National children's hospital timeline

Summary

Deputy Bacik raises concerns arising from recent scrutiny of the national children's hospital, including the handover and delivery timeline. The Minister expresses confidence in the board, says it is managing a very difficult situation well, and urges support for the contractor-led process.

We are all aware of the terrible impact on children of long waiting lists, particularly for those with scoliosis and spina bifida.

As we head into flu season, all of us are thinking about healthcare and the health of our children, and we all know how much we need a new national children's hospital. Last week, the Minister for Health, Deputy Donnelly, and members of the board of the national children's hospital appeared before the health committee. In response to questions from my colleague Deputy Alan Kelly, some issues emerged which I wish to raise with the Minister. First, we understand there have been several design changes to the project since the Minister, Deputy Donnelly, said he agreed a handing-over date of June 2025. Second, we want to understand better the relationship between the board and the independent standing conciliator. At last week's meeting, the chair of the board said the board has no confidence in the standing conciliator. Third, we learned that the board signed off on continuous professional development courses for senior executives on the project. As the Minister for public expenditure and national development plan delivery, does the Minister still have confidence in the board and does he believe the hospital will be handed over in June 2025, the date we are currently being told is likely?

Comment on this

I very much support the board and the work it is doing and I have confidence it is managing a very difficult situation on our behalf well. It is making the kinds of demands and putting in place the kinds of arrangements that taxpayers and the children of Ireland deserve. Yes, I expect we will see the hospital handover at that point but I know also, given all the difficulty we have had, that it is important we support the board in ensuring the timeline and deadline are observed. The work of the board is central to that and I support it in its efforts, particularly with regard to the contractor.