Dublin housing allocation and schemes

Summary

Asked about the Exchequer cost of additional Dublin housing, the Minister cited a £14 million increase in Dublin Corporation’s allocation, from £62 million to £76 million, and projected additional construction and employment. Members questioned whether funds had been paid, where the houses would be built, and the schemes’ costs, land and readiness; the Minister said the allocation covered inner-city and county schemes but could not provide some details immediately, offering to circulate the list.

asked the Minister for the Environment the cost to the Exchequer of the additional housing for Dublin as outlined in the arrangement between Deputies Haughey and Gregory-Independent and announced in the Dáil on 9 March 1982.

Comment on this

(Dublin South-East): The Minister for Finance in his budget speech of 25 March 1982 stated that an additional £14 million will be made available to Dublin Corporation for house construction, especially for urban renewal purposes, in the current year bringing the total allocation from £62 million to £76 million. The additional capital will enable the Dublin Corporation to boost work in progress by 650 dwellings and employment by about 500 at the end of this year compared with the end of 1981.

Comment on this

Has any of that money yet been paid to the local authorities?

Comment on this

(Dublin South-East): I would not have that information for the Deputy.

Comment on this

Is the Minister aware that not a penny has in fact been paid, that interest payments on the debt arising at local authority level are of the order of £20,000 per week and that the local authorities are naturally very concerned about this? Would the Minister please ensure that whatever moneys have been promised will be paid as quickly as possible?

Comment on this

(Dublin South-East): Yes. I am not quite sure in the context of the reply what the Deputy is actually indicating. I must compliment him on his adroitness in asking supplementary questions.

Comment on this

Would it be within the brief of Dublin Corporation to expend portion of the money on the construction of houses in county areas or would that money be confined to inner-city housing construction?

Comment on this

(Dublin South-East): It will not apply only to inner-city houses. I have a complete list of the starts here with which I shall be happy to furnish the Deputy.

Comment on this

Are there any in County Dublin?

Comment on this

(Dublin South-East): I should have to go through them all. I shall be happy to communicate with the Deputy about the matter later.

Comment on this

(Cavan-Monaghan): I understood the Minister to say that the money involved——

Comment on this

(Dublin South-East): The total allocation goes from £62 million to £76 million.

Comment on this

(Cavan-Monaghan): Did I understand the Minister to say that this is to be applied towards building houses and could he say when these houses will start or what arrangements have been made regarding them?

Comment on this

(Dublin South-East): Yes. I certainly can. It is quite a detailed list and I have it before me. In the inner-city, which is designated northside and south-side, there are seven such starts projected for 1982 — I am sure the Deputy is speaking about those.

There are ten starts on the south side. These were actually published in the newspapers about a week ago. Of other schemes there are 12, and in the county areas — for Deputy Taylor — there are nine schemes. If the House is agreeable I shall read them all out or I shall circulate the list. It is probably better to do that. It is split north side and south side in Dublin: 343 on the north side and 345 on the south side; other areas, 382. The total is 2,033.

Comment on this

(Cavan-Monaghan): What is the total cost of those houses?

Comment on this

(Dublin South-East): This is getting down to very specific detail. I am not in a position to give all that information now.

Comment on this

(Cavan-Monaghan): Are these imaginary schemes?

Comment on this

(Dublin South-East): My goodness, no.

Comment on this

(Cavan-Monaghan): Have they been planned and sent for contract?

Comment on this

(Dublin South-East): I have always known the Deputy to be very particular and detailed and very adept in the art of asking supplementary questions. However, as regards that question, if the Deputy were familiar with what is happening at present in the schemes, he would know that Montpelier Hill, for instance, was started six weeks ago or more. Many other schemes are well in train at the moment. They are certainly not in any way imaginary schemes. They are well drafted out by Dublin Corporation and I am quite sure that any Deputies who are members of Dublin Corporation are very familiar with them and have been present on the sites and at the openings.

Comment on this

(Cavan-Monaghan): I was trying to see what sort of deal Deputy Gregory-Independent got.

Comment on this

To make sure what sort of deal he got, would the Minister confirm that the Montpelier Hill scheme has been planned for years and was well planned and well in progress long before Deputy Gregory or Deputy Haughey ever sat down in Summerhill?

Comment on this

(Dublin South-East): I do not imagine any question was asked. I did not hear one anyhow.

Comment on this

The Minister of State has stated that he is providing for 2,033 houses. Will he inform me if the land has been acquired to build that number of houses?

Comment on this

(Dublin South-East): The Deputy probably realises that I would have to go through each scheme before a figure would emerge.

Comment on this
John F. O'Connell An Ceann Comhairle Fianna Fáil

The remaining questions will appear on tomorrow's Order Paper.