537 Mr. T. Dempsey asked the Minister for the Environment, Heritage and Local Government the water schemes completed and in planning in County Wexford since 1997 to date in 2007; and the investment made, and future allocation. [13824/07]
Comment on this
The Government has committed substantially increased funding for water services infrastructure over the past decade and again in the new National Development Plan (NDP). Some €3.7 billion was invested in new and upgraded water services infrastructure under NDP 2000-2006. €4.7 billion, an increase of 27%, has been provided under NDP 2007-2013. Real improvements being achieved on foot of this ongoing investment include:
Rapid progress in meeting targets under the EU Urban Wastewater Treatment Directive. Compliance with the end 2005 deadline for the provision of secondary treatment, which stood at 25% in 2000 had risen to some 90% at the end of 2006, with all remaining schemes needed to ensure full compliance included in the Water Services Investment Programme.
The extensive programme of wastewater treatment works has reduced the pollutant load from municipal discharges to rivers, lakes and sea (measured as Biochemical Oxygen Demand) by 45,000 tonnes per annum in a period of unprecedented economic and population growth.
Wastewater treatment capacity was increased since 1997 by an equivalent to the needs of a population of 3.3 million; the increase in drinking water treatment capacity over the same period was equivalent to the needs of a population of 1.2 million.
By the end of December 2006 of some 85,000 sites had been provided under the Serviced Land Initiative, with a further 100,000 sites at construction stage.
Massive investment under the Rural Water Programme has resulted in great progress in upgraded and renewed rural water supply systems and improved water quality in private group water schemes.
Overall, my Department is committing sufficient resources to ensure that the coverage and quality of the national water infrastructure will be able to fully meet current and anticipated demand in the future.
My Department provided a total of €121.92 million to County Wexford under the Water Services Investment and Rural Water Programmes in the period 1997 to 2006. Major schemes completed during that period are set out in the table below. In addition, many more schemes, smaller in scale, were completed under the devolved Rural Water Programme, of which details may be obtained from the County Council. Full details of currently approved major schemes in County Wexford, including the value of the investment proposed in each case, are set out in my Department's Water Services Investment Programme 2005-2007, which is available in the Oireachtas Library.
New Assessments of Needs were undertaken last year in response to the Department's request to all local authorities to review the needs for capital works in their areas and to prioritise their proposals on the basis of the assessments. The priorities adopted by the members of Wexford County Council will be taken into account in the framing of the next phase of the Water Services Investment Programme.
Scheme | Year Completed
Fardystown Water Supply Scheme Contract 2 | 1999
Wexford Water Conservation Works | 1999
Wexford Water Conservation Works | 2000
Blackwater Sewerage Treatment Works improvements | 2001
Gorey (Rehabilitation) Water Conservation | 2001
Kilmuckridge Sewerage Treatment Plant SLI | 2001
Courtown/Riverchapel Sewerage | 2002
Rosslare Strand Sewerage Scheme | 2002
Fardystown Water Supply | 2003
Ballymurm Sewerage Scheme | 2003
Gorey Main Drainage — pipeline ext. | 2003
Wexford Main Drainage | 2003
Carrick-on-Bannow Sewerage Scheme | 2005
Comment on this
538 Mr. Wilkinson asked the Minister for the Environment, Heritage and Local Government the water schemes completed and in planning in County Waterford since 1997, to date in 2007; and the investment made, and future allocation. [13825/07]
Comment on this
The Government has committed substantially increased funding for water services infrastructure over the past decade and again in the new National Development Plan (NDP). Some €3.7 billion was invested in new and upgraded water services infrastructure under NDP 2000-2006. €4.7 billion, an increase of 27%, has been provided under NDP 2007-2013. Real improvements being achieved on foot of this ongoing investment include:
Rapid progress in meeting targets under the EU Urban Wastewater Treatment Directive. Compliance with the end 2005 deadline for the provision of secondary treatment, which stood at 25% in 2000 had risen to some 90% at the end of 2006, with all remaining schemes needed to ensure full compliance included in the Water Services Investment Programme.
The extensive programme of wastewater treatment works has reduced the pollutant load from municipal discharges to rivers, lakes and sea (measured as Biochemical Oxygen Demand) by 45,000 tonnes per annum in a period of unprecedented economic and population growth.
Wastewater treatment capacity was increased since 1997 by an equivalent to the needs of a population of 3.3 million; the increase in drinking water treatment capacity over the same period was equivalent to the needs of a population of 1.2 million.
By the end of December 2006 of some 85,000 sites had been provided under the Serviced Land Initiative, with a further 100,000 sites at construction stage.
Massive investment under the Rural Water Programme has resulted in great progress in upgraded and renewed rural water supply systems and improved water quality in private group water schemes.
Overall, my Department is committing sufficient resources to ensure that the coverage and quality of the national water infrastructure will be able to fully meet current and anticipated demand in the future.
My Department provided a total of €70.29 million to Waterford County Council and €40.19 million to Waterford City Council under the Water Services Investment and Rural Water Programmes in the period 1997 to 2006. Major schemes completed during that period are set out in the following table. In addition, many more schemes, smaller in scale, were completed under the devolved Rural Water Programme, of which details may be obtained from the County Council. Full details of currently approved major schemes in Waterford County and City, including the value of the investment proposed in each case, are set out in my Department's Water Services Investment Programme 2005-2007, which is available in the Oireachtas Library.
New Assessments of Needs were undertaken last year in response to the Department's request to all local authorities to review the needs for capital works in their areas and to prioritise their proposals on the basis of the assessments. The priorities adopted by the members of Waterford County and City Councils will be taken into account in the framing of the next phase of the Water Services Investment Programme.
