Approval of the purchase of the pipes for this project was given by my Department as long ago as September 1973. Unfortunately, the local authority encountered major difficulties when they sought to acquire the wayleaves for the scheme. These difficulties were only finally resolved within the past few months.

The scheme provides for the laying of over 16 miles of special 60 inch diameter pipe. In order to speed up the completion of the project the work is being divided into three contracts. Even by this approach it will be some time before a fully satisfactory quantity of water will be available in all areas in Dublin. It is, therefore, important that consumers should be aware of the need for economy in their use of water in the intervening period.

Comment on this

Is the Minister aware of the real seriousness of this situation? Is there no way that a compulsory purchase order can be put on a complete line of wayleaves in circumstances where people in Dublin city and indeed also in the expanding county, are often without water for long periods? Because there was resistance to wayleaves since 1973 it is outrageous that this can happen in the circumstances that I am describing.

Comment on this
Joseph Brennan An Ceann Comhairle Fianna Fáil

I am calling the next question.

Comment on this

I understand that the Deputy is asking whether a blanket CPO could be put on several properties.

Comment on this

Yes, for the purpose of a wayleave for water.

Comment on this

As far as I am aware there must be separate CPOs for properties of different ownership. I am not aware whether or not a blanket CPO can be used.

Comment on this

Is there any way in which the local authorities concerned could move in and pay the arbitrator's award subsequently?

Comment on this

Of course I am well aware that it is possible that the local authority can move in where a CPO has been applied and can acquire the property, and the arbitration can come afterwards.

Comment on this

The Minister is no doubt aware that the ESB can erect poles on a person's property in a matter of days.

Comment on this

And talk later.

Comment on this

Here is something which is extremely vital to the services to the largest city in the country.

Comment on this
Joseph Brennan An Ceann Comhairle Fianna Fáil

I would like to have a question. The Deputy is making a statement.

Comment on this

I ask the Minister if he will look into ways and means of solving an important problem like this. It does not have to take from 1973 until the present.

Comment on this

I assure the Deputy that I will. As far as I am aware, the local authority have the power to move in, and arbitration and compensation can be resolved later.

Comment on this

Is the Minister aware that the city manager and chief engineer have drawn the attention of all of us to this matter? Will the Minister give a guarantee to this House that he will commit any degree of resources, finance, personnel or otherwise, to ensure that the real danger of a water shortage this summer will be averted if any action on his part can achieve it?

Comment on this

I assure the Deputy that I will take any action necessary within my responsibility to ensure that it does not happen. Guarantees are a different matter.

Comment on this

Is the Minister aware that there is sufficient water and that it is a lack of pipes to carry the water that is in question? Is he aware that the problem, as Deputy Clinton stated, is that the tremendous difficulty of getting wayleaves has delayed this pipe being layed for an unnecessarily lengthy time? Will the Minister examine the need for some similar system for getting wayleaves such as this more quickly in the future? Will he consider bringing in legislation if necessary similar to that which applies to the ESB?

Comment on this

I would like to join with Deputy Briscoe in asking the Minister whether he recalls that he told the House some months ago that he was quite happy with the CPO procedure.

Comment on this
Joseph Brennan An Ceann Comhairle Fianna Fáil

Deputy Browne has a final supplementary.

Comment on this

There are delays involved and we are examining it to see if we can improve it.

Comment on this

If the scheme was to start in 1973 and it is now 1978, should we take it that there will be a five-year delay before we are in a position where shortages will not arise? We are five years behind time apparently.

Comment on this

I would hope that we will not have any further delays.

Comment on this

Is delay likely?

Comment on this

Not in my opinion.