‹ Ceisteanna—Questions. Oral Answers. - Trim (Meath) Vocational School.

Trim vocational school construction timeline

Summary

Planning was revised to provide for 250 pupils, and working drawings, a bill of quantities and tendering remain before construction can begin. The Minister expects work to start this year but gave no firm commitment on timing or funding details.

asked the Minister for Education when Meath VEC provided their observations to him on the proposed schedule of accommodation for the new vocational school at Trim. County Meath; the steps taken by his Department in the matter since then; and when he expects work on the school to commence and to be completed.

Comment on this

Agreement was reached with the County Meath Vocational Education Committee in June 1979 in relation to a schedule of accommodation for a new vocational school at Trim to cater for 275 pupils overall and an acceptable outline sketch scheme was received in my Department on the 29 April 1980. Subsequently, because of enrolment trends, it became necessary to review the question of the number of pupil places to be provided in the new school. Following discussions with the committee, it has now been decided that provision should be made for 250 pupils and planning will be resumed on that basis.

It is not possible at this stage to indicate when building work may commence.

Comment on this

Will there be a significant delay in the originally intended commencement time as a result of the downward revision in the number of places to be provided?

Comment on this

I do not think so. We are increasing them by 25 per cent on the existing enrolment. That is a significant number, but it should not have any effect on the process of planning or building.

Comment on this

What remaining steps must be taken before work will commence?

Comment on this

The revised schedule of accommodation for 225 pupils was sent to the CEO in October 1980. As a result of a deputation which came to me on 19 November, I raised the figure to 250. On 5 February 1981 the building unit was informed that 250 pupils places was the basis for the planning.

Comment on this

Would the Minister answer the question I asked: what further steps must be taken——

Comment on this

We just go ahead with the working drawings on 250 pupil places.

Comment on this

What steps have to be taken between now and the date on which building will commence?

Comment on this

The normal ones are the working drawings, the bill of quantities, and the tender. We can start after that.

Comment on this

Is it proposed to start the school this year and has financial provision been made for this?

Comment on this

I expect it will start this year but I do not want to be more positive than that.

Comment on this

Has the necessary money been made available?

Comment on this

As a matter of fact, I am embarrassed by the amount of money I have for building schools.

Comment on this

Would the Minister embarrass some of the vocational education committees throughout the country and give them some money so that they can be embarrassed too?

Comment on this

That is what I am doing.

Comment on this
Edward Collins Mr. E. Collins Fine Gael

The Minister's embarrassment is not shared by many school managers.

Comment on this