Ceisteanna—Questions. Oral Answers. - Local Authority House Completions.

Robert Molloy Mr. Molloy, Mr. S. Walsh and Mr. Fitzsimons Fianna Fáil

asked the Minister for the Environment the number of local authority houses completed in each of the past three years; and if he will give an estimate of the number of completions provided for in 1983.

Comment on this

The information requested is as follows: 1980—5, 984; 1981—5,681; 1982—5,686. It is estimated that 5,800 houses will be completed in 1983.

Comment on this

The Minister will recall that this time last year the Minister for the Environment discovered that the allocations provided to the local authorities were inadequate. Later on in the year the Minister provided local authorities with an extra contribution——

Comment on this
Thomas J. Fitzpatrick An Ceann Comhairle Fine Gael

A question, please, Deputy.

Comment on this

Is it the Minister's intention to ensure that the local authorities will receive an adequate amount of money to build sufficient houses? I would also like to ask if the sums are found to be inadequate now, will they be supplemented later on in the year?

Comment on this

The provision of £208 million for 1983 for the provision of local authority houses is an increase from the £187.5 million provided last year and I am optimistic that that sum will be adequate to complete the programme as outlined.

Comment on this

If the Minister has the information available perhaps he would give me the breakdown of the local authority houses proposed for Mayo, Galway and Donegal?

Comment on this

That is a separate question.

Comment on this

Has the Minister got the information on his file?

Comment on this

No, I have not got it on the file.