Road Projects

277. Deputy Séamus McGrath asked the Minister for Transport for a full update on the M28 Road project, Rochestown to Ringaskiddy motorway; the estimated timeline for the appointment of the main contractor; and the commencement of work and anticipated completion date of the overall project. [1790/25]

Comment on this
Eamon Ryan Minister for Transport

As Minister for Transport, I have responsibility for overall policy and exchequer funding in relation to the National Roads Programme. Under the Roads Acts 1993-2015 and in line with the National Development Plan (NDP), the planning and construction of individual national roads is a matter for Transport Infrastructure Ireland (TII), in conjunction with the local authorities concerned. This is also subject to the Infrastructure Guidelines and the necessary statutory approvals. In this context, TII is best placed to advise you on the latest status of this project.

Appointment of the main contractor and commencement of work is subject to Government Consent to award the contract under the Infrastructure Guidelines. In that regard, the final business case was submitted to the Department of Transport on December 20th.

Noting the above position, I have referred your question to TII for a direct reply updating you as to the latest status of the project. Please advise my private office if you do not receive a reply within 10 working days.