Written answer
Departmental Expenditure
1426. Deputy Malcolm Byrne asked the Minister for Health the cost to date of work relating to the construction of the planned National Maternity Hospital; to indicate a timetable for opening; and if he will make a statement on the matter. [46798/24]
Comment on this
In July 2023, Cabinet gave its approval for the new National Maternity Hospital (NMH) at Elm Park, co-located with St Vincent’s University Hospital (SVUH), to proceed to tender for a main contractor to construct the new hospital in line with EU and national requirements.
The main tender process, which began in September 2023, is programmed to run over a period of c.18 months.
The budget for the main construction works is subject to the outcome of this tender process, the selection of the most economically advantageous tenderer(s), and the subsequent updating of the final business case for Government approval to proceed. It is expected that construction of the hospital will commence later this year and be completed in 2029.
Construction Costs to date:
A series of works were initially carried out to de-risk the campus in advance of the construction works for the new hospital and as part of the ongoing investment in our legacy health estate to address the risks on acute hospital campuses. This included enabling works, decanting, junction upgrades, and prevention works, some of which were specific planning requirements. As part of the SVUH Campus Development Plan a new pharmacy facility and extension to the existing multi storey carpark were completed in 2021.
In parallel to the ongoing tender and procurement process, and in order to construct the proposed NMH development as a single-phase development and de-risk the future site as much as possible, a number of buildings are required to be completed in advance of the commencement of the main NMH works. This will enable the decant of existing facilities away from the footprint of the new NMH and improve campus-wide resilience in terms of mechanical and electrical energy for both SVUH and the new NMH.
Construction commenced on these works in December 2023. It is expected that these enabling works and the main tender process will both be completed in tandem by mid-2025. The overall spend to date on these enabling works, and important projects in their own right, is €124m.