Written answer
Schools Building Projects Data
236. Deputy John Curran asked the Minister for Education and Skills the details of each school that recently progressed to the next stage of architectural planning, stage 3 tender phase and that had previously been at stage 2B for a considerable period of time; and if he will make a statement on the matter. [53259/19]
Comment on this
The following spreadsheet details the 13 projects that have progressed from an advanced stage of architectural planning - Stage 2(b), Detailed Design to the next stage of architectural planning - Stage 3, Tender Stage since the start of the 2019/20 academic year.
Thereafter, a tender stage normally takes between 7 and 8 months to complete depending on the size and complexity of the project.