Dunboyne telephone exchange delay

Summary

The Minister said Dunboyne’s exchange building was completed in 1976, equipment installed and tested in 1977, and cable works finished in 1980; staff facility adaptations still delayed opening. The exchange will expand capacity from 600 to 2,000 lines, while 137 applicants were waiting. The Deputy criticised the delay and sought to raise the matter on the adjournment.

asked the Minister for Posts and Telegraphs when the new telephone exchange in Dunboyne, County Meath was completed; when the equipment was installed; if the exchange is yet in operation; if not, why; and the number of additional telephone lines that can be provided in Dunboyne when the exchange comes into full operation.

Comment on this

The new exchange building was finished in July 1976. Installation and testing of equipment was completed in October 1977. Extensive cableworks were necessary to bring the exchange into service and these were completed in October 1980. The bringing of the exchange into service has been further delayed pending the completion of certain building adaption works requested by the staff. The new exchange will increase the existing exchange capacity from 600 subscribers lines to 2,000.

Comment on this

Would the Minister not agree that it is an absolute disgrace that an exchange completed in July 1976 is not yet in operation?

Comment on this

No. We had to take into account facilities for staff working in this district. We have completed negotiations with the IPOEU. It is only right to have proper facilities for the staff.

Comment on this

I agree with that, but why are adaptation works now being requested by the staff? Why were they not incorporated in the original design of the exchange and implemented in October 1977? The exchange was completed in 1976.

Comment on this

It was not completed in 1976.

Comment on this

In July 1976.

Comment on this

No. In October 1977.

Comment on this

That is when the equipment was put in.

Comment on this

There was a problem regarding visibility from the equipment room.

Comment on this

Why was that not foreseen by the well-paid architects employed by the Department to do this kind of work? Is the Minister aware that there is a backlog of people waiting for telephones in Dunboyne? There is a bad service there because the exchange has not been brought into operation although it was completed in 1976.

Comment on this

There are 137 applicants waiting at present, 17 were offered service in 1980 and as soon as possible service will be offered to the others.

Comment on this

Why were these problems not foreseen?

Comment on this

They were not foreseen.

Comment on this

Why?

Comment on this

It was members of the IPOEU who brought up the matter.

Comment on this

Why?

Comment on this

The Deputy had better ask them.

Comment on this

These are employees of the Minister's Department. It is money spent by his Department. If an exchange on which his Department spent money in 1976 is not in operation in 1981 the Minister should be asking questions and should have a more serious attitude towards the matter.

Comment on this

I respect the employees and their opinions and it is high time Fine Gael respected them too.

Comment on this

Waffle. Keep to the point of the question.

Comment on this

In view of the totally unsatisfactory nature of the Minister's reply, I wish to raise this matter on the adjournment.

Comment on this
Padraig Faulkner An Ceann Comhairle Fianna Fáil

I will communicate with the Deputy.