Dáil
‹ Ceisteanna ar Pholasaí nó ar Reachtaíocht - Questions on Policy or Legislation

Children’s and maternity hospital procurement

Summary

Deputy Tóibín attacks overspends and tendering on the national children’s and maternity hospitals and asks for a review of the maternity hospital process. The Tánaiste blames design flaws, political delay and current systems, and rejects the idea that politicians should oversee every bill of quantities.

The overspend and the massive delay that exists in the national children's hospital exists because of the ill-defined, woolly confusion in that hospital contract. The contract for the national children's hospital was signed by the Taoiseach, Simon Harris, and it has proven to be a shambles. It has created an open chequebook for BAM. I have the bill of quantities for the tender for the national maternity hospital. It appears that the Government is again rushing to tender before the job is properly designed. It also appears that the bill of quantities for the national maternity hospital is as half-baked as the contract for the national children's hospital. I understand that there are only two companies now tendering for the mechanical elements of the national maternity hospital contract. It appears that the Government is heading for the same procurement car crash for the national maternity hospital that exists for the national children's hospital.

Comment on this

I thank the Deputy. The time is up.

Comment on this

The Government is incinerating taxpayers' money.

Comment on this

The time is up.

Comment on this

Will the Government review the tender process for the national maternity hospital, given the fiasco over the national children's hospital?

Comment on this

First, the question of definitive design has been raised in respect of the national children's hospital. The PwC report goes into considerable detail on errors and mistakes that were made at the time-----

Comment on this

They were signed off on.

Comment on this

-----in terms of the development of the national children's hospital and so on, and all of that. On the national maternity hospital, the delay was more on the political side in terms of getting that project off the ground.

Comment on this

That was your fault.

Comment on this

When you delay, you increase costs. We had a farcical debate in here on that question for far too long.

Comment on this

That is a different question.

Comment on this

It is relevant to costs, and the increased costs.

Comment on this

The question is about the bill of quantities.

Comment on this

It is ridiculous to suggest that politicians now have to oversee every bill of quantity in respect of every hospital that is going to be built.

Comment on this

They must make sure it is done right.

Comment on this

That is just ridiculous. Are we really going to get into the operational issues pertaining to the building of a hospital or a school?

Comment on this

We are out of time now.

Comment on this

We have systems and procedures.

Comment on this

They are not working.

Comment on this

We will change the procedures and the systems.

Comment on this

Not in this contract.

Comment on this

The idea that I will revise-----

Comment on this

The time is up.

Comment on this

-----the bill of quantities is just farcical. In my humble opinion, the agencies responsible need to do their job. They need to do it properly and effectively.

Comment on this

The buck stops with the Minister.

Comment on this

We have procedures here where we try to stick to a minute but nobody is paying any attention.

Comment on this

I apologise.