Scheme | Year Completed
East Waterford Water Supply Scheme — Contract 5 | 2000
East Waterford Water Supply Stage 2 Phase 1 | 2000
Extension of Sewer along Coolagh Road Dungarvan | 2000
Extension of Sewer in Ballymacarbry | 2000
Development of Crobally Upper Tramore Serviced Land Initiative | 2001
Scheme | Year Completed
East Waterford Water — Emergency Contract (Civil Works) | 1999
East Waterford Water — Emergency Contract (Mechanical & Electrical) | 1999
East Waterford Water Conservation – | 1999
East Waterford Water Supply Scheme — Contracts 6 & 7 | 1999
East Waterford Water Supply Stage 2 Phase 1 | 2000
Logloss/Bawndaw Development area | 2000
Waterford Main Drainage (Collection) | 2000
Kilbarry Development Area | 2002
East Waterford Water Supply Contracts 17A & B1 | 2003
Comment on this
539 Mr. Davern asked the Minister for the Environment, Heritage and Local Government the water schemes completed and in planning in County Tipperary since 1997, to date in 2007; and the investment made, and future allocation. [13826/07]
Comment on this
The Government has committed substantially increased funding for water services infrastructure over the past decade and again in the new National Development Plan (NDP). Some €3.7 billion was invested in new and upgraded water services infrastructure under NDP 2000-2006. €4.7 billion, an increase of 27%, has been provided under NDP 2007-2013. Real improvements being achieved on foot of this ongoing investment include:
Rapid progress in meeting targets under the EU Urban Wastewater Treatment Directive. Compliance with the end 2005 deadline for the provision of secondary treatment, which stood at 25% in 2000 had risen to some 90% at the end of 2006, with all remaining schemes needed to ensure full compliance included in the Water Services Investment Programme.
The extensive programme of wastewater treatment works has reduced the pollutant load from municipal discharges to rivers, lakes and sea (measured as Biochemical Oxygen Demand) by 45,000 tonnes per annum in a period of unprecedented economic and population growth.
Wastewater treatment capacity was increased since 1997 by an equivalent to the needs of a population of 3.3 million; the increase in drinking water treatment capacity over the same period was equivalent to the needs of a population of 1.2 million.
By the end of December 2006 of some 85,000 sites had been provided under the Serviced Land Initiative, with a further 100,000 sites at construction stage.
Massive investment under the Rural Water Programme has resulted in great progress in upgraded and renewed rural water supply systems and improved water quality in private group water schemes.
Overall, my Department is committing sufficient resources to ensure that the coverage and quality of the national water infrastructure will be able to fully meet current and anticipated demand in the future.
My Department provided a total of €57.98 million to North Tipperary County Council and €89.14 million to South Tipperary County Council under the Water Services Investment and Rural Water Programmes in the period 1997 to 2006. Major schemes completed during that period are set out in the following table. In addition, many more schemes, smaller in scale, were completed under the devolved Rural Water Programme, of which details may be obtained from the County Councils. Full details of currently approved major schemes in County Tipperary, including the value of the investment proposed in each case, are set out in my Department's Water Services Investment Programme 2005-2007, which is available in the Oireachtas Library.
New Assessments of Needs were undertaken last year in response to the Department's request to all local authorities to review the needs for capital works in their areas and to prioritise their proposals on the basis of the assessments. The priorities adopted by the members of North Tipperary and South Tipperary County Councils will be taken into account in the framing of the next phase of the Water Services Investment Programme.
Scheme | Year Completed
Nenagh Water | 1997
Nenagh Phosphate Removal | 1998
Roscrea Sewerage | 2000
Templemore Water | 2000
Thurles (TRBDI) Sewerage | 2000
Thurles Sewerage — Surface water sewer at Ballycurrane Road | 2000
Nenagh Sewerage Treatment Plant Improvement | 2001
Roscrea Water | 2001
N52 Outer Ring Watermain SLI | 2004
Nenagh Sewerage Scheme Stage 2 | 2004
Scheme | Year Completed
Cahir Sewerage | 1997
Clonmel Sewerage | 1998
Galtee Water | 1998
Cashel Sewerage | 1999
Ardfinnan Water Supply Scheme | 1999
Clonmel Serviced Land Sewerage Ext. SLI | 2001
Clonmel Water Conservation | 2001
Tipperary Town Sewerage | 2001
Carrick on Suir Sewerage (Collection System) | 2003
Limerick Junction Sewerage | 2003
Ardfinnan Sewerage | 2005
Ballyclerihan Sewerage | 2005
Ballyporeen Sewerage | 2005
Cahir Sewerage | 2005
Carrick-on-Suir Sewerage | 2005
Clogheen Sewerage | 2005
Clonmel Sewerage | 2005
Fethard Sewerage | 2005
Killenaule Sewerage | 2005
Kilsheelan Sewerage | 2005
Comment on this
540 Mr. Callanan asked the Minister for the Environment, Heritage and Local Government the water schemes completed and in planning in Galway City and County since 1997, to date in 2007; and the investment made, and future allocation. [13827/07]
Comment on this
547 Mr. Callanan asked the Minister for the Environment, Heritage and Local Government the water schemes completed and in planning in County Galway since 1997, to date in 2007; and the investment made, and future allocation. [13834/07]
Comment on this
I propose to take Questions Nos. 540 and 547 together.
The Government has committed substantially increased funding for water services infrastructure over the past decade and again in the new National Development Plan (NDP). Some €3.7 billion was invested in new and upgraded water services infrastructure under NDP 2000-2006. €4.7 billion, an increase of 27%, has been provided under NDP 2007-2013. Real improvements being achieved on foot of this ongoing investment include:
Rapid progress in meeting targets under the EU Urban Wastewater Treatment Directive. Compliance with the end 2005 deadline for the provision of secondary treatment, which stood at 25% in 2000 had risen to some 90% at the end of 2006, with all remaining schemes needed to ensure full compliance included in the Water Services Investment Programme.
The extensive programme of wastewater treatment works has reduced the pollutant load from municipal discharges to rivers, lakes and sea (measured as Biochemical Oxygen Demand) by 45,000 tonnes per annum in a period of unprecedented economic and population growth.
Wastewater treatment capacity was increased since 1997 by an equivalent to the needs of a population of 3.3 million; the increase in drinking water treatment capacity over the same period was equivalent to the needs of a population of 1.2 million.
By the end of December 2006 of some 85,000 sites had been provided under the Serviced Land Initiative, with a further 100,000 sites at construction stage.
Massive investment under the Rural Water Programme has resulted in great progress in upgraded and renewed rural water supply systems and improved water quality in private group water schemes.
Overall, my Department is committing sufficient resources to ensure that the coverage and quality of the national water infrastructure will be able to fully meet current and anticipated demand in the future.
My Department provided a total of €103.61 million and €195.23 million to Galway City and Galway County Councils respectively under the Water Services Investment and Rural Water Programmes in the period 1997 to 2006. Major schemes completed during that period are set out in the following table. In addition, many more schemes, smaller in scale, were completed under the devolved Rural Water Programme, of which details may be obtained from the County Council. Full details of currently approved major schemes in Galway City and County, including the value of the investment proposed in each case, are set out in my Department's Water Services Investment Programme 2005-2007, which is available in the Oireachtas Library.
