Dáil

Ceisteanna—Questions. Oral Answers. - Beaumont (Dublin) New Hospital.

asked the Minister for Health the estimated cost and the expected time schedule for the new hospital building project at Beaumont, Dublin.

Comment on this

The accepted tender for the construction of Beaumont Hospital was for £18.2 million approximately at prices ruling at November 1977. The hospital is scheduled for completion in March, 1982.

Comment on this

Can the Minister say how many beds will be provided here?

Comment on this

Offhand, I think it is about 750.

Comment on this

What is the ratio between the health authority and the Department likely to be?

Comment on this

It will be run by a board on which the Eastern Health Board will be represented.

Comment on this

Is the money coming from the sweep funds?

Comment on this

It is coming through the sweep funds.