Purteen Harbour improvements

Summary

Dredging of the approach channel is underway, pier repairs are being addressed, and an engineering report and cost estimate for further requested works are awaited.

Denis Gallagher Mr. D. Gallagher Fianna Fáil

asked the Minister for Fisheries and Forestry if he has any plans for improving Purteen Harbour, Keel, Achill, County Mayo.

Comment on this

(Cavan-Monaghan): My Department have approved a grant for the dredging of the approach channel at Purteen Harbour. Work at the site commenced last August and is in progress.

During the course of the work it was found that repairs to the pier were necessary and this matter is being attended to. Furthermore, the fishermen have requested that some other improvement works be carried out at the harbour and in this regard an engineering report together with an estimate of cost is awaited.