New Assessments of Needs were undertaken last year in response to the Department's request to all local authorities to review the needs for capital works in their areas and to prioritise their proposals on the basis of the assessments. The priorities adopted by the members of Galway City and County Councils will be taken into account in the framing of the next phase of the Water Services Investment Programme.
Scheme | Year of Completion
Galway Main Drainage — Knocknacarra Eastern | 1997
Inish Oirr Water Supply Scheme | 1997
Tuam Regional Water Supply Scheme — Stage 1 | 1997
Williamstown Sewerage Scheme | 1997
Ballinasloe Phosphorus Removal | 1998
Spiddal/Rossaveal Water Supply Scheme | 1998
Galway Main Drainage — Causeway to Mutton Island | 1999
Galway Main Drainage — Oranmore Sewers | 2000
Oughterard Sludge Facilities (Water Scheme) | 2000
Portumna Sewerage Scheme | 2000
Tuam Main Drainage — Stage 2 (Galway Road) Serviced Land Initiative Scheme | 2000
Galway City Water Conservation (Phase 1) | 2001
Loughrea Sewerage Scheme | 2001
Terryland River Valley Scheme — Serviced Land Initiative | 2001
Tuam Regional Water Supply — Phase 3 | 2001
Tuam Regional Water Supply — Ext to Athenry | 2001
Ballinasloe (Laurencetown) Water | 2002
Inishmore Water Supply Scheme | 2002
Loughrea — Serviced Land Initiative | 2002
Moycullen Sewerage Scheme | 2002
Tuam Main Drainage Stage 2 — Balgaddy Road (part) Serviced Land Initiative | 2002
Galway Main Drainage — Mutton Island Plant | 2003
Galway City Water Supply — Tuam Interlink | 2003
Barna Sewerage Scheme — Advance Works | 2004
Galway Main Drainage — Knocknacarra Integration | 2004
Gort Regional Water Supply Scheme — Advance Works | 2004
Tuam Main Drainage Stage 2 — Killaloonty Serviced Land Initiative | 2005
Comment on this
541 Dr. Devins asked the Minister for the Environment, Heritage and Local Government the water schemes completed and in planning in County Sligo since 1997, to date in 2007; and the investment made, and future allocation. [13828/07]
Comment on this
The Government has committed substantially increased funding for water services infrastructure over the past decade and again in the new National Development Plan (NDP). Some €3.7 billion was invested in new and upgraded water services infrastructure under NDP 2000-2006. €4.7 billion, an increase of 27%, has been provided under NDP 2007-2013. Real improvements being achieved on foot of this ongoing investment include:
Rapid progress in meeting targets under the EU Urban Wastewater Treatment Directive. Compliance with the end 2005 deadline for the provision of secondary treatment, which stood at 25% in 2000 had risen to some 90% at the end of 2006, with all remaining schemes needed to ensure full compliance included in the Water Services Investment Programme.
The extensive programme of wastewater treatment works has reduced the pollutant load from municipal discharges to rivers, lakes and sea (measured as Biochemical Oxygen Demand) by 45,000 tonnes per annum in a period of unprecedented economic and population growth.
Wastewater treatment capacity was increased since 1997 by an equivalent to the needs of a population of 3.3 million; the increase in drinking water treatment capacity over the same period was equivalent to the needs of a population of 1.2 million.
By the end of December 2006 of some 85,000 sites had been provided under the Serviced Land Initiative, with a further 100,000 sites at construction stage.
Massive investment under the Rural Water Programme has resulted in great progress in upgraded and renewed rural water supply systems and improved water quality in private group water schemes.
Overall, my Department is committing sufficient resources to ensure that the coverage and quality of the national water infrastructure will be able to fully meet current and anticipated demand in the future.
My Department provided a total of €92.89 million to County Sligo under the Water Services Investment and Rural Water Programmes in the period 1997 to 2006. Major schemes completed during that period are set out in the following table. In addition, many more schemes, smaller in scale, were completed under the devolved Rural Water Programme, of which details may be obtained from the County Council. Full details of currently approved major schemes in County Sligo, including the value of the investment proposed in each case, are set out in my Department's Water Services Investment Programme 2005-2007, which is available in the Oireachtas Library.
New Assessments of Needs were undertaken last year in response to the Department's request to all local authorities to review the needs for capital works in their areas and to prioritise their proposals on the basis of the assessments. The priorities adopted by the members of Sligo County Council will be taken into account in the framing of the next phase of the Water Services Investment Programme.
Scheme | Year of Completion
Enniscrone Sewerage Scheme | 1997
Lough Talt Water Supply Scheme | 1997
North Sligo Regional Water Scheme | 1999
Sligo Main Drainage — Caltragh Ext. | 2000
Curry WS Rural Towns & Villages Initiative (Rhue/Curry/Bellaghy WSS) | 2001
Sligo & Environs Water Supply Stage 1 | 2001
Comment on this
542 Mr. Finneran asked the Minister for the Environment, Heritage and Local Government the water schemes completed and in planning in Counties Roscommon and Leitrim since 1997, to date in 2007; and the investment made, and future allocation. [13829/07]
Comment on this
The Government has committed substantially increased funding for water services infrastructure over the past decade and again in the new National Development Plan (NDP). Some €3.7 billion was invested in new and upgraded water services infrastructure under NDP 2000-2006. €4.7 billion, an increase of 27%, has been provided under NDP 2007-2013. Real improvements being achieved on foot of this ongoing investment include:
Rapid progress in meeting targets under the EU Urban Wastewater Treatment Directive. Compliance with the end 2005 deadline for the provision of secondary treatment, which stood at 25% in 2000 had risen to some 90% at the end of 2006, with all remaining schemes needed to ensure full compliance included in the Water Services Investment Programme.
The extensive programme of wastewater treatment works has reduced the pollutant load from municipal discharges to rivers, lakes and sea (measured as Biochemical Oxygen Demand) by 45,000 tonnes per annum in a period of unprecedented economic and population growth.
Wastewater treatment capacity was increased since 1997 by an equivalent to the needs of a population of 3.3 million; the increase in drinking water treatment capacity over the same period was equivalent to the needs of a population of 1.2 million.
By the end of December 2006 of some 85,000 sites had been provided under the Serviced Land Initiative, with a further 100,000 sites at construction stage.
Massive investment under the Rural Water Programme has resulted in great progress in upgraded and renewed rural water supply systems and improved water quality in private group water schemes.
