Dáil

Written Answers ›

Garda Stations

John O'Donoghue Deputy John O’Donoghue Question Fianna Fáil

50 Deputy John O’Donoghue asked the Minister for Finance the status of the new Castleisland Garda station that is being constructed; the way the project is proceeding; and if he will make a statement on the matter. [46223/10]

Comment on this
Dr Martin Mansergh Minister of State at the Department of Finance (Deputy Martin Mansergh) Fianna Fáil

The Contractor commenced works on site on 3 August 2010. I can confirm that works are progressing well with demolitions, site set and foundation for the main building all completed. The project has progressed and the form of the main building is now evident. It is expected that the project will be completed in the fourth quarter of 2011.