Written answer

Schools Site Acquisitions

173. Deputy Brendan Ryan asked the Minister for Education and Skills further to Parliamentary Question No. 172 of 14 May 2019, if there has been further progress on the site acquisition; if a design team will be put in place for the three projects; the estimated timetable for the completion of the education campus; and if he will make a statement on the matter. [37085/19]

Comment on this

217. Deputy Brendan Ryan asked the Minister for Education and Skills further to Parliamentary Question No. 172 of 14 May 2019, if there has been further progress on the site acquisition; if a design team will be put in place for the three projects; the estimated timetable for the completion of the education campus; and if he will make a statement on the matter. [37301/19]

Comment on this
Joe McHugh Minister for Education and Skills Fine Gael

I propose to take Questions Nos. 173 and 217 together.

Agreement in principle has been reached with a landowner for the acquisition of a site at Donaghcumper, Celbridge. As previously advised, there are technical considerations crucial to the delivery of the site and my Department continues to engage with the landowner and Kildare County Council on these issues in order to enable architectural planning to commence.

I can assure the Deputy that it is a priority for my Department to commence the architectural planning process for this site at the earliest possible stage. For the time being, and as previously indicated - given the commercially sensitive nature of site acquisitions in general, I am unable to elaborate further.