Overall, my Department is committing sufficient resources to ensure that the coverage and quality of the national water infrastructure will be able to fully meet current and anticipated demand in the future.
My Department provided a total of €78.15 million to County Roscommon and €53.99 million to County Leitrim under the Water Services Investment and Rural Water Programmes in the period 1997 to 2006. Major schemes completed during that period are set out in the following table. In addition, many more schemes, smaller in scale, were completed under the devolved Rural Water Programme, of which details may be obtained from the County Councils. Full details of currently approved major schemes in Counties Roscommon and Leitrim, including the value of the investment proposed in each case, are set out in my Department's Water Services Investment Programme 2005-2007, which is available in the Oireachtas Library.
New Assessments of Needs were undertaken last year in response to the Department's request to all local authorities to review the needs for capital works in their areas and to prioritise their proposals on the basis of the assessments. The priorities adopted by the members of Roscommon and Leitrim County Councils will be taken into account in the framing of the next phase of the Water Services Investment Programme.
Scheme Name | Year of Completion
Boyle/Arcarne Water Supply Scheme | 1997
North East Roscommon Water Extension to Ballagh/Ballybeg | 1999
North East Roscommon Water Extension to Tarmonbarry | 1999
North Roscommon Water Supply Scheme Intake | 1999
Ballaghderreen Sewerage Scheme | 2000
Boyle Sewerage Scheme | 2000
Monksland Sewerage Scheme | 2000
Roscommon Sewerage Scheme | 2000
Tarmonbarry Sewerage Scheme | 2000
Ballinagare Sewerage Scheme — Rural Towns and Villages Initiative | 2001
Ballintubber Sewerage Scheme — Rural Towns and Villages Initiative | 2001
Charlestown Road, Ballaghderreen — Serviced Land Initiative | 2001
Roscommon North Regional Water Supply Scheme (Fairymount/Loughglynn) | 2001
Monksland Townland Provision of Services — Serviced Land Initiative | 2002
Warren or Drum Townland, Boyle Provision of Services — Serviced Land Initiative | 2002
Falladeen Road, Ballinlough, Provision of Services — Serviced Land Initiative | 2004
Castlerea Sewerage Scheme Stages 1 & 2 | 2006
Scheme | Year of Completion
Keshkerrigan Sewerage Scheme | 1998
Newtowngore Sewerage Scheme | 1998
Carrick-on-Shannon Sewerage Scheme (Sludge Press) | 1999
Newtowngore/Keshcarrigan Sewerage Scheme | 1999
Dromod Sewerage Scheme | 2000
Lurganboy Sewerage Scheme — Rural Towns and Villages Initiative | 2001
Drumsna Sewerage Scheme — Rural Towns and Villages Initiative | 2003
Fenagh Sewerage Scheme | 2003
Lurganboy Sewerage Scheme — Rural Towns and Villages Initiative | 2003
North Leitrim Rural Water Supply Scheme | 2004
Comment on this
543 Mr. McGuinness asked the Minister for the Environment, Heritage and Local Government the water schemes completed and in planning in Counties Carlow and Kilkenny since 1997, to date in 2007; and the investment made, and future allocation. [13830/07]
Comment on this
The Government has committed substantially increased funding for water services infrastructure over the past decade and again in the new National Development Plan (NDP). Some €3.7 billion was invested in new and upgraded water services infrastructure under NDP 2000-2006. €4.7 billion, an increase of 27%, has been provided under NDP 2007-2013. Real improvements being achieved on foot of this ongoing investment include:
Rapid progress in meeting targets under the EU Urban Wastewater Treatment Directive. Compliance with the end 2005 deadline for the provision of secondary treatment, which stood at 25% in 2000 had risen to some 90% at the end of 2006, with all remaining schemes needed to ensure full compliance included in the Water Services Investment Programme.
The extensive programme of wastewater treatment works has reduced the pollutant load from municipal discharges to rivers, lakes and sea (measured as Biochemical Oxygen Demand) by 45,000 tonnes per annum in a period of unprecedented economic and population growth.
Wastewater treatment capacity was increased since 1997 by an equivalent to the needs of a population of 3.3 million; the increase in drinking water treatment capacity over the same period was equivalent to the needs of a population of 1.2 million.
By the end of December 2006 of some 85,000 sites had been provided under the Serviced Land Initiative, with a further 100,000 sites at construction stage.
Massive investment under the Rural Water Programme has resulted in great progress in upgraded and renewed rural water supply systems and improved water quality in private group water schemes.
Overall, my Department is committing sufficient resources to ensure that the coverage and quality of the national water infrastructure will be able to fully meet current and anticipated demand in the future.
My Department provided a total of €27.87 million to County Kilkenny and €31.78 million to County Carlow under the Water Services Investment and Rural Water Programmes in the period 1997 to 2006. Major schemes completed during that period are set out in the following table. In addition, many more schemes, smaller in scale, were completed under the devolved Rural Water Programme, of which details may be obtained from the County Councils. Full details of currently approved major schemes in Counties Kilkenny and Carlow, including the value of the investment proposed in each case, are set out in my Department's Water Services Investment Programme 2005-2007, which is available in the Oireachtas Library.
New Assessments of Needs were undertaken last year in response to the Department's request to all local authorities to review the needs for capital works in their areas and to prioritise their proposals on the basis of the assessments. The priorities adopted by the members of Kilkenny and Carlow County Councils will be taken into account in the framing of the next phase of the Water Services Investment Programme.
Scheme | Year of Completion
Kilkenny Main Drainage (Treatment Plant Works) | 1997
Gowran/Paulstown Water (Source Protection) Scheme | 1998
Kilkenny Sewerage Scheme | 2001
Graiguenamanagh Sewerage Scheme — Rural Towns and Villages Initiative | 2002
Thomastown Sewerage Scheme | 2002
Graiguenamanagh Sewerage Scheme — Rural Towns and Villages Initiative | 2004
Urlingford Sewerage Scheme | 2005
Scheme | Year of Completion
Carlow Water Conservation | 2000
Graiguecullen Sewerage Scheme Serviced Land Initiative | 2000
Extension to Carlow Sewage Treatment Plant — Mortarstown | 2002
Hacketstown Water Supply — Rural Towns and Villages Initiative | 2003
Tullow Rising Main Replacement | 2006
Comment on this
544 Mr. Moloney asked the Minister for the Environment, Heritage and Local Government the water schemes completed and in planning in Counties Laois and Offaly since 1997, to date in 2007; and the investment made, and future allocation. [13831/07]
Comment on this
The Government has committed substantially increased funding for water services infrastructure over the past decade and again in the new National Development Plan (NDP). Some €3.7 billion was invested in new and upgraded water services infrastructure under NDP 2000-2006. €4.7 billion, an increase of 27%, has been provided under NDP 2007-2013. Real improvements being achieved on foot of this ongoing investment include:
Rapid progress in meeting targets under the EU Urban Wastewater Treatment Directive. Compliance with the end 2005 deadline for the provision of secondary treatment, which stood at 25% in 2000 had risen to some 90% at the end of 2006, with all remaining schemes needed to ensure full compliance included in the Water Services Investment Programme.
