Ceisteanna—Questions. Oral Answers. - County Donegal Schools.
- Convoy school extension 2 speeches
White asks when the extension will begin; tenders are due by 31 July, and work cannot be scheduled until a suitable tender is accepted and the local contribution lodged.
James White, Pearse Wyse
- Temporary classroom at Convoy 3 speeches
White requests a prefab classroom after the music room is sold; Wyse says the matter falls to the Department of Education.
James White, Joseph Brennan, Pearse Wyse
- Moyle school construction timeline 6 speeches
White asks when the new Moyle school will begin construction, noting the project has been delayed for four years. Wyse says the bills of quantities are advanced and tenders are expected within weeks, but gives no start date.
James White, Pearse Wyse
asked the Minister for Finance when work will commence on the extension to the Protestant school in Convoy, County Donegal.
Comment on this
Tenders for the erection of the extension to Convoy joint national school, County Donegal, were invited in the public press on Monday 2 June 1979 and the closing date for receipt of tenders is 31 July 1979. If a suitable tender is received, the Reverend Chairman will be asked to lodge the local contribution and the contract will then be placed. It is not possible to state at this stage when work will commence.
Comment on this
Is the Minister aware that a music room that they were using as one of the classrooms has been sold, and that these children have nowhere to go in September? Will the Minister supply a prefab classroom until the extension is built?
Comment on this
asked the Minister for Finance when work will commence on the new Moyle school, Newtown-cunningham, County Donegal.
Comment on this
The bills of quantities for the proposed new national school are being prepared and the Commissioners of Public Works hope to invite tenders shortly. It is not possible at this stage to say when work will commence.
Comment on this
Is the Minister aware that the bills of quantities were prepared last February? Surely we should be given a definite date as to when it should go out for contract. This has gone on now for four years.