Port-na-Blagh pier improvements
The Department is examining whether further works are needed at Port-na-Blagh. £3,000 has been sanctioned for lights and markers, while a possible £80,000 breakwater is under consideration; no larger funding has been approved.
asked the Minister for Fisheries and Forestry if he is aware of the dire need for improvements to Port-na-Blagh pier, County Donegal; and if there are any proposals to rectify the situation.
Comment on this
The marine facilities at Port-na-Blagh are at present under examination by my Department in consultation with the Office of Public Works to determine if new works are required in the interest of the local fishermen.
State grants have been sanctioned for the provision of leading lights and day markers and arrangements made to have the work carried out.
Comment on this
Am I correct in assuming that the money being provided is for lights and markers solely? That is all that has yet been decided?
Comment on this
Is there any hope that anything more useful and substantial is even in prospect of examination regarding the pier and facilities generally?
Comment on this
An estimate is being made in regard to the construction of a breakwater which would cost about £80,000. That is being considered at present as to whether it will make the harbour safe. The question of how effective that expenditure can be is being examined.