The extensive programme of wastewater treatment works has reduced the pollutant load from municipal discharges to rivers, lakes and sea (measured as Biochemical Oxygen Demand) by 45,000 tonnes per annum in a period of unprecedented economic and population growth.
Wastewater treatment capacity was increased since 1997 by an equivalent to the needs of a population of 3.3 million; the increase in drinking water treatment capacity over the same period was equivalent to the needs of a population of 1.2 million.
By the end of December 2006 of some 85,000 sites had been provided under the Serviced Land Initiative, with a further 100,000 sites at construction stage.
Massive investment under the Rural Water Programme has resulted in great progress in upgraded and renewed rural water supply systems and improved water quality in private group water schemes.
Overall, my Department is committing sufficient resources to ensure that the coverage and quality of the national water infrastructure will be able to fully meet current and anticipated demand in the future.
My Department provided a total of €42.82 million to County Laois and €58.41 million to County Offaly under the Water Services Investment and Rural Water Programmes in the period 1997 to 2006. Major schemes completed during that period are set out in the following table. In addition, many more schemes, smaller in scale, were completed under the devolved Rural Water Programme, of which details may be obtained from the County Councils. Full details of currently approved major schemes in Counties Laois and Offaly, including the value of the investment proposed in each case, are set out in my Department's Water Services Investment Programme 2005-2007, which is available in the Oireachtas Library.
New Assessments of Needs were undertaken last year in response to the Department's request to all local authorities to review the needs for capital works in their areas and to prioritise their proposals on the basis of the assessments. The priorities adopted by the members of Laois and Offaly County Councils will be taken into account in the framing of the next phase of the Water Services Investment Programme.
Scheme | Year of Completion
Mountmellick Sewerage Scheme | 1998
Portlaoise Sewerage Scheme (Colliers Lane) | 1998
Portlaoise Water Supply Scheme | 1998
Graiguecullen Sewerage Scheme — Serviced Land Initiative | 2000
Portlaoise Sludge Dewatering | 2000
Sleaty Road Sewerage Scheme | 2000
Knockmay Mains Water Supply Scheme | 2000
Stradbally Sewerage Improvement Scheme | 2002
Ballyroan Sewerage Scheme — Rural Towns & Villages Initiative | 2003
Graiguecullen Sewerage Scheme — Serviced Land Initiative | 2004
Scheme | Year of Completion
Birr Sewerage Scheme | 1997
Birr Sewerage (Phosphorus Removal) Scheme | 1998
Clara Water Supply Scheme | 1998
Tullamore Sewerage Scheme | 1998
Banagher Sewerage Scheme | 1999
Cloncollig Water Supply Scheme | 2000
Kilcormac Water and Sewerage Scheme — Serviced Land Initiative | 2000
Silver River (Collins Lane/Arden) Water Supply Scheme | 2000
Ferbane Sewerage Scheme — Serviced Land Initiative | 2001
Ferbane Water Supply Scheme | 2002
Edenderry Interim Sewage Treatment Scheme — Rural Towns & Villages Initiative. | 2003
Clara Sewerage Scheme | 2005
Ferbane Sewerage Scheme — Rural Towns & Villages Initiative | 2005
Collins Lane (Tullamore) Surface Water Sewerage Scheme | 2005
Tullamore Water Supply Scheme Contracts 1&3 (Sillogue Well) | 2006
Comment on this
545 Mr. Kelleher asked the Minister for the Environment, Heritage and Local Government the water schemes completed and in planning in Cork City and County since 1997, to date in 2007; and the investment made, and future allocation. [13832/07]
Comment on this
The Government has committed substantially increased funding for water services infrastructure over the past decade and again in the new National Development Plan (NDP). Some €3.7 billion was invested in new and upgraded water services infrastructure under NDP 2000-2006. €4.7 billion, an increase of 27%, has been provided under NDP 2007-2013. Real improvements being achieved on foot of this ongoing investment include:
Rapid progress in meeting targets under the EU Urban Wastewater Treatment Directive. Compliance with the end 2005 deadline for the provision of secondary treatment, which stood at 25% in 2000 had risen to some 90% at the end of 2006, with all remaining schemes needed to ensure full compliance included in the Water Services Investment Programme.
The extensive programme of wastewater treatment works has reduced the pollutant load from municipal discharges to rivers, lakes and sea (measured as Biochemical Oxygen Demand) by 45,000 tonnes per annum in a period of unprecedented economic and population growth.
Wastewater treatment capacity was increased since 1997 by an equivalent to the needs of a population of 3.3 million; the increase in drinking water treatment capacity over the same period was equivalent to the needs of a population of 1.2 million.
By the end of December 2006 of some 85,000 sites had been provided under the Serviced Land Initiative, with a further 100,000 sites at construction stage.
Massive investment under the Rural Water Programme has resulted in great progress in upgraded and renewed rural water supply systems and improved water quality in private group water schemes.
Overall, my Department is committing sufficient resources to ensure that the coverage and quality of the national water infrastructure will be able to fully meet current and anticipated demand in the future.
My Department provided a total of €324.76 million to Cork City Council and €67.64 million to Cork County Council under the Water Services Investment and Rural Water Programmes in the period 1997 to 2006. Major schemes completed during that period are set out in the following table. In addition, many more schemes, smaller in scale, were completed under the devolved Rural Water Programme, of which details may be obtained from the County Council. Full details of currently approved major schemes in Cork City and County, including the value of the investment proposed in each case, are set out in my Department's Water Services Investment Programme 2005-2007, which is available in the Oireachtas Library.
New Assessments of Needs were undertaken last year in response to the Department's request to all local authorities to review the needs for capital works in their areas and to prioritise their proposals on the basis of the assessments. The priorities adopted by the members of Cork City and County Councils will be taken into account in the framing of the next phase of the Water Services Investment Programme.
