Departmental Expenditure

1425. Deputy Malcolm Byrne asked the Minister for Health the cost to date of work relating to the construction of the National Children’s Hospital; to indicate a timetable for opening; and if he will make a statement on the matter. [46797/24]

Comment on this
Stephen Donnelly Minister for Health

In February 2024, Government approved enhanced capital and current budget sanctions for the New Children’s Hospital (NCH) project and programme, bringing the total approved budget to €2.24billion.

Included in this is the capital budget of €1.88 billion for designing, building and equipping the NCH and the two satellite centres. A separate €362 million budget is for the programme of integration and transition of services to the NCH from the three existing children’s hospitals, including commissioning, ICT, and the Electronic Health Record system.

The timely completion of the NCH is a government priority. Everything possible is being done to ensure the project is completed as soon as possible on behalf of children, young people and their families.

The two satellite centres, which represent major milestones in the programme, are open and delivering the new model of care. Construction has advanced to over 94% complete against contract value. The project is now in the construction completion (‘snagging’ and ?nishing) phase, with the fit out of rooms and installation of fixed medical equipment and integrated building technical commissioning well underway.

The substantial completion of NCH is informed by the contractor’s programme of works and its ability to meet the targets set out in its own programme.

The National Paediatric Hospital Development Board (NPHDB) advised that BAM Ireland has submitted an updated programme underpinning its intention to complete the construction and fit out of the NCH by June 2025 . On 2 December 2024, after reviewing the updated programme and its further revisions, the Employer’s Representative- the independent third party responsible for administration of the contract- deemed the programme to be compliant with the requirements of the contract.

NPHDB is continuing to use the full extent of levers available to it under the contract to hold BAM to its new commitment of substantially completing the hospital by June 2025.

Once substantial completion is achieved, the hospital will be handed over to Children’s Health Ireland (CHI) for a post substantial completion operational commissioning period of at least 6 months.

To ensure operational commissioning is achieved as close to 6 months as possible, the NPHDB and CHI are engaging closely with BAM to secure 3 months early access to certain areas of the hospital, prior to substantial completion.

Ahead of the transition to the new facilities, a significant body of work is ongoing to integrate the three hospitals from a clinical, operational, and cultural perspective.

While much focus has been on the challenges faced by the project, it is important to note that once open, the NCH will provide world class facilities to its patients. The NCH is unprecedented in scale, facilities, and technological advancement. It will be transformational in how we treat and deliver care to children and their families. The hospital has been designed and constructed to be as enduring and adaptable as possible. It is a building for the next 75-100 years, rather than the 40-50 years of other hospitals internationally.