The two schemes’ designs were under examination, with the Minister saying grants could be considered once proposals were in order. He said the designs had arrived in September and November 1984 and would be cleared without avoidable delay.

asked the Minister for the Environment when the Drumlosh-Nure group water scheme will be cleared by his Department; and when grant aid will be paid.

13.

Comment on this

asked the Minister for the Environment when the Cloonronniffe group water scheme will be cleared by his Department; and when grant payment will issue.

Comment on this

I propose to take Questions Nos. 12 and 13 together. Designs for these proposed schemes were recently received in my Department and are currently under examination. I cannot say at this stage when grants may be allocated or paid to these groups but there will be no avoidable delay so far as my Department are concerned.

Comment on this

When did the Department receive the designs for the schemes at Drumlosh and Nure?

Comment on this

In September and November 1984.

Comment on this

Could the Minister give a date for the clearing of the Drumlosh group scheme?

Comment on this

I have referred both schemes to the local inspector for examination and as soon as the proposals are seen to be in order I will not delay the clearing of the provisions.