Scheme | Year of Completion
Chetwynd Water (Cork CB) | 1998
Cork Main Drainage Site Investigations | 1999
Cork City Water — Chetwynd Main | 1999
Glen/Bride/Kiln River — Phase 3&4 | 1999
Blarney Street/Road (Improvement in Services) | 2000
Cork Main Drainage — Atlantic Pond Civil Contract | 2002
Cork Main Drainage — Boreenmana Road/Blackrock/Centre Park | 2002
Cork Main Drainage (Phase 1) Interceptor Sewer — River Lee Siphon | 2002
Cork Main Drainage (Collection and Treatment Works) | 2003
Scheme | Year of Completion
Cloyne Sewerage | 1997
Ballincollig Water Supply | 2000
Ballincollig, Greenhills, Foul Sewer | 2000
Ballyviniter Water Scheme | 2000
Blarney Water | 2000
Cobh Water Tower | 2000
Cork Water Conservation Phase A | 2000
Fermoy Storm Water (Pike Road) | 2000
Fermoy Storm Water Sewer (Cork Road) | 2000
Fermoy Water | 2000
Fethard Town — Killenaule Road | 2000
Glanmire Water Supply, Castlejane | 2000
Glashaboy Water Supply, Caherlag | 2000
Kinsale Water Supply Ardbrack | 2000
Bandon Foul Sewerage Serviced Land Initiative | 2001
Carrigaline Storm Drain SLI | 2001
Carrigrohane-sewage pumping station Serviced Land Initiative | 2001
Castlemartyr Treatment Plant Serviced Land Initiative | 2001
Clonakility Water Stage 1 | 2001
Conna STP upgrade Serviced Land Initiative | 2001
Cork Water Conservation (Phase 1) | 2001
Glasheen River | 2001
Mallow Rd. Serviced Land Initiative | 2001
Midleton Sewerage | 2001
Passage West Storm Drain Serviced Land Initiative | 2001
Western Rd, Clonakility Serviced Land Initiative | 2001
Blarney — Water Supply and Sewerage | 2002
Buttevant Water Supply - | 2002
Clonakility Water — Sludge Treatment | 2002
Mitchelstown Services Extension — Serviced Land Initiative | 2002
Watergrasshill Serviced Land Initiative | 2002
Poundhill St. (Market St.) Serviced Land Initiative | 2003
Crosshaven Sewerage | 2005
Mitchelstown Sewerage Scheme (Nutrient Removal) | 2006
Cork Lower Harbour Sewerage Scheme (Crosshaven SS) | 2006
Mallow/Fermoy/Blarney Treatment Plant Upgrading Serviced Land Initiative | 2006
Sally’s Cross Sewerage Scheme Serviced Land Initiative | 2006
Kilbrin Sewerage Scheme | 2006
Comment on this
546 Mr. P. Power asked the Minister for the Environment, Heritage and Local Government the water schemes completed and in planning in Counties Limerick and Clare since 1997, to date in 2007; and the investment made, and future allocation. [13833/07]
Comment on this
The Government has committed substantially increased funding for water services infrastructure over the past decade and again in the new National Development Plan (NDP). Some €3.7 billion was invested in new and upgraded water services infrastructure under NDP 2000-2006. €4.7 billion, an increase of 27%, has been provided under NDP 2007-2013. Real improvements being achieved on foot of this ongoing investment include:
Rapid progress in meeting targets under the EU Urban Wastewater Treatment Directive. Compliance with the end 2005 deadline for the provision of secondary treatment, which stood at 25% in 2000 had risen to some 90% at the end of 2006, with all remaining schemes needed to ensure full compliance included in the Water Services Investment Programme.
The extensive programme of wastewater treatment works has reduced the pollutant load from municipal discharges to rivers, lakes and sea (measured as Biochemical Oxygen Demand) by 45,000 tonnes per annum in a period of unprecedented economic and population growth.
Wastewater treatment capacity was increased since 1997 by an equivalent to the needs of a population of 3.3 million; the increase in drinking water treatment capacity over the same period was equivalent to the needs of a population of 1.2 million.
By the end of December 2006 of some 85,000 sites had been provided under the Serviced Land Initiative, with a further 100,000 sites at construction stage.
Massive investment under the Rural Water Programme has resulted in great progress in upgraded and renewed rural water supply systems and improved water quality in private group water schemes.
Overall, my Department is committing sufficient resources to ensure that the coverage and quality of the national water infrastructure will be able to fully meet current and anticipated demand in the future.
My Department provided a total of €295.26 million, €71.14 million and €100.43 million, respectively, to Limerick City and County Councils and Clare County Council under the Water Services Investment and Rural Water Programmes in the period 1997 to 2006. Major schemes completed during that period are set out in the following table. In addition, many more schemes, smaller in scale, were completed under the devolved Rural Water Programme, of which details may be obtained from the County Councils. Full details of currently approved major schemes in Limerick City and County and in County Clare, including the value of the investment proposed in each case, are set out in my Department's Water Services Investment Programme 2005-2007, which is available in the Oireachtas Library.
New Assessments of Needs were undertaken last year in response to the Department's request to all local authorities to review the needs for capital works in their areas and to prioritise their proposals on the basis of the assessments. The priorities adopted by the members of Limerick City and County Councils and Clare County Council will be taken into account in the framing of the next phase of the Water Services Investment Programme.
