Schools Building Projects Status

211. Deputy Brendan Ryan asked the Minister for Education and Skills further to Parliamentary Question No. 540 of 23 July 2019, if the letter of intent has issued; if a letter of acceptance has issued; when construction will commence on site; and if he will make a statement on the matter. [37293/19]

Comment on this
Joe McHugh Minister for Education and Skills Fine Gael

As the Deputy is aware, the delivery of the project for Naas Community College has been devolved to Kildare and Wicklow Education & Training Board (KWETB).

The project is still at tender stage and the Letter of Intent has not issued yet. It is expected that the project will commence construction towards the end of this year so that it will be completed before September 2021.