Ceisteanna—Questions. Oral Answers. - Connaught Regional Airport.
- Connaught Airport cost and runway 6 speeches
The Minister estimated the airport’s total cost at £12.2 million and completion in 1984, and confirmed the funding covered the longer, 7,500-foot runway.
John Bruton, John P. Wilson, Barry Desmond
- Impact on other regional airports 2 speeches
Yates asked whether Knock Airport would worsen losses at Shannon and Cork; the Minister rejected that concern and said he was reviewing regional airports.
Ivan Yates, John P. Wilson
- Release of airport reports 4 speeches
Desmond asked for two feasibility reports to be placed in the Oireachtas Library; the Minister could not answer immediately, and Desmond sought a further supplementary.
Barry Desmond, John P. Wilson, John F. O'Connell
asked the Minister for Transport when he expects Knock Airport to be completed in accordance with the pre-election commitments of the Government; and the total cost of the project.
Comment on this
Work on the construction of the Connaught Regional Airport will continue as planned by the airport development company. The company have indicated that they will not require any increase on the existing Exchequer allocation of £4.35 million this year. Expenditure up to the end of the present contract for earth moving is estimated at £6.6 million. A further £5.6 million will be required to complete the project thus bringing the total cost to £12.2 million. It is expected that the airport will be completed in 1984.
Comment on this
Can the Minister tell me if the expenditure of £12.5 million is for a 6,000 foot runway or a 7,500 foot runway?
Comment on this
Would the Minister envisage when the Knock Airport is completed that other regional airports, such as Shannon and Cork, which are at present experiencing great difficulty, will experience even greater losses due to the provision of this airport?
Comment on this
I would not accept that the provision of this airport will damage any other airport in any way. I am having a look at the whole situation with regard to regional airports at the moment.
Comment on this
Is the Minister prepared to place in the Library of the Houses of the Oireachtas the report of the consultants engaged by the airport company, and the inter-departmental report on the feasibility of the consultants' report?