Ceisteanna—Questions . Oral Answers . - Schull (Cork) Pier .
- Schull Pier improvement 16 speeches
The Minister hopes work on the proposed pier improvement will begin before the end of 1983, but cannot guarantee a start or say how the work will be phased.
Joe Walsh, P. J. Sheehan, Patrick O'Toole, Gene Fitzgerald, Thomas J. Fitzpatrick
- Schull funding and access to Minister 10 speeches
Fitzgerald asked whether funds were available and alleged Sheehan lacked access to the Minister. The Minister said both Deputies could meet him and hoped money would be available to start the priority scheme before year-end.
Gene Fitzgerald, Thomas J. Fitzpatrick, Patrick O'Toole
asked the Minister for Fisheries and Forestry if he will sanction the commencement of work on the proposed improvement to Schull Pier, County Cork.
10.
Comment on this
asked the Minister for Fisheries and Forestry when work will commence on the proposed development of Schull Pier, County Cork.
Comment on this
: I propose to take Questions Nos. 9 and 10 together.
The fishery harbour improvement programme for the current year is at present in course of being finalised in the light of the provision contained in the Fisheries Estimate for the purpose and the contractual commitments already entered into in respect of works in progress.
Comment on this
: Can I get an assurance from the Minister that work will commence before the end of this year?
Comment on this
: I cannot give a cast iron assurance but I hope we will be in a position to begin work before the end of the year.
Comment on this
: Is the Minister aware that the pier is in a state of collapse at the moment and if something is not started there shortly the pier is in danger of being washed away?
Comment on this
: In view of the fact that when the Chair was Minister for Fisheries he had it on his priority list in 1981——
Comment on this
: Is the Minister aware that in answer to a Dáil Question tabled by me in June 1982 I was told that work would commence at the end of that year? Can we now take it that there is a firm indication that work will definitely commence before the end of this year?
Comment on this
: I cannot give a cast iron guarantee, as, indeed, neither did the Ceann Comhairle or my predecessor in this respect. All I am saying is that I hope we will be in a position to commence work before the end of 1983.
Comment on this
: Will the Minister inform us if the full job will be completed in the one operation or will it be done in a piecemeal fashion? Once the work is started will it be completed?
Comment on this
: I am not in a position to give details of the modus operandi that will be applied when the work commences.
Comment on this
: Is there money available for it this year? It is correct to say now that Deputy Sheehan has no longer access to the office of his Minister for Fisheries because of the new shabby treatment he is introducing to the House of copying Deputy Walsh's questions?
Comment on this
: Obviously the Deputy is not welcome in the Minister's office.
Comment on this
: Is it true that Deputy Sheehan has not access to the Minister's office?
Comment on this
: The Deputy has access to me at any time as indeed Deputy Fitzgerald has if he wishes. In relation to the availability of money this particular scheme is on a priority list and because of the nature of marine works the expenditure in any given year is difficult to calculate exactly, as the Deputy will appreciate. I hope we will be in a position to have some money available to commence work before the end of the year.
Comment on this
: The Minister should keep Deputy Sheehan informed in future.