‹ Ceisteanna—Questions. Oral Answers. - Natural Gas.

Dublin–Belfast pipeline route and town connections

Summary

The proposed optimum route runs from Abbottstown towards Dundalk and the Border, though no spur decisions have been made. The Minister said Drogheda and Dundalk would be considered for supply, but could not commit to connection dates.

asked the Minister for Energy if any definite decision has been made on the route for the Dublin to Belfast gas pipeline.

Comment on this

The target date for completion of the natural gas pipeline from Dublin to the Border is October 1985.

Bord Gáis Éireann have undertaken a detailed analysis of the optimum route for the pipeline to the Border, and this is at present under discussion between them and other relevant authorities.

Comment on this

Does the route that has been determined include connections or spurs to Drogheda and Dundalk in particular?

Comment on this
Thomas J. Fitzpatrick An Ceann Comhairle Fine Gael

That would not seem to arise on this question which is about the time.

Comment on this

It is about the route, Sir.

Comment on this

As I am sure the Deputy is aware, the first phase of the development plan is in relation to the Dublin ring mains and the second, more extensive development is from Dublin to the Border. That has been the subject of detailed analysis by Bord Gáis Éireann. The straight line route from Abbottstown to Dundalk and then on to the Border crossing has been suggested as the optimum route for the pipe. No decisions have been taken in relation to spurs at this time.

Comment on this

Would that straight line route from Abbottstown to the Border not pass very close to both Drogheda and Dundalk?

Comment on this

Yes, very close.

Comment on this

Will the Minister give the House an assurance, therefore, that those two towns will have connections at a very early date as soon as the main pipe is laid by October 1985?

Comment on this

I can say to the Deputy that it is too early at this stage to give any details of the spur-lines or the timings of them. Obviously the object is to have maximum utility and, given the proximity of these towns, I can assure the Deputy that arrangements will be made to have gas supplies for those towns as quickly as possible.

Comment on this