Scheme | Year of Completion
Askeaton/Pallaskenry (Phase 1) Water | 1998
Limerick City Water Conservation (Phase 1) | 1999
Limerick Trunk Mains Rosbrien | 2000
Limerick Water (Phase 2) Newcastle | 2000
Rhebogue/Bloodmill Road — Serviced Land Initiative | 2000
Surface Water Sewer at Annacotty — Serviced Land Initiative | 2000
Castletroy Water Supply Scheme — Low level area Serviced Land Initiative | 2001
Fedamore Sewerage (Rural Towns & Villages Initiative) | 2001
Clareville to Newcastle Reservoir Rising Main | 2002
Foynes Water Supply Scheme | 2003
Castleconnell Sewerage Scheme | 2003
Limerick Main Drainage (Collection & Treatment Works) | 2003
Croagh Sewerage Scheme | 2004
Southern Ring Watermain | 2004
Limerick Main Drainage Contract 4.3 | 2005
Castletroy Water Supply High Level Demand Serviced Land Initiative | 2007
Scheme | Year of Completion
Kilkee Sewerage Scheme | 1997
Kilkee Water Scheme | 1997
Killaloe Sewerage Scheme | 1997
Lahinch Sewerage Scheme | 1997
Sixmilebridge Sewerage Scheme | 1998
Lisdoonvarna Water Supply Stage 1 | 2001
Kilkishen Sewerage Scheme | 2002
Lisdoonvarna Sewerage Scheme | 2002
Newmarket on Fergus Water (Advance) | 2003
Gillogue Water Supply Serviced Land Initiative | 2007
Comment on this
548 Mr. Kirk asked the Minister for the Environment, Heritage and Local Government the water schemes completed and in planning in Counties Louth, Cavan and Monaghan since 1997, to date in 2007; and the investment made, and future allocation. [13835/07]
Comment on this
The Government has committed substantially increased funding for water services infrastructure over the past decade and again in the new National Development Plan (NDP). Some €3.7 billion was invested in new and upgraded water services infrastructure under NDP 2000-2006. €4.7 billion, an increase of 27%, has been provided under NDP 2007-2013. Real improvements being achieved on foot of this ongoing investment include:
Rapid progress in meeting targets under the EU Urban Wastewater Treatment Directive. Compliance with the end 2005 deadline for the provision of secondary treatment, which stood at 25% in 2000 had risen to some 90% at the end of 2006, with all remaining schemes needed to ensure full compliance included in the Water Services Investment Programme.
The extensive programme of wastewater treatment works has reduced the pollutant load from municipal discharges to rivers, lakes and sea (measured as Biochemical Oxygen Demand) by 45,000 tonnes per annum in a period of unprecedented economic and population growth.
Wastewater treatment capacity was increased since 1997 by an equivalent to the needs of a population of 3.3 million; the increase in drinking water treatment capacity over the same period was equivalent to the needs of a population of 1.2 million.
By the end of December 2006 of some 85,000 sites had been provided under the Serviced Land Initiative, with a further 100,000 sites at construction stage.
Massive investment under the Rural Water Programme has resulted in great progress in upgraded and renewed rural water supply systems and improved water quality in private group water schemes.
Overall, my Department is committing sufficient resources to ensure that the coverage and quality of the national water infrastructure will be able to fully meet current and anticipated demand in the future.
My Department provided a total of €175.72 million, €107.63 million and €68.38 million respectively to Counties Louth, Cavan and Monaghan under the Water Services Investment and Rural Water Programmes in the period 1997 to 2006. Major schemes completed during that period are set out in the following table. In addition, many more schemes, smaller in scale, were completed under the devolved Rural Water Programme, of which details may be obtained from the County Councils. Full details of currently approved major schemes in Counties Louth, Cavan and Monaghan, including the value of the investment proposed in each case, are set out in my Department's Water Services Investment Programme 2005-2007, which is available in the Oireachtas Library.
New Assessments of Needs were undertaken last year in response to the Department's request to all local authorities to review the needs for capital works in their areas and to prioritise their proposals on the basis of the assessments. The priorities adopted by the members of Louth, Cavan and Monaghan County Councils will be taken into account in the framing of the next phase of the Water Services Investment Programme.
Scheme | Year of Completion
Carlingford Sewerage Scheme | 2000
Clogherhead Water/Sewerage Scheme | 2000
Dunleer Sewerage Scheme | 2000
Dunleer Sewerage Scheme Phase 2 | 2000
Drogheda Main Drainage | 2001
Drogheda Water Supply | 2001
Dundalk Main Drainage | 2001
Greenhills W&S Serviced Land Initiative | 2001
Ardee Link Road Sewer | 2002
Mount Avenue Drainage | 2002
Dunleer/Mid-Louth RWSS Advance Works | 2004
Termonfeckin/Baltray Sewerage Rural Towns & Villages Initiative | 2004
Tulllyallen Sewerage Scheme — Serviced Land Initiative | 2006
Scheme | Year of Completion
Ballyconnell Sewerage | 1998
Virginia Sewerage | 1998
Ballyjamesduff Water | 2000
Cullies/Drumlark Sewerage Scheme — Serviced Land Initiative | 2000
Cootehill Sewerage Scheme | 2001
Bailieborough Regional Water Supply Stage 1 | 2001
Lough Gowna Village Sewerage Scheme — Rural Towns & Villages | 2001
Rathardrum, Dublin Rd. Virginia Serviced Land Initiative | 2001
Swellan Sewerage Scheme — Serviced Land Initiative | 2001
Tanderagee/Curkish Water & Sewerage | 2002
Bailieboro RWSS — Stage 2 | 2003
Redhills Sewerage Scheme — Rural Towns & Villages | 2006
Scheme | Year of Completion
Carrickmacross Sewerage (Improvement — Phase 2) | 1998
Castleblayney Water Supply Improvement Scheme | 1999
Monaghan Water Contract 1 — Pipelines | 1999
Carrickmacross- Convent Lands sewerage | 2000
Monaghan Water Supply | 2001
Tydavnet Sewerage (Reedbed) | 2001
Clones Water Scheme | 2003
Monaghan Town Sewerage (Peter’s Lake) | 2003
Comment on this
549 Mr. Kelly asked the Minister for the Environment, Heritage and Local Government the water schemes completed and in planning in Counties Longford and Westmeath since 1997, to date in 2007; and the investment made, and future allocation. [13836/07]
Comment on this
The Government has committed substantially increased funding for water services infrastructure over the past decade and again in the new National Development Plan (NDP). Some €3.7 billion was invested in new and upgraded water services infrastructure under NDP 2000-2006. €4.7 billion, an increase of 27%, has been provided under NDP 2007-2013. Real improvements being achieved on foot of this ongoing investment include:
Rapid progress in meeting targets under the EU Urban Wastewater Treatment Directive. Compliance with the end 2005 deadline for the provision of secondary treatment, which stood at 25% in 2000 had risen to some 90% at the end of 2006, with all remaining schemes needed to ensure full compliance included in the Water Services Investment Programme.
The extensive programme of wastewater treatment works has reduced the pollutant load from municipal discharges to rivers, lakes and sea (measured as Biochemical Oxygen Demand) by 45,000 tonnes per annum in a period of unprecedented economic and population growth.
Wastewater treatment capacity was increased since 1997 by an equivalent to the needs of a population of 3.3 million; the increase in drinking water treatment capacity over the same period was equivalent to the needs of a population of 1.2 million.
By the end of December 2006 of some 85,000 sites had been provided under the Serviced Land Initiative, with a further 100,000 sites at construction stage.
Massive investment under the Rural Water Programme has resulted in great progress in upgraded and renewed rural water supply systems and improved water quality in private group water schemes.
