We use Google Analytics to see which pages are read and how the site is used, so we know what to improve. This only runs if you accept. See our privacy notice for details.

Dáil

Written Answers. - Electricity Generation.

Tom Enright Mr. Enright Question Fine Gael

193 Mr. Enright asked the Minister for Public Enterprise the progress to date regarding the building of the new electricity generating station at Shannonbridge, County Offaly. [23470/01]

Comment on this
Mary O'Rourke Minister for Public Enterprise (Mrs. O'Rourke) Fianna Fáil

Progress on the construction of power stations is a day to day matter for the companies concerned. However, in this case construction cannot commence until final planning permission and an integrated pollution control licence are in place. The approval of public service obligation arrangements by the Commission of the European Union is also a prerequisite for the ESB and this latter is still under discussion between my Department and the ESB. Assuming satisfactory outcomes in these matters, the ESB would expect to commence construction early in 2002.

Comment on this