Schools Building Projects Status

407. Deputy Alan Shatter asked the Minister for Education and Skills in relation to the Dublin South constituency, the new works sanctioned for schools since 9 March 2011; the funding provided, to date, for such works; the schools that received such funding; the new schools, school buildings and-or school extensions completed from March 2011 to date in 2015; the works currently being undertaken, and works expected to commence within the next 12 months; the position regarding school projects for which sanction has been sought; the current stage in respect of each such project, and the schools concerned. [19248/15]

Comment on this
Jan O'Sullivan Minister for Education and Skills Labour Party

The records maintained by my Department in respect of large scale building projects are retained on a county basis. The first table provides a list of new schools and large scale extensions/refurbishments in Dublin that were completed in the period 2011 to 2014. The five year plan for new schools and large scale extensions was announced in March 2012 and information in respect of these schools is available on my Department's website and this information is updated on a monthly basis. The most recent updates to the appropriate files are included in the tables numbered 1 to 7. Under the Infrastructure and Capital Investment Framework 2012-2016 announced in November 2011, a total of €1.5 billion funding is assigned to the delivery of new schools and large scale extensions.

Ongoing Projects from 2014 - updated beginning June 2015

.

.

Announced 19th December 2011 : Projects to go to construction in 2012 - Current Status Updated beginning June 2015

"Investing in Infrastructure & Jobs" Package 2013 updated beginning June 2015

New Primary Schools completed 2011-2014

Large Scale Primary Extensions/Refurbishments completed 2011-2014

New Post-Primary Schools completed 2011-2014

Large Scale Post-Primary Extensions/Refurbishments completed 2011-2014

final table

Large Scale Primary Extensions/Refurbishments completed 2011-2014

New Post-Primary Schools completed 2011-2014

Large Scale Post-Primary Extensions/Refurbishments completed 2011-2014

table