Overall, my Department is committing sufficient resources to ensure that the coverage and quality of the national water infrastructure will be able to fully meet current and anticipated demand in the future.
My Department provided a total of €22.92 million to County Longford and €62.01 million to Westmeath County Council under the Water Services Investment and Rural Water Programmes in the period 1997 to 2006. Major schemes completed during that period are set out in the following table. In addition, many more schemes, smaller in scale, were completed under the devolved Rural Water Programme, of which details may be obtained from the County Councils. Full details of currently approved major schemes in Counties Longford and Westmeath, including the value of the investment proposed in each case, are set out in my Department's Water Services Investment Programme 2005-2007, which is available in the Oireachtas Library.
New Assessments of Needs were undertaken last year in response to the Department's request to all local authorities to review the needs for capital works in their areas and to prioritise their proposals on the basis of the assessments. The priorities adopted by the members of Longford and Westmeath County Councils will be taken into account in the framing of the next phase of the Water Services Investment Programme.
Scheme | Year of Completion
Ardnacassa Scheme | 2000
Longford Water Conservation Scheme | 2000
Ballymahon Sewerage Scheme | 2001
Granard Sewerage Scheme | 2002
Clondra Sewerage Scheme — Rural Towns & Villages Initiative | 2006
Scheme | Year of Completion
Moate Sewerage Scheme | 1998
Tyrellspass Water Supply Scheme | 1998
Athlone Sewerage (Westbank) Scheme | 2000
Athlone Water (Annagh/Baylin) Supply Scheme | 2000
Coosan Athlone Surface Water Drainage Scheme | 2000
Athlone Water Conservation Scheme | 2001
Coosan Athlone Surface Water Drainage Scheme — Serviced Land Initiative | 2001
Mullingar/Marlinstown Sewerage Scheme — Serviced Land Initiative | 2001
Mullingar Water (Taughmon) Supply Scheme | 2001
Kinnegad Sewerage Extension Scheme | 2003
South Westmeath Regional Water Supply Scheme — Advance Works at Moate | 2003
Tyrellspass Sewerage Scheme — Serviced Land Initiative | 2004
Lough Owel Treatment Plant | 2005
Mullingar Regional Water Supply Scheme — South Western High Level Area | 2005
Comment on this
550 Mr. Ó Fearghaíl asked the Minister for the Environment, Heritage and Local Government the water schemes completed and in planning in County Kildare since 1997, to date in 2007; and the investment made, and future allocation. [13837/07]
Comment on this
The Government has committed substantially increased funding for water services infrastructure over the past decade and again in the new National Development Plan (NDP). Some €3.7 billion was invested in new and upgraded water services infrastructure under NDP 2000-2006. €4.7 billion, an increase of 27%, has been provided under NDP 2007-2013. Real improvements being achieved on foot of this ongoing investment include:
Rapid progress in meeting targets under the EU Urban Wastewater Treatment Directive. Compliance with the end 2005 deadline for the provision of secondary treatment, which stood at 25% in 2000 had risen to some 90% at the end of 2006, with all remaining schemes needed to ensure full compliance included in the Water Services Investment Programme.
The extensive programme of wastewater treatment works has reduced the pollutant load from municipal discharges to rivers, lakes and sea (measured as Biochemical Oxygen Demand) by 45,000 tonnes per annum in a period of unprecedented economic and population growth.
Wastewater treatment capacity was increased since 1997 by an equivalent to the needs of a population of 3.3 million; the increase in drinking water treatment capacity over the same period was equivalent to the needs of a population of 1.2 million.
By the end of December 2006 of some 85,000 sites had been provided under the Serviced Land Initiative, with a further 100,000 sites at construction stage.
Massive investment under the Rural Water Programme has resulted in great progress in upgraded and renewed rural water supply systems and improved water quality in private group water schemes.
Overall, my Department is committing sufficient resources to ensure that the coverage and quality of the national water infrastructure will be able to fully meet current and anticipated demand in the future.
My Department provided a total of €171.10 million to Kildare County Council under the Water Services Investment and Rural Water Programmes in the period 1997 to 2006. Major schemes completed during that period are set out in the following table. In addition, many more schemes, smaller in scale, were completed under the devolved Rural Water Programme, of which details may be obtained from the County Council. Full details of currently approved major schemes in County Kildare, including the value of the investment proposed in each case, are set out in my Department's Water Services Investment Programme 2005-2007, which is available in the Oireachtas Library.
New Assessments of Needs were undertaken last year in response to the Department's request to all local authorities to review the needs for capital works in their areas and to prioritise their proposals on the basis of the assessments. The priorities adopted by the members of Kildare County Council will be taken into account in the framing of the next phase of the Water Services Investment Programme.
Scheme | Year of Completion
Naas Water | 1997
Castledermot Water | 1998
Leixlip NE Kildare Water | 1998
Calverstown Sewerage Improvement | 2000
Castlecomer Road to Glendine Water Supply | 2000
Kilcullen Sewerage | 2000
Kildare/Rathangan Water Supply | 2000
Kilkenny East Environs | 2000
Kill Sewerage Improvement | 2000
Leixlip Sewerage | 2000
Monasterevin Water | 2000
Morristown, Newbridge Sewerage | 2000
Osberstown Sewerage | 2000
Prosperous Sewerage | 2000
Prosperous Water Improvement | 2000
Castletown Celbridge Pumping Station | 2001
Derrinturn Sewerage | 2001
Kildare Planning and Dev. of Phases 1A and 1B of Water Supply Strategy | 2001
Maynooth Pumping Station | 2001
Kilcock Water Improvement | 2002
Kilcullen Water | 2002
Nurney Water | 2002
Coill Dubh Sewerage Treatment Plant | 2003
Athy Sewerage (Nutrient Reduction) | 2004
Castledermot Water Stage 2 | 2004
Kildangan Sewerage Scheme | 2004
Monasterevin Sewerage | 2005
Monasterevin Sewerage Scheme | 2005
South Kildare Water Supply Scheme | 2005
Castledermot Sewerage Scheme — Sewer Network Contract | 2006
Monasterevin Sewerage Scheme (extension of Treatment Plant and attendant network improvements) | 2006
Allenwood Sewerage Scheme (construction of Treatment Olant and network) | 2006
Lower Liffey Valley Regional Sewerage Scheme — Straffan Sewerage Scheme (connection of Straffan to regional network sending waste to Leixlip Treatment Plant) | 2006