North-South interconnector route

Summary

Deputy Carthy argued the North-South interconnector should be undergrounded, citing an earlier report and landowner opposition to overhead pylons. The Tánaiste said the Government had secured reviews but EirGrid still says undergrounding is not feasible and the project has already been delayed.

A Government-commissioned report back in 2017 described the undergrounding of the North-South interconnector as feasible. Indeed, it said it was a credible option, but that part of the report has been ignored and, instead, EirGrid and the Government are proceeding with a plan to erect pylon-supported overhead power lines through five counties. EirGrid and its agents are currently trying to engage with landowners across counties Cavan, Monaghan and Meath but we are told that the overwhelming majority of landowners are refusing to engage. They are stating that they will not allow this infrastructure on their lands.

I want to put it on the record and to put the Tánaiste on notice that the current approach is going to lead to huge conflict with local communities and the inevitable delay of the North-South interconnector. Therefore, I ask the Tánaiste to adhere to his own party's pre-election commitments to take the concerns of landowners and local communities and force a rethink on this issue because otherwise this interconnector is not going to be developed anytime soon.

Comment on this

We did take that forward-----

Comment on this

No, the Government did not.

Comment on this

-----and we did ensure a rethink. There was a review.

Comment on this

There was a review of previous reviews.

Comment on this
Catherine Connolly An Leas-Cheann Comhairle Independent

We are not doing an interview on it.

Comment on this

There was a further review of previous reports. I am not sure the 2017 report is as clear as the Deputy has outlined in terms of undergrounding. EirGrid has been consistent in saying undergrounding is not feasible. We did ask for a review of that and we secured it from the Minister. We looked at what happens internationally, as well as the specifics of this case. The review has since been published. EirGrid is still engaging with farmers in the area. The project has been delayed for quite a long time. Issues will arise in that regard as well from an energy-security perspective. There are no easy answers to this right now.

Comment on this

The current approach is not working.

Comment on this

I am not sure what proposals will work.

Comment on this