Written Answers. - Courts Accommodation.

Peter Barry Mr. Barry Question Fine Gael

237 Mr. Barry asked the Minister for Justice if plans for the upgrading of the courthouse at Washington Street, Cork, have been finalised; and if she will make a statement on the matter. [4384/97]

Comment on this
Nora Owen Minister for Justice (Mrs. Owen) Fine Gael

It is planned to upgrade the courthouse at Washington Street, Cork in two phases. Phase I involves restoration of the exterior of building and will cost approximately £3.6 million and take about eighteen months to complete. Tenders have been received for this project and it is hoped to place a contract shortly.

Phase 2 of the project will involve the refurbishment of the interior of the building and is at the initial planning stage. It is not possible to provide a timescale for this phase at this early stage.