299. Deputy William Aird asked the Minister for Public Expenditure, Infrastructure, Public Service Reform and Digitalisation the timeline for the completion of the new Garda station in Portlaoise; and if he will make a statement on the matter. [50078/26]

Comment on this
Kevin Boxer Moran Minister of State at the Department of Public Expenditure, Infrastructure, Public Service Reform and Digitalisation Independent

Construction works to renovate and extend Portlaoise Garda station commenced in Q4 2024. In accordance with the terms of the Construction Contract, it is anticipated that these works will reach Substantial Completion in Q1 2027.

Thereafter, An Garda Síochána will carry out, directly, the installation and commissioning of final fittings and equipment before the building and site can be returned to use.