Cootehill housing scheme delays
Sewer rerouting and water infiltration delayed the 80-home scheme; completion was expected by late July or early August 1979, after which the council would allocate homes. The Minister agreed to ask the council to treat allocation as urgent.
(Cavan-Monaghan) asked the Minister for the Environment when 85 homes in course of erection in Cootehill, County Cavan will be completed and allocated; and if he will explain the unreasonable delay and give the expected date of completion.
Comment on this
I understand from Cavan County Council that they had expected to complete their 80 house scheme in Cootehill last March. However, delays occurred in the completion of the scheme when sewer lines for the scheme had to be re-routed because of the difficult terrain. Furthermore, it was discovered that water was infiltrating the sewer pipes and this problem is being rectified at present. Despite these difficulties, the council have informed my Department that they expect the scheme to be completed by the end of July, or in early August, 1979. As soon as the scheme is handed over by the contractors to the council the houses will be allocated to applicants on the council's approved housing waiting list in accordance with their scheme of letting priorities.
Comment on this
(Cavan-Monaghan): May I take it from that reply that the Minister's information is that the house should be allocated within the next month?
Comment on this
The scheme will be completed and handed over to the council about the end of July or in early August and it will then be a matter for the council to carry out the necessary procedures regarding allocation.
Comment on this
(Cavan-Monaghan): The general opinion down there is that the delay is unreasonable. There are many people living in unsuitable flats who were waiting for adequate housing.