Howth Harbour Development
The Minister said there was no phase 3 as such; the auction hall remained undecided, while West Pier resurfacing was expected to proceed shortly and the syncrolift was due to operate in early 1985. He gave no completion date, citing competing needs at other harbours and the need to consider available funding.
asked the Minister for Fisheries and Forestry if he will make a statement on the completion date on the Howth harbour development with special reference to (a) the erection of a fish auction hall; (b) the surfacing of the west pier; (c) when the syncrolift will be in operation and (d) when derelict boats will be removed from the harbour.
12.
Comment on this
asked the Minister for Fisheries and Forestry when it is proposed to commence phase 3 of the Howth harbour with special reference to the reclaiming of lands at the industrial estate.
Comment on this
I propose to take Questions Nos. 11 and 12 together.
The overall development scheme for Howth harbour, which incidentally does not provide for a phase 3 as such, envisages the erection of a fish auction hall and its provision will be considered in the context of the formulation of the 1985 national harbour development programme.
Tenders for the resurfacing of the West Pier are being considered in the Office of Public Works and it is expected that a contract will be placed shortly.
The syncrolift, which is at present being tested, should be in operation early in 1985
The removal of derelict boats from the harbour is a matter for the harbour authority, which is the Commissioners of Public Works.
The reclamation of land to accommodate fish related industries at the harbour as part of the development scheme has been completed. The allocation of sites in that area is being considered in my Department.
Comment on this
I thank the Minister for his reply. When was the fish auction hall first proposed by the Minister's Department.
Comment on this
My understanding is that it was proposed when the scheme was being drawn up back in, I think, 1979. I do not have the exact date.
Comment on this
Will the Minister ensure that any money which is allocated for the development of Howth Harbour will be allocated for the benefit of fishermen, that is, to erect a fish auction hall and not put money into yachting as such? Has the Minister received representations from interested bodies such as the Dublin Fish Market to inhibit auctions taking place at Howth Harbour?
Comment on this
I have had representations from several interested bodies in the Howth harbour area. We will give consideration to all representations irrespective of where they come from. As regards the auction hall it will cost in the region of £1 million. Decisions have been made to do other work such as tarring, the provision of a new ice plant and the fencing of the industrial area. A final decision has not been made on the provision of an auction hall.
Comment on this
Will the Minister assure me that any representations he receives inhibiting the erection of the auction hall will be disregarded and that the auction hall will be erected?
Comment on this
When does the Minister hope to have the project completed? This is an excellent project and we are anxious to see it completed as soon as possible.
Comment on this
The amount of money expended for the Howth area is £12 million. There are dozens of other fishing harbours in very bad condition. I must take into consideration the condition of those harbours when allocating funds. Howth will be given consideration also.