Schools Building Projects Status

238. Deputy Brendan Ryan asked the Minister for Education and Skills further to Parliamentary Question No. 174 of 17 September 2019, if tenders have now been invited for the project; the closing date for receipt of tenders; and if he will make a statement on the matter. [42258/19]

Comment on this
Joe McHugh Minister for Education and Skills Fine Gael

The major building project for the school referred to by the Deputy has recently completed Stage 2(b) of architectural planning and has been progressed to tender stage.

A tender stage normally takes between 7 and 8 months to complete.