Carillion school construction collapse

Summary

Deputies raised uncertainty for six schools and local subcontractors after Carillion entered liquidation. The Education Minister said the projects were about 90% complete and the NDFA expected limited delays while securing continuation of the work.

Yesterday we received the news that Carillion, the company that had won the tender to construct, maintain and manage six new schools in the State, had gone into voluntary liquidation. This has left huge fear in the schools among the teachers, principals, parents and children. Two of the schools - Coláiste Ráithín and St. Philomena's - happen to be located in my constituency. There has been a lot of uncertainty in recent months. Those involved in the schools were supposed to move into the new buildings - they are substantially completed - in October and November last year, but that date was pushed back to December. They were then due to move in on 22 January.

There is considerable uncertainty and fear. Christmas exams have been interrupted, we are heading into the mock exams period and additional teachers have been taken on in order to serve the schools in their new buildings. Will the Minister assure the House that the deadlines will be met, that the schools can move into their new premises and that whatever work is necessary will be completed so as to ensure a continuation of service?

Comment on this

Deputy Thomas Byrne on the same matter.

Comment on this

I endorse Deputy Brady's comments because people in Kells are concerned. Five schools are affected. However, an issue has reared its head in the years that these projects have been running, with subcontractors and local businesses in Kells in my constituency left short numerous times by contractors and other subcontractors above them. They are worried that this will become a major problem for them with Carillion going into liquidation.

Comment on this

The Deputies are correct in that one of the companies involved in the joint venture to build a number of PPP schools has gone into liquidation. At this point, the National Development Finance Agency, NDFA, is dealing with the remaining shareholder and has expressed confidence that there should not be significant delays in the execution of these projects given that they are 90% built. It must complete its discussions so as to ensure that the work continues. It should be mentioned that not only are the projects 90% built, but the State has not made any payment beyond a small element of site cost. The only way in which the value to the developer can be obtained is if the State issues the licences. The State is in a relatively strong position. The NDFA is dealing with this issue and is determined to ensure that there will be no